Substation Scout

Ottawa

Named in 8 PJM planning documents for 6 projects, from November 6, 2024 to October 6, 2026.

Existingdescribed as
ATSIzone
138 kVkV as printed
8mentions

Also printed as: Ottawa Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Lakeview-Ottawa 138 kV Line
b3978.1
Not printed $1.41M 6/1/2030 Not printed 2025-11-14
SRRTEP Western
Cluster 2 (ATSI) Not printed Not printed Not printed Not printed 2024-11-06
TEAC
Rebuild/Reconductor existing 138 kV lines/Terminal upgrades at 345 kV substations Not printed 265.1 Not printed Not printed 2024-11-19
TEAC
Lakeview-Ottawa 138 kV Line Not printed $1.41M 6/1/2030 Not printed 2025-10-17
SRRTEP Western
Lemoyne Substation Upgrades for MISO Tranche 2.1
ATSI-2025-004 · s3844.1
Not printed $100.86M 6/1/2032 Not printed 2026-10-06
TEAC
Toussaint 138 kV Substation
ATSI-2026-014
Not printed Not printed Not printed 25 MW 2026-01-16
SRRTEP Western

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate $15.6 M → $100.86 M 2025-03-04 2025-12-08
Substations named LAPLAISANCE CREEK; LEMOYNE; MAJESTIC; MAPLE → LEMOYNE 2025-02-04 2025-03-04
Substations named LEMOYNE → GREENFIELD; LAKEVIEW; LEMOYNE; OTTAWA 2025-03-04 2025-12-08
Substations named GREENFIELD; LAKEVIEW; LEMOYNE; OTTAWA → GREENFIELD; LEMOYNE; OTTAWA 2025-12-08 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - ATSI Local Plan Submission of the Supplemental Projects for 2026 p. 19
Lemoyne Substation Upgrades for MISO Tranche 2.1 “At Ottawa Substation: Convert the ring bus configuration to breaker and a half by installing three circuit breakers and associated disconnects.”
2026-09-23* SRRTEP Western
ATSI local plan submission of the supplemental projects for 2026 RTEP p. 19
Lemoyne Substation Upgrades for MISO Tranche 2.1 “At Ottawa Substation: Convert the ring bus configuration to breaker and a half”
2026-01-16 SRRTEP Western
Item 04 - ATSI Supplemental Projects p. 14
Toussaint 138 kV Substation No role wording
138 kV
2025-12-08 TEAC
Item 04 - ATSI Supplemental Projects p. 4
Lemoyne Substation Upgrades for MISO Tranche 2.1 “At Ottawa Substation: Convert the ring bus configuration”
138 kV
2025-11-14 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 13
Lakeview-Ottawa 138 kV Line “Reconductor 1 span of transmission line outside Ottawa Substation”
2025-10-17 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 7
Lakeview-Ottawa 138 kV Line “transmission line outside Ottawa Substation”
138 kV
2024-11-19 TEAC
Item 1 - Reliability Analysis Update p. 32
Rebuild/Reconductor existing 138 kV lines/Terminal upgrades at 345 kV substations “Reconductor 1 span from Ottawa substation”
138 kV
2024-11-06 TEAC
Item 13 - Reliability Analysis Update p. 58
Cluster 2 (ATSI) “Reconductor 1 span from Ottawa substation”
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this