Delco Tap

Named in 2 PJM planning documents for 2 projects, from November 6, 2024 to December 3, 2024.

Not stateddescribed as
ACEzone
—kV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Delco Tap – Mickleton Facility Upgrades
b3867.1
Not printed $1.03M 06/01/2029 Not printed 2024-12-03
TEAC
Delco Tap – Mickleton Facility Upgrades Not printed $1.03M 06/01/2029 Not printed 2024-11-06
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2024-12-03 TEAC
Item 11 - Reliability Analysis Update p. 39
Delco Tap – Mickleton Facility Upgrades No role wording
2024-11-06 TEAC
Item 13 - Reliability Analysis Update p. 39
Delco Tap – Mickleton Facility Upgrades No role wording