Parr Run

Named in 6 PJM planning documents for 3 projects, from October 18, 2024 to October 6, 2026.

Existingdescribed as
APSzone
138 kVkV as printed
6mentions

Also printed as: Parr Run Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Misoperation Relay Projects
APS-2024-085, -86, -089, -090
Not printed Not printed Not printed Not printed 2024-10-18
SRRTEP Western
Misoperations Relays
APS-2024-086 · s3934.1
Not printed $4.67 M 12/31/2028 Not printed 2026-10-06
TEAC
Junction – Parr Run 138 kV
APS-2024-096
Conceptual $35M 06/16/2028 Not printed 2025-12-12
SRRTEP Western

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named JUNCTION; NORTH SHENANDOAH; OAK MOUND; PAGE; PARR RUN; QUIET DELL; TILTONSVILLE; WINDSOR → NORTH SHENANDOAH; PAGE 2024-10-18 2026-04-15
Substations named JUNCTION; PARR RUN → JUNCTION; KELSO GAP; PARR RUN 2024-11-15 2025-12-12

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2026 p. 79
Misoperations Relays “At Parr Run Substation: Replace substation conductor, circuit breaker, disconnect switches, line trap, PT, CCVT, and relaying.”
138 kV
2026-09-28* SRRTEP Western
APS local plan submission of the supplemental projects for 2026 RTEP p. 79
Misoperations Relays “At Parr Run Substation: Replace substation conductor”
2026-07-17 SRRTEP Western
Item 02 - APS Supplemental Projects p. 9
Misoperations Relays “At Parr Run Substation: Replace substation conductor, circuit breaker, disconnect switches, line trap, PT, CCVT, and relaying.”
2025-12-12 SRRTEP Western
Item 14 - APS Supplemental Projects p. 6
Junction – Parr Run 138 kV No role wording
138 kV
2024-11-15 SRRTEP Western
Item 05 - APS Supplemental projects p. 11
Junction – Parr Run 138 kV No role wording
138 kV
2024-10-18 SRRTEP Western
Item 03 - APS Supplemental projects p. 4
Misoperation Relay Projects No role wording
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.