Substation Scout

Mount Vernon

Named in 2 PJM planning documents for 2 projects, from October 18, 2024 to November 15, 2024.

Existingdescribed as
AEPzone
69kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
AEP Transmission Zone: Baseline Mount Vernon 69kV A and S CB Replacements
b3892.1
Not printed $2.0M 6/1/2026 Not printed 2024-11-15
SRRTEP Western
AEP Transmission Zone: Baseline Mount Vernon 69kV A and S CB Replacements Not printed $2.0M 6/1/2026 Not printed 2024-10-18
SRRTEP Western

Every mention

DateDocumentProjectWhat the document says about it
2024-11-15 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 23
AEP Transmission Zone: Baseline Mount Vernon 69kV A and S CB Replacements “Replace over duty Mount Vernon 69kV circuit breakers A and S”
69kV
2024-10-18 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 21
AEP Transmission Zone: Baseline Mount Vernon 69kV A and S CB Replacements “Replace over duty Mount Vernon 69kV circuit breakers A and S”
69kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.