Substation Scout

Hunterstown

Named in 1 PJM planning document for 1 project, on November 6, 2024.

Not stateddescribed as
PPLzone
500 kVkV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
PPL Transmission Zone: Baseline
2024-W1-935
Not printed Not printed 6/1/2029 Not printed 2024-11-06
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2024-11-06 TEAC
Item 13 - Reliability Analysis Update p. 51
PPL Transmission Zone: Baseline No role wording
500 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.