Substation Scout

Lime Kiln

Named in 12 PJM planning documents for 9 projects, from October 8, 2024 to October 6, 2026.

Existingdescribed as
APSzone
230 kVkV as printed
20mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Sage 230 kV Customer Load Increase
APS-2023-017 · s3152.1
Not printed $1.5M 10/01/2025 576 MW 2024-10-08
TEAC
Doubs – Sage 230 kV New Customer
APS-2023-029 · s3150.2
Not printed $23.2M 12/31/2025 approximately 300 MW 2025-10-08
TEAC
New Customer
APS-2023-029 (s3150.1, s3150.2) · s3150.2
Not printed $23.2M 12/31/2025 approximately 300 MW 2026-09-08*
SRRTEP Western
Doubs – Lime Kiln 230 kV #231 Line New Customer
APS-2023-031 · s3153.1
Not printed $28.7M 12/31/2025 360 MW 2024-10-08
TEAC
Misoperation Relay Projects
APS-2024-002, APS-2024-003, APS-2024-004 · s3353.1, s3354.1, s3355.1
Not printed Not printed Not printed Not printed 2024-10-08
TEAC
Misoperation Relay Projects
APS-2024-058 · s3541.1
Not printed $9.20 10/31/2026 Not printed 2025-10-08
TEAC
Lime Kiln – Montgomery 230 kV Line
APS-2024-091
Conceptual $73.5 M 12/13/2030 Not printed 2026-10-06
TEAC
Doubs - Lime Kiln 230 kV Line
APS-2025-021
Conceptual $63.16 M 09/23/2032 Not printed 2026-02-03
TEAC
New Customer Connection
APS-2026-041
Conceptual $54.99M 11/08/2032 1000 MW 2026-09-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate $23.2M → $20.8M 2025-10-08 Not reported
Cost estimate $20.8M → $8M Not reported Not reported
Cost estimate
prior value printed on the same page
$20.8M → 23.2M 2025-01-07 2025-01-07
Cost estimate $20.8M → 23.2M 2024-10-08 2025-01-07
In-service date 12/31/2025 → 09/01/2025 2025-10-08 Not reported
In-service date 09/01/2025 → 12/31/2027 Not reported Not reported
In-service date 09/01/2025 → 12/31/2025 2024-10-08 2025-01-07
Substations named DOUBS; LIME KILN; QUANTUM 400; SAGE → DOUBS; QUANTUM 400; SAGE Not reported Not reported
Substations named BELMONT; LIME KILN; MONOCACY; PLEASANTS UNIT 1; PLEASANTS UNIT 2 → BELMONT; LIME KILN; MONOCACY 2024-10-08 Not reported
Cost estimate 36.75 → $63.16 M 2025-11-04 2026-02-03
In-service date 09/2030 → 02/18/2032 2025-09-09 2025-11-04
In-service date 02/18/2032 → 09/23/2032 2025-11-04 2026-02-03
Substations named DOUBS; LIME KILN → DOUBS; LIME KILN; QUANTUM 300; SAGE 2025-09-09 2025-11-04
Substations named DOUBS; LIME KILN; QUANTUM 300; SAGE → DOUBS; LIME KILN; MANOR WOODS; QUANTUM 300; SAGE 2025-11-04 2026-02-03
In-service date 12/31/2032 → 11/08/2032 2026-07-07 2026-09-08

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Item 07 - APS Supplemental Projects - Presentation p. 11
Lime Kiln – Montgomery 230 kV Line “At Lime Kiln and Montgomery substations: remove wave trap, upgrade circuit breakers”
230 kV
2026-09-08 TEAC
Item 05 - APS Supplemental Projects p. 8
New Customer Connection No role wording
230 kV
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2024 RTEP p. 5
Sage 230 kV Customer Load Increase No role wording
230 kV
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2024 RTEP p. 7
Doubs – Sage 230 kV New Customer “Modify line relay settings at Doubs and Lime Kiln substations”
230 kV
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2024 RTEP p. 88
Misoperation Relay Projects “At Lime Kiln, replace wave trap, substation conductor and relaying”
230 kV
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2024 RTEP p. 9
Doubs – Lime Kiln 230 kV #231 Line New Customer “Modify relay settings in Doubs and Lime Kiln substations”
230 kV
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2025 RTEP p. 17
New Customer “Modify line relay settings at Doubs and Lime Kiln substations”
230 kV
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2025 RTEP p. 4
Misoperation Relay Projects “At Lime Kiln, replace CVT on bus”
230 kV
2026-07-07 TEAC
Item 06 - APS Supplemental Projects p. 3
New Customer Connection No role wording
230 kV
2026-02-03 TEAC
Item 04 - APS Supplemental Projects p. 3
Doubs - Lime Kiln 230 kV Line No role wording
230 kV
2025-11-04 TEAC
Item 04 - APS Supplemental Projects - Version 7 p. 11
Doubs - Lime Kiln 230 kV Line No role wording
230 kV
2025-10-08 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2025 p. 17
Doubs – Sage 230 kV New Customer “Modify line relay settings at Doubs and Lime Kiln substations”
230 kV
2025-10-08 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2025 p. 4
Misoperation Relay Projects “At Lime Kiln, replace CVT on bus, substation conductor and relaying”
230 kV
2025-09-09 TEAC
Item 05 - APS Supplemental Projects p. 3
Doubs - Lime Kiln 230 kV Line No role wording
230 kV
2025-01-07 TEAC
Item 05 - APS Supplemental Project p. 7
Doubs – Sage 230 kV New Customer “Modify line relay settings at Doubs and Lime Kiln substations”
230 kV
2024-11-06 TEAC
Item 04 - APS Supplemental Projects p. 5
Lime Kiln – Montgomery 230 kV Line No role wording
230 kV
2024-10-08 TEAC
Informational Only - APS Local Plan submission of supplemental project 2024 p. 5
Sage 230 kV Customer Load Increase No role wording
230 kV
2024-10-08 TEAC
Informational Only - APS Local Plan submission of supplemental project 2024 p. 7
Doubs – Sage 230 kV New Customer “Modify line relay settings at Doubs and Lime Kiln substations”
230 kV
2024-10-08 TEAC
Informational Only - APS Local Plan submission of supplemental project 2024 p. 88
Misoperation Relay Projects “At Lime Kiln, replace wave trap, substation conductor and relaying”
2024-10-08 TEAC
Informational Only - APS Local Plan submission of supplemental project 2024 p. 9
Doubs – Lime Kiln 230 kV #231 Line New Customer “Modify relay settings in Doubs and Lime Kiln substations”
230 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this