ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Penhorn to Union City 69 kV
b3868.1
Not printed $46 M 6/1/2029 Not printed 2024-11-14
SRRTEP Mid-Atlantic

Every mention

DateDocumentProjectWhat the document says about it
2024-11-14 SRRTEP Mid-Atlantic
Item 01 - SRRTEP Mid-Atlantic - Reliability Analysis Update p. 8
Penhorn to Union City 69 kV No role wording