Chandler Sub

Named in 3 PJM planning documents for 2 projects, from November 6, 2024 to October 8, 2025.

Newdescribed as
DOMzone
230 kV, 230kVkV as printed
5mentions

Described as new: “Connect the new substation” — source, page 14

Also printed as: Chandler Substation · Chandler

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Chandler 230kV Delivery - DEV
DOM-2024-0082 · s 3682
Conceptual $20.8M Q2 2028 112 MW 2025-10-08
TEAC
McDevitt 230kV Delivery - DEV
DOM-2024-0083 · s3683
Conceptual $19.8M Q2 2028 118 MW 2025-10-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date 10/15/2027 → Q2 2028 2024-11-06 2025-02-04
Substations named CHANDLER → CHANDLER; PALOMINO 2024-11-06 2025-02-04
In-service date 10/15/2027 → Q2 2028 2024-11-06 2025-02-04
Substations named MCDEVITT → CHANDLER; MCDEVITT 2024-11-06 2025-02-04

Every mention

DateDocumentProjectWhat the document says about it
2025-10-08 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2025 p. 42
Chandler 230kV Delivery - DEV “new 230 kV delivery point (Chandler Sub)”
230 kV
2025-10-08 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2025 p. 45
McDevitt 230kV Delivery - DEV “future Chandler Substation”
230kV
2025-02-04 TEAC
Item 11 - Dominion Supplemental Projects p. 14
Chandler 230kV Delivery - DEV “Connect the new substation”
230kV
2025-02-04 TEAC
Item 11 - Dominion Supplemental Projects p. 16
McDevitt 230kV Delivery - DEV “feed from future Chandler Substation”
2024-11-06 TEAC
Item 12 - Dominion Supplemental Projects p. 10
Chandler 230kV Delivery - DEV “new 230 kV delivery point (Chandler Sub)”
230 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.