Each row is one PJM document naming substations for one project, newest first. Atom feed

Latest · October 2026 (547) · September 2026 (830) · August 2026 (58) · July 2026 (80) · June 2026 (64) · May 2026 (90) · April 2026 (85) · March 2026 (71) · February 2026 (74) · January 2026 (69) · December 2025 (82) · November 2025 (156) · October 2025 (355) · September 2025 (219) · August 2025 (33) · July 2025 (40) · June 2025 (34) · May 2025 (41) · April 2025 (50) · March 2025 (56) · February 2025 (63) · January 2025 (42) · December 2024 (89) · November 2024 (138) · October 2024 (496)

DateDocumentProjectSubstations namedAs printed
2025-04-11 SRRTEP Western
Item 01 - Reliability Analysis Update p. 3
Warfordsburg Capacitor Bank
b3773
Cherry Run
McConnellsburg
Morgan
Warfordsburg
Cost $3.05M
In service 6/1/2027
2025-04-11 SRRTEP Western
Item 02 - DEOK Supplemental Projects p. 3
Front Street
DEOK-2024-007
Front Street New
West End
Status Engineering
Cost $41,915,473
In service 01-22-2030
2025-04-11 SRRTEP Western
Item 03 - EKPC Supplemental Projects p. 3
Cynthiana, KY/Renaker, KY
EKPC-2025-002
Cynthiana Junction
KU’s EK Cynthiana T New
Renaker
Status Engineering
Cost $8.9 M
In service 06/30/2026
2025-04-11 SRRTEP Western
Item 04 - AEP Supplemental Projects p. 3
AEP Transmission Zone M-3 Process Kalamazoo, MI
AEP-2025-IM004
Kalamazoo
Moore Park
In service 7/1/2026
Load 13.84MW
2025-04-11 SRRTEP Western
Item 04 - AEP Supplemental Projects p. 5
AEP Transmission Zone M-3 Process New Carlisle Customer Needs
AEP-2023-IM020
Creek Walker
Edison
Fillmore Road New
Olive
Status Scoping (Conceptual)
Cost $30.463 M
In service 05/09/2028
Load 90 MW
2025-04-11 SRRTEP Western
Item 05 - ATSI Supplemental Project p. 3
Grand River – Leroy Center No. 1 138 kV Line
ATSI-2025-003
Grand River
Leroy Center
Nursery Substation
Load 135 MW
2025-04-11 SRRTEP Western
Item 05 - ATSI Supplemental Project p. 4
New Customer Connection
ATSI-2025-013
Crossland
Sharon
In service 7/30/2027
2025-04-11 SRRTEP Western
Item 05 - ATSI Supplemental Project p. 5
New Customer Connection
ATSI-2025-014
Homer
Wellington
In service 5/14/2027
2025-04-11 SRRTEP Western
Item 06 - APS Supplemental Project p. 3
New Customer Connection
APS-2025-011
Rider
Weston Substation
In service 12/31/2027
Load 22 MVA
2025-04-11 SRRTEP Western
Item 06 - APS Supplemental Project p. 4
Finzel - Ridgeley 138 kV line
APS-2025-014
Finzel
Frostburg
Ridgeley
No figures printed
2025-04-11 SRRTEP Western
Item 06 - APS Supplemental Project p. 6
Tidd (AEP) - Weirton 138 kV Line
APS-2025-015
Carnegie
Tidd (AEP)
Weirton Substation
No figures printed
2025-04-11 SRRTEP Western
Item 06 - APS Supplemental Project p. 9
Misoperation Relays
APS-2024-104
Brownsville Junction
Charleroi
Emerald Substation
Gates Hill Substation
Status Conceptual
Cost $6.17 M
In service 07/02/2029
2025-04-11 SRRTEP Western
Item 06 - APS Supplemental Project p. 12
New Customer Connection
APS-2024-110
Dutch Fork
Windsor
Status Conceptual
Cost $5.8 M
In service 08/14/2026
Load 20 MW
2025-04-11 SRRTEP Western
Item 06 - APS Supplemental Project p. 14
Fairview – Whiteley 138 kV
APS-2025-010
Blacksville No. 1 Tap
Fairview
Miracle Run Tap
Whiteley
Status Conceptual
Cost $1.3 M
In service 08/21/2026
2025-04-10 SRRTEP Mid-Atlantic
Item 01 - PENELEC Supplemental Projects p. 3
Altoona - Hollidaysburg 46 AH kV Line
PN-2024-005
Altoona
Hollidaysburg
Status Conceptual
Cost $2.21 M
In service 12/01/2027
2025-04-10 SRRTEP Mid-Atlantic
Item 01 - PENELEC Supplemental Projects p. 5
Tyrone North – Tipton 46 kV Line
PN-2024-006
Tipton Substation
Tyrone North Substation
Status Conceptual
Cost $2.92 M
In service 12/31/2027
2025-04-10 SRRTEP Mid-Atlantic
Item 02 - JCPL Supplemental Projects p. 3
Metedeconk Substation, NJ
JCPL-2025-003
Metedeconk In service 11/30/2026
Load 17 MW
2025-04-10 SRRTEP Mid-Atlantic
Item 02 - JCPL Supplemental Projects p. 5
Raritan River (Sayreville), NJ
JCPL-2024-029
Raritan River Substation Status Conceptual
Cost $6.91 M
In service 03/30/2029
2025-04-10 SRRTEP Mid-Atlantic
Item 02 - JCPL Supplemental Projects p. 7
Franklin No. 1 115-34.5 kV Transformer
JCPL-2024-036
Franklin Status Conceptual
Cost $6 M
In service 12/28/2029
2025-04-10 SRRTEP Mid-Atlantic
Item 02 - JCPL Supplemental Projects p. 9
Pequest River No. 1 115-34.5 kV Transformer
JCPL-2024-037
Pequest River Status Conceptual
Cost $6.9 M
In service 01/30/2030
2025-04-10 SRRTEP Mid-Atlantic
Item 02 - JCPL Supplemental Projects p. 11
Automatic Restoration Projects
JCPL-2024-052
Jacksonville Tap
Montville
Riverdale
Status Conceptual
Cost $0.15 M
In service 07/05/2026
2025-04-10 SRRTEP Mid-Atlantic
Item 02 - JCPL Supplemental Projects p. 13
Old Bridge Substation, NJ/Raritan River (Sayreville), NJ
JCPL-2025-001
Old Bridge
Raritan River Substation
Red Oak Tap
Status Conceptual
Cost $0.1 M
In service 05/31/2025
2025-04-10 SRRTEP Southern
Item 01 - Dominion Supplemental Projects p. 3
Dominion Transmission Zone: Supplemental Customer Service
DOM-2025-0014
Disputanta Substation In service 12/31/2026
2025-04-10 SRRTEP Southern
Item 01 - Dominion Supplemental Projects p. 4
Dominion Transmission Zone: Supplemental Equipment Material Condition, Performance and Risk
DOM-2025-0015
Basin
Manchester
Maury Street substation
Plaza substation
Load 4 MW
2025-04-10 SRRTEP Southern
Item 01 - Dominion Supplemental Projects p. 5
Dominion Transmission Zone: Supplemental Customer Service
DOM-2025-0016
London Bridge Substation In service 12/29/2028
2025-04-01 TEAC
Item 03 - ATSI Supplemental Projects p. 3
Mayfield - Northfield Q1 & Q3 & Eastlake - Lloyd Q12 & Q13 138 kV lines
ATSI-2025-006
Eastlake
Lloyd
Mayfield
Northfield
Load approximately 290 MW
2025-04-01 TEAC
Item 04 - APS Supplemental Projects p. 3
Elko 230/138 kV Transformer
APS-2025-012
Elko Substation No figures printed
2025-04-01 TEAC
Item 04 - APS Supplemental Projects p. 5
Pruntytown No. 1 500/138 kV Transformer
APS-2024-077
Pruntytown Substation Status Conceptual
Cost $ 18.8 M
In service 06/13/2031
2025-04-01 TEAC
Item 04 - APS Supplemental Projects p. 7
Pruntytown No. 2 500/138 kV Transformer
APS-2024-078
Pruntytown Substation Status Conceptual
Cost $ 18.8 M
In service 12/13/2030
2025-04-01 TEAC
Item 04 - APS Supplemental Projects p. 9
Wylie Ridge No. 7 500/345 kV Transformer
APS-2024-080
Wylie Ridge Substation Status Conceptual
Cost $ 20 M
In service 12/13/2030
2025-04-01 TEAC
Item 04 - APS Supplemental Projects p. 11
Frederick A – Monocacy 230 kV Line
APS-2025-001
Frederick A Substation
Monocacy Substation
Status Conceptual
Cost $ 3.9 M
In service 11/24/2027
2025-04-01 TEAC
Item 05 - AEP Supplemental Projects p. 3
Olive, IN
AEP-2025-IM005
Goodings Grove
Green Acres
Olive
University Park
No figures printed
2025-04-01 TEAC
Item 05 - AEP Supplemental Projects p. 6
New Carlisle, IN
AEP-2024-IM016
Dumont
Navistar New
New Prairie
Status Scoping (Conceptual)
Cost $50.364 M
In service 03/15/2027
Load 437MW
2025-04-01 TEAC
Item 06 - Dayton Supplemental Projects p. 5
Dayton-2025-001, Dayton-2025-002 Atlanta
Clinton
Fayette
Status Conceptual
Cost $480 M
In service 01/2031
Load 1.5 GW
2025-04-01 TEAC
Item 07 - PPL Supplemental Projects p. 3
Susquehanna, PA
PPL-2025-0003
None named In service 04/2026
Load 1,440 MW
2025-04-01 TEAC
Item 07 - PPL Supplemental Projects p. 5
Hauto, PA
PPL-2025-0002
Frackville
Tresckow
Status Conceptual
Cost $101 M
In service 05/30/2028
Load 350 MW
2025-04-01 TEAC
Item 08 - ComEd Supplemental Projects p. 3
Customer in Grayslake
ComEd-2025-005
None named Load 1,550 MW
2025-04-01 TEAC
Item 09 - DEOK Supplemental Projects p. 3
New Customer Load Request
DEOK-2025-002
Beckjord
Gold Finch New
Newtown
Pierce
Red Bank
Silver Grove
Status Scoping (Conceptual)
Cost $49.0M
In service 06/01/2028
Load 300 MW
2025-04-01 TEAC
Item 10 - PSEG Supplemental Projects p. 3
PSE&G Transmission Zone M-3 Process Newark Area
PSEG-2025-0002
Newark switching station No figures printed
2025-04-01 TEAC
Item 11 - DOM Supplemental Projects p. 4
Trabue 230kV Delivery - DEV
DOM-2025-0001
Trabue Substation Status Engineering
Cost $10.1M
In service 1/1/2026
Load 100 MW
2025-04-01 TEAC
Item 11 - DOM Supplemental Projects p. 6
Enon 230kV Delivery - DEV
DOM-2025-0010
Enon substation Status Engineering
Cost $1.6M
In service 3/1/2028
Load 88.9 MW
2025-04-01 TEAC
Item 11 - DOM Supplemental Projects p. 8
Ruther Glen 230kV Delivery - DEV
DOM-2024-0012
Four Rivers
Ladysmith CT
Ruther Glen New
Status Engineering
In service 7/1/2027
Load 300 MW
2025-04-01 TEAC
Item 11 - DOM Supplemental Projects p. 10
Carmel Church 230kV Delivery - DEV
DOM-2023-0055
Carmel Church Sub New
Four Rivers
Ladysmith CT
Status Engineering
In service 7/1/2027
Load 125.0 MW
2025-04-01 TEAC
Item 11 - DOM Supplemental Projects p. 12
New Post 230kV Delivery - DEV
DOM-2023-0016
Allman
Elmont
Four Rivers
Fredericksburg
Kraken
Ladysmith
Ladysmith CT
Lee’s Hill
N. Doswell
New Post New
Pinewood
Ruther Glen
St. Johns
Status Engineering
Cost $27.0 M
In service 05/31/2025
Load 248.0 MW
2025-04-01 TEAC
Item 11 - DOM Supplemental Projects p. 14
Lee’s Hill 230kV Delivery - DEV
DOM-2023-0053
Fredericksburg
Lee’s Hill New
New Post
Status Engineering
Cost $16.0 M
In service 12/15/2025
Load 300 MW
2025-04-01 TEAC
Item 12 - WVPA Supplemental Projects p. 3
Elderberry, IN/Stillwell, IN
WVPA-2025-001
Elderberry Substation
Stillwell substation
Status Conceptual
Cost $0M ($80 M covered by MISO)
In service 12/31/2028
2025-04-01 TEAC
Item 14 - Reliability Analysis Update p. 5
New Mars – Lockridge – Golden 230kV Lines New Mars – Golden 500kV Line
B3800.210 – B3800.212
Golden
Lockridge
Mars
Shellhorn
Sojourner
Cost $439.92M
In service 6/1/2027
2025-04-01 TEAC
Item 14 - Reliability Analysis Update p. 8
Doubs 500kV Breaker Replacement
b4000.110
Doubs Cost $10.06 M
In service 6/1/2029
2025-04-01 TEAC
Item 14 - Reliability Analysis Update p. 10
Loudoun – Morrisville 500kV
B3211
Loudoun
Morrisville
Status Cancelled
Cost $4.5 M
In service 12/31/2024
2025-04-01 TEAC
Item 14 - Reliability Analysis Update p. 11
Ox 500kV Breaker Replacements
B4000.130
None named Status Cancelled
Cost $3.045 M
In service 6/1/2029

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Latest · October 2026 (547) · September 2026 (830) · August 2026 (58) · July 2026 (80) · June 2026 (64) · May 2026 (90) · April 2026 (85) · March 2026 (71) · February 2026 (74) · January 2026 (69) · December 2025 (82) · November 2025 (156) · October 2025 (355) · September 2025 (219) · August 2025 (33) · July 2025 (40) · June 2025 (34) · May 2025 (41) · April 2025 (50) · March 2025 (56) · February 2025 (63) · January 2025 (42) · December 2024 (89) · November 2024 (138) · October 2024 (496)