Tiltonsville
Named in 2 PJM planning documents for 2 projects, from October 18, 2024 to November 15, 2024.
Existingdescribed as
AEPzone
138 kVkV as printed
2mentions
Also printed as: Tiltonsville station
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| AEP Transmission Zone: Baseline
Tiltonsville Upgrades b3889.1 |
Not printed | $0.8M | 4/1/2029 | Not printed | 2024-11-15 SRRTEP Western |
| AEP Transmission Zone: Baseline Tiltonsville Upgrades | Not printed | $0.8M | 4/1/2029 | Not printed | 2024-10-18 SRRTEP Western |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2024-11-15 | SRRTEP Western Item 01 - SRRTEP West - Reliability Analysis Update p. 41 |
AEP Transmission Zone: Baseline Tiltonsville Upgrades | “Replace limiting station equipment at Tiltonsville station” 138 kV |
| 2024-10-18 | SRRTEP Western Item 01 - SRRTEP West - Reliability Analysis Update p. 40 |
AEP Transmission Zone: Baseline Tiltonsville Upgrades | “Replace limiting station equipment at Tiltonsville station” 138 kV |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.