Richlands
Named in 4 PJM planning documents for 3 projects, from October 8, 2024 to November 15, 2024.
Existingdescribed as
AEPzone
69kVkV as printed
4mentions
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| AEP Transmission Zone: Baseline
Richlands Cap 69kV Bank Installation b3876.1 |
Not printed | $1.0M | 12/1/2029 | Not printed | 2024-11-15 SRRTEP Western |
| AEP Transmission Zone: Baseline Richlands Cap 69kV Bank Installation | Not printed | $1.0M | 12/1/2029 | Not printed | 2024-10-18 SRRTEP Western |
| Buchanan County & Tazewell County, VA AEP-2021-AP014 · s3135.1-.5 |
Not printed | $29.2 M | 10/30/2027 | Not printed | 2024-10-08 TEAC |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-09-08* | SRRTEP Western AEP local plan submission of the supplemental projects for 2024 RTEP p. 45 |
Buchanan County & Tazewell County, VA | “Remote end work at Richlands substation” |
| 2024-11-15 | SRRTEP Western Item 01 - SRRTEP West - Reliability Analysis Update p. 31 |
AEP Transmission Zone: Baseline Richlands Cap 69kV Bank Installation | “Install a 69kV 11.5MVar capacitor bank at Richlands station
with a circuit switcher.” 69kV |
| 2024-10-18 | SRRTEP Western Item 01 - SRRTEP West - Reliability Analysis Update p. 29 |
AEP Transmission Zone: Baseline Richlands Cap 69kV Bank Installation | “Install a 69kV 11.5MVar capacitor bank at Richlands station
with a circuit switcher.” 69kV |
| 2024-10-08 | TEAC Informational Only - AEP Local Plan submission of supplemental projects 2024 p. 45 |
Buchanan County & Tazewell County, VA | “Remote end work at Richlands substation” 69kV |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.