Named in 3 PJM planning documents for 3 projects, from October 18, 2024 to February 13, 2026.

Not stateddescribed as
AEPzone
34.5kVkV as printed
3mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
AEP Transmission Zone: Baseline Greenleaf Cap Bank
b3873.1
Not printed $1.314M 6/1/2029 Not printed 2024-11-15
SRRTEP Western
AEP Transmission Zone: Baseline Greenleaf Cap Bank Not printed $1.314M 6/1/2029 Not printed 2024-10-18
SRRTEP Western
AEP Transmission Zone M-3 Process Greenleaf, IN/Conant, IN/Elkhart Hydro, IN/Osolo, IN /Dunlap, IN/East Elkhart, IN/Wyland SS, IN /Middleton Run SS, IN/Middlebury, IN/Parkway, IN
AEP-2023-IM003, AEP-2023-IM005
Conceptual $20.647 M 09/01/2028 Not printed 2026-02-13
SRRTEP Western

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named CONANT; DUNLAP; EAST ELKHART; ELKHART HYDRO; GREENLEAF; MIDDLEBURY TAP; MIDDLETON RUN SS; OSOLO; PARKWAY TAP; WYLAND SS → CONANT; DUNLAP; EAST ELKHART; ELKHART HYDRO; GREENLEAF; MIDDLETON RUN SS; OSOLO; WYLAND SS 2026-10-06 Not reported
Substations named CONANT; DUNLAP; EAST ELKHART; ELKHART HYDRO; GREENLEAF; MIDDLEBURY; MIDDLETON RUN SS; OSOLO; PARKWAY; WYLAND SS → CONANT; DUNLAP; EAST ELKHART; ELKHART HYDRO; GREENLEAF; MIDDLEBURY TAP; MIDDLETON RUN SS; OSOLO; PARKWAY TAP; WYLAND SS 2026-02-13 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-02-13 SRRTEP Western
Item 02 - AEP Supplemental Projects p. 8
AEP Transmission Zone M-3 Process Greenleaf, IN/Conant, IN/Elkhart Hydro, IN/Osolo, IN /Dunlap, IN/East Elkhart, IN/Wyland SS, IN /Middleton Run SS, IN/Middlebury, IN/Parkway, IN No role wording
2024-11-15 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 26
AEP Transmission Zone: Baseline Greenleaf Cap Bank No role wording
34.5kV
2024-10-18 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 25
AEP Transmission Zone: Baseline Greenleaf Cap Bank No role wording
34.5kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.