Substation Scout

Bokes Creek

Named in 3 PJM planning documents for 3 projects, from November 19, 2024 to January 7, 2025.

Not stateddescribed as
AEPzone
345 kV, 345kVkV as printed
3mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Clusters AEP- 3, 4, 5
b3919.1
Not printed $145.494 M 12/31/2028 1.4GW 2025-01-07
TEAC
Maliszewski 765/345 kV Upgrades Not printed 145.494 Not printed Not printed 2024-11-19
TEAC
Clusters AEP- 3, 4, 5
2024-W1-408
Not printed $145.494 12/31/2028 1115MW 2024-12-03
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2025-01-07 TEAC
Item 12 - Reliability Analysis Update p. 45
Clusters AEP- 3, 4, 5 No role wording
345 kV
2024-12-03 TEAC
Item 11 - Reliability Analysis Update p. 67
Clusters AEP- 3, 4, 5 No role wording
345 kV
2024-11-19 TEAC
Item 1 - Reliability Analysis Update p. 30
Maliszewski 765/345 kV Upgrades No role wording
345kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this