Bergen

Named in 2 PJM planning documents for 2 projects, from November 14, 2024 to October 16, 2025.

Existingdescribed as
PSEGzone
138 kV, 138kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Bergen 138 kV series reactors
b3869.1
Not printed $12.5 M 9/1/2027 Not printed 2024-11-14
SRRTEP Mid-Atlantic
Bergen 138 kV series reactors
b3869.3
Not printed $12.77M 9/1/2027 Not printed 2025-10-16
SRRTEP Mid-Atlantic

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate
prior value printed on the same page
$12.5 M → $12.77M 2025-10-16 2025-10-16

Every mention

DateDocumentProjectWhat the document says about it
2025-10-16 SRRTEP Mid-Atlantic
Item 02 - SRRTEP Mid-Atlantic - Reliability Analysis Update p. 43
Bergen 138 kV series reactors “Replaced the two (2) Bergen 138kV Series Reactors with two (2) new dry type 138kV Series Reactors”
138 kV
2024-11-14 SRRTEP Mid-Atlantic
Item 01 - SRRTEP Mid-Atlantic - Reliability Analysis Update p. 9
Bergen 138 kV series reactors “Relocate the Bergen Gen #1 point of interconnection from Bergen 138kV to Bergen 345kV GIS”
138kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.