Martins Creek

Named in 3 PJM planning documents for 1 project, from November 6, 2024 to October 8, 2025.

Not stateddescribed as
JCPLzone
230 kVkV as printed
3mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
JCPL Transmission Zone M-3 Process Morris Park Substation
JCPL-2023-011 · s3611.1
Not printed $15.4M 1/29/2027 13 MW 2025-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Mid-Atlantic
JCPL local plan submission for 2025 RTEP p. 4
JCPL Transmission Zone M-3 Process Morris Park Substation No role wording
230 kV
2025-10-08 TEAC
Informational Only - JCPL Local Plan Submission of the Supplemental Projects for 2025 p. 4
JCPL Transmission Zone M-3 Process Morris Park Substation No role wording
230 kV
2024-11-06 TEAC
Item 05 - JCPL Supplemental Projects p. 3
JCPL Transmission Zone M-3 Process Morris Park Substation No role wording
230 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.