Substation Scout

Milford

Named in 2 PJM planning documents for 2 projects, from November 6, 2024 to December 3, 2024.

Existingdescribed as
DPLzone
—kV as printed
2mentions

Also printed as: Milford Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Milford and Cedar Creek Facility Upgrades
b3866.1
Not printed $0.200M 12/31/2029 Not printed 2024-12-03
TEAC
Milford and Cedar Creek Facility Upgrades Not printed $0.200M 12/31/2029 Not printed 2024-11-06
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2024-12-03 TEAC
Item 11 - Reliability Analysis Update p. 40
Milford and Cedar Creek Facility Upgrades “Adjust relay setting at Milford (Cedar Creek – Milford) Substation”
2024-11-06 TEAC
Item 13 - Reliability Analysis Update p. 40
Milford and Cedar Creek Facility Upgrades “Adjust relay setting at Milford Substation”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.