Substation Scout

Mentions: January 2026

Each row is one PJM document naming substations for one project, newest first. Atom feed

Latest · October 2026 (547) · September 2026 (830) · August 2026 (58) · July 2026 (80) · June 2026 (64) · May 2026 (90) · April 2026 (85) · March 2026 (71) · February 2026 (74) · January 2026 (69) · December 2025 (82) · November 2025 (156) · October 2025 (355) · September 2025 (219) · August 2025 (33) · July 2025 (40) · June 2025 (34) · May 2025 (41) · April 2025 (50) · March 2025 (56) · February 2025 (63) · January 2025 (42) · December 2024 (89) · November 2024 (138) · October 2024 (496)

DateDocumentProjectSubstations namedAs printed
2026-01-16 SRRTEP Western
Item 01 - AEP supplemental projects p. 3
AEP Transmission Zone: Supplemental S2888 Scope Change
AEP-2022-IM008 · S2888
Adams
Berne
Cost $19.45M
In service 2/13/2029
2026-01-16 SRRTEP Western
Item 01 - AEP supplemental projects p. 5
Buchanan South, MI
AEP-2026-IM001
Buchanan South No figures printed
2026-01-16 SRRTEP Western
Item 01 - AEP supplemental projects p. 6
Progress Park, VA
AEP-2026-AP001
None named In service Q1 2027
Load 240MW
2026-01-16 SRRTEP Western
Item 01 - AEP supplemental projects p. 7
Bixby, OH/Beatty, OH
AEP-2026-OH001
Cyprus In service Q2 2027
Load 675 MW
2026-01-16 SRRTEP Western
Item 01 - AEP supplemental projects p. 9
Haverhill, Ohio
AEP-2022-OH002
North Haverhill Status Conceptual
Cost $12.985 M
In service 03/01/2027
2026-01-16 SRRTEP Western
Item 01 - AEP supplemental projects p. 11
Lazelle, OH/Bush, OH
AEP-2025-OH002
Busch
Sancus Switch New
Status Engineering
Cost $4.44 M
In service 12/28/2027
2026-01-16 SRRTEP Western
Item 01 - AEP supplemental projects p. 13
Hannibal, WV
AEP-2025-OH012
Hannibal Status Engineering
Cost $1.875 M
In service 10/26/2026
Load 570 MW
2026-01-16 SRRTEP Western
Item 02 - AMPT Supplemental Projects p. 3
Bryan-Edgerton 69 kV
AMPT-2026-001
Edgerton substation No figures printed
2026-01-16 SRRTEP Western
Item 02 - AMPT Supplemental Projects p. 5
Niles Central 138 kV substation
AMPT-2025-005
McDonald Steel
Niles
Niles Central
Status Pre-Engineering (Engineering)
Cost $14.1M
In service 08/01/2028
Load 63 MW
2026-01-16 SRRTEP Western
Item 03 - APS Supplemental Projects p. 3
Smithton 138 kV Substation
APS-2026-001
Allenport
Charleroi
Iron Bridge
Mitchell
Smithton Substation
Yukon
Load 10 MW
2026-01-16 SRRTEP Western
Item 03 - APS Supplemental Projects p. 4
Misoperation Relay Projects
APS-2026-002
Glenville
Goff Run Substation
Grantsville
No figures printed
2026-01-16 SRRTEP Western
Item 03 - APS Supplemental Projects p. 5
Joffre 138 kV Substation
APS-2026-003
Joffre Substation In service 05/27/2027
2026-01-16 SRRTEP Western
Item 03 - APS Supplemental Projects p. 6
Bredinville - McCalmont 138 kV Line
APS-2026-004
Bredinville
McCalmont
In service 3/15/2028
Load 80 MW
2026-01-16 SRRTEP Western
Item 03 - APS Supplemental Projects p. 8
Loughs Lane - Pickens 138 kV Line
APS-2025-016
Loughs Lane Substation
Pickens
Status Conceptual
Cost $1.05M
In service 12/31/2026
2026-01-16 SRRTEP Western
Item 03 - APS Supplemental Projects p. 10
Glenville - Weston 138 kV Line
APS-2024-074
Glenville
Weston Substation
Status Conceptual
Cost $89.52M
In service 12/15/2030
2026-01-16 SRRTEP Western
Item 04 - ATSI Supplemental Projects p. 3
Abbe - Carlisle No. 1 and No. 2 69 kV lines
ATSI-2026-001
Abbe
Carlisle
Johnson
Robson
Load 9 MW
2026-01-16 SRRTEP Western
Item 04 - ATSI Supplemental Projects p. 4
Bulk Mail Facility 138 kV
ATSI-2026-002
Bulk Mail Facility
Fernway Tap
Pine
No figures printed
2026-01-16 SRRTEP Western
Item 04 - ATSI Supplemental Projects p. 5
Crestline 69 kV Capacitor
ATSI-2026-003
Crestline Station
Leaside
Stevens
No figures printed
2026-01-16 SRRTEP Western
Item 04 - ATSI Supplemental Projects p. 6
Dale 138 kV Substation
ATSI-2026-004
Dale
Moore
South Akron
Strobel Substation
Load 56 MW
2026-01-16 SRRTEP Western
Item 04 - ATSI Supplemental Projects p. 7
Dixie 69 kV Substation
ATSI-2026-005
Dixie Substation
Omni
Perstorp Polyols
Teledyne
No figures printed
2026-01-16 SRRTEP Western
Item 04 - ATSI Supplemental Projects p. 8
East Springfield station
ATSI-2026-006
Benjamin T Branch
East Springfield
North Titus
No figures printed
2026-01-16 SRRTEP Western
Item 04 - ATSI Supplemental Projects p. 9
Eber 138 kV Substation
ATSI-2026-007
Eber Substation
Swanton
Wentworth
Load 43 MW
2026-01-16 SRRTEP Western
Item 04 - ATSI Supplemental Projects p. 10
Genoa - Maclean 69 kV Line
ATSI-2026-008
Genoa
Maclean
No figures printed
2026-01-16 SRRTEP Western
Item 04 - ATSI Supplemental Projects p. 11
Gilchrist - Hartville 69 kV
ATSI-2026-009
Burger Iron
Burger Iron Tap
Burger Rubbermaid Tap
Gilchrist
Goodyear Wingfoot
Goodyear Wingfoot Tap
Hartville
Omnova Tap
Rubbermaid
Trelleborg Wheel
No figures printed
2026-01-16 SRRTEP Western
Item 04 - ATSI Supplemental Projects p. 13
Pemberville 69 kV breakers
ATSI-2026-013
Bowling Green No. 4
Hancock Wood Tap
Maclean
Pemberville Station
No figures printed
2026-01-16 SRRTEP Western
Item 04 - ATSI Supplemental Projects p. 14
Toussaint 138 kV Substation
ATSI-2026-014
Bayshore
Brush Wellman
Davis Besse
Ottawa
Toussaint Substation
Load 25 MW
2026-01-16 SRRTEP Western
Item 04 - ATSI Supplemental Projects p. 16
Cascade (Cedar Street) 69 kV Line
ATSI-2022-001 · s3495.1
Blair Strip Steel
Cascade
Cedar St
Cedar Street
Hillcrest
New Wilmington
Public Welfare
Ray St
Walmo
YDC- West Tap
Status Conceptual
Cost $34.7 M
In service 3/31/2028
2026-01-16 SRRTEP Western
Item 05 - ComEd Supplemental Projects p. 3
Belvidere 138KV BT3-4 and L12205 Relays
ComEd-2026-001
Belvidere
Marengo
No figures printed
2026-01-16 SRRTEP Western
Item 05 - ComEd Supplemental Projects p. 5
NIPSCO Customer in Chicago
ComEd-2025-027
State Line
Wolf Lake
Status Engineering
Cost $ 0M
In service 6/1/2027
Load 260 MW
2026-01-16 SRRTEP Western
Item 06 - SRRTEP West - Reliability Analysis Update p. 3
Huntington Court 69kV Breaker CS-XT4 Replacement
B3975.2
Catawba
Huntington Court
Cost $1.0 M
In service 6/1/2030
2026-01-15 SRRTEP Mid-Atlantic
Item 01 - BGE Supplemental Projects p. 3
Triple Bridges
BGE-2026-001
None named Load 150 MW
2026-01-15 SRRTEP Mid-Atlantic
Item 02 - JCPL Supplemental Projects p. 3
Morris Court 34.5 kV Substation – Customer Interconnection, NJ
JCPL-2025-011
Briant Park
Morris Court Substation
Traynor
Status Conceptual
Cost $110,000
In service 09/14/2026
Load approximately 10 MW
2026-01-15 SRRTEP Mid-Atlantic
Item 03 - PPL Supplemental Projects p. 3
PPL Transmission Zone: Supplemental Watson, PA
PPL-2026-0005
Watson In service 4/1/2027
2026-01-15 SRRTEP Mid-Atlantic
Item 03 - PPL Supplemental Projects p. 4
PPL Transmission Zone: Supplemental West Berwick, PA
PPL-2026-0007
West Berwick In service 11/30/2028
2026-01-15 SRRTEP Mid-Atlantic
Item 03 - PPL Supplemental Projects p. 5
PPL Transmission Zone: Supplemental Fairfield, PA
PPL-2026-0008
Fairfield In service 10/8/2028
2026-01-15 SRRTEP Mid-Atlantic
Item 04 - UGI Supplemental Projects p. 3
UGI-2026-0001 Hunlock Creek Substation In service Q4 of 2027
Load 200MW
2026-01-15 SRRTEP Mid-Atlantic
Item 04 - UGI Supplemental Projects p. 4
UGI-2026-0002 Swoyersville No figures printed
2026-01-15 SRRTEP Mid-Atlantic
Item 06 - SRRTEP Mid-Atlantic - Reliability Analysis Update p. 4
ACE Transmission Zone: Baseline b3737.24 and B3737.25 Cancellation: Cardiff – Lewis 138kV
b3737.24 and B3737.25
Cardiff
Lewis
Status Cancelled
2026-01-15 SRRTEP Southern
Item 05 - DOM Supplemental Projects p. 3
Equipment Material Condition, Performance and Risk
DOM-2025-0074
Moon Corner
Northern Neck
Rappahannock
No figures printed
2026-01-15 SRRTEP Southern
Item 05 - DOM Supplemental Projects p. 5
Operational Flexibility and Efficiency
DOM-2022-0061 (Update)
Alexander Corner
Brown Boveri
Deep Creek
Quantico
Tunis
Status Engineering
Cost $1.86M
In service 12/31/2026
2026-01-06 TEAC
Item 02 - APS Supplemental Projects p. 3
Yukon No. 7 500/138 kV Transformer
APS-2025-030
Yukon Status Engineering
Cost $0.41M
In service 12/31/2026
2026-01-06 TEAC
Item 03 - JCPL Supplemental Projects p. 3
Manchester 230-34.5 kV Substation
JCPL-2026-001
Cookstown
Larrabee
Manchester
Whitings
Load 23 MW
2026-01-06 TEAC
Item 04 - Penelec Supplemental Projects p. 3
Keystone 500/230 kV No. 4 Transformer
PN-2026-002
Keystone No figures printed
2026-01-06 TEAC
Item 05 - ACE Supplemental Projects p. 3
ACE-2026-001 None named Load 49 MW
2026-01-06 TEAC
Item 06 - PECO Supplemental Projects p. 3
PE-2026-001 Newlinville No figures printed
2026-01-06 TEAC
Item 06 - PECO Supplemental Projects p. 4
PE-2026-002 Buxmont
Whitpain
No figures printed
2026-01-06 TEAC
Item 07 - DOM Supplemental Projects p. 3
Customer Load Request
DOM-2025-0030
Sunset Hill Substation In service December 31, 2028
Load 100 MW
2026-01-06 TEAC
Item 07 - DOM Supplemental Projects p. 4
Customer Load Request
DOM-2025-0031
Elm Farm Substation In service December 31, 2027
Load 69 MW
2026-01-06 TEAC
Item 07 - DOM Supplemental Projects p. 5
Customer Load Request
DOM-2025-0078
Barrister Substation In service May 31, 2029
Load 290 MW
2026-01-06 TEAC
Item 07 - DOM Supplemental Projects p. 6
Customer Load Request
DOM-2025-0098
Quantico New In service 12/31/2029
Load 30.3 MW
2026-01-06 TEAC
Item 07 - DOM Supplemental Projects p. 7
Customer Load Request
DOM-2026-0001
Correctional In service 12/31/2028
Load 41.3 MW
2026-01-06 TEAC
Item 07 - DOM Supplemental Projects p. 8
DOM-2025-0073 Correctional
Goalder’s Creek
Harmony Village Substation
Lanexa
Owl Trap
Paper Mill
Shackleford
West Point
No figures printed
2026-01-06 TEAC
Item 07 - DOM Supplemental Projects p. 10
Hanover 230 kV Delivery – TX Upgrade - DEV
DOM-2025-0017
Hanover Status Engineering
Cost $1.5M
In service 12/31/2026
2026-01-06 TEAC
Item 07 - DOM Supplemental Projects p. 12
West Creek 230kV Delivery - DEV
DOM-2025-0054
Midlothian
North Pole
Rockville
Short Pump
West Creek New
Status Planning (Conceptual)
Cost $35M
In service 07/26/2028
Load 100 MW
2026-01-06 TEAC
Item 07 - DOM Supplemental Projects p. 14
Shaw 230kV Delivery - REC
DOM-2025-0070
Kyser
Remington
Shaw New
Status Planning (Conceptual)
Cost $32M
In service 5/1/2028
Load 300 MW
2026-01-06 TEAC
Item 07 - DOM Supplemental Projects p. 16
Frances 230kV Delivery - REC
DOM-2025-0071
Frances New
Southall
Status Planning (Conceptual)
Cost $21M
In service 8/01/2027
Load 176 MW
2026-01-06 TEAC
Item 07 - DOM Supplemental Projects p. 18
Do No Harm Analysis
DOM-2025-0071-DNH
Foxbrook Lane substation
Frances
Gordonsville
N Anna
North Anna
Southall
Status Planning (Conceptual)
Cost $12M
In service 12/30/2028
2026-01-06 TEAC
Item 07 - DOM Supplemental Projects p. 20
Wesbey Drive 230kV Delivery - REC
DOM-2025-0072
Foxbrook Lane substation
Wesbey Drive New
Status Planning (Conceptual)
Cost $21M
In service 3/01/2029
Load 292 MW
2026-01-06 TEAC
Item 07 - DOM Supplemental Projects p. 22
Do No Harm Analysis
DOM-2019-0021, DOM-2024-0022, DOM-2024-0023, DOM-2024-0024 - DNH
Bermuda Hundred New
Chickahominy
Enon substation
Meadowville New
Shand Creek New
Sycamore Springs New
Status Engineering
Cost $95.1M
In service Q4 2028
2026-01-06 TEAC
Item 09 - Reliability Analysis Update p. 13
Woodsdale 345 kV Reliability & Reconfigure
b3940.1
Todhunter
Woodsdale
Cost $36.818 M
In service 11/16/2028
2026-01-06 TEAC
Item 09 - Reliability Analysis Update p. 15
Montville 500/230 kV Substation
b4032.1
Hopatcong
Iliff
Montville
Roseland
Whippany
Cost $98.10 M
In service 11/1/2029
2026-01-06 TEAC
Item 09 - Reliability Analysis Update p. 17
PPL Cluster
B4029.18
Kelayres
Susquehanna
Cost $4.5 M
In service 6/1/2030
2026-01-06 TEAC
Item 09 - Reliability Analysis Update p. 21
MAAC Regional Cluster: Baseline
b4036.1
Belmont
Buttermilk Falls
Conemaugh
Juniata
Kammer
Keystone
Mountain Stone
Mountaineer
South Bend
Sunbury
Cost $1789.39M
In service 6/1/2032
2026-01-06 TEAC
Item 09 - Reliability Analysis Update p. 24
Exelon/PEPCO Cluster
b4052.1
Aspen
Bells Mill
Brighton
Dickerson New
Quince Orchard
Rocky Point
Cost $282.16 M
In service 6/1/2032
2026-01-06 TEAC
Item 09 - Reliability Analysis Update p. 27
Regional Solution: 2025-W1-275 Portfolio
b4053.1
Burches Hill
Carson
Celestial
Chickahominy
Clifton
Cunningham
Elmont
Heritage New
Kraken New
Midlothian
Mosby
North Anna
Possum Point
Surry
Vint Hill
Vontay New
Wishing Star
Yeat
Cost $4832.45
In service 6/1/2032
2026-01-06 TEAC
Item 09 - Reliability Analysis Update p. 44
West Cluster Recommended Selection (2nd Read)
b4068.1
Adkins New
Allen
Beatty
Bethel
Bixby
Cole
Conesville New
Greentown
Guernsey
Hayden
Hess
Hyatt
Kirk
Maliszewski
Marysville
Meadow Lake
Newark Center
Ohio Central
OSU
South Kenton
Teddy New
West Millersport New
Cost $2,768.0M
In service 10/1/2032
2026-01-06 TEAC
Item 09 - Reliability Analysis Update p. 63
Richmond-Waneeta 230 kV Underground Rebuild
b3737.23
None named Status Cancellation (Cancelled)
Cost $16 M
In service 6/1/2029
2026-01-06 TEAC
Item 09 - Reliability Analysis Update p. 64
Ringgold 138 kV Breaker “138 BUS TIE” Replacement
b3983.1
Ringgold Status Cancellation (Cancelled)
Cost $0.957M
In service 6/1/2030
2026-01-06 TEAC
Item 09 - Reliability Analysis Update p. 66
NextEra MidAtlantic Resiliency Link ‘MARL’ Project Summary
b3800.102
502 Junction
Bismark
Black Oak
Doubs
Gore
Stonewall
Woodside New
Cost $844.80M
In service December 2028

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Latest · October 2026 (547) · September 2026 (830) · August 2026 (58) · July 2026 (80) · June 2026 (64) · May 2026 (90) · April 2026 (85) · March 2026 (71) · February 2026 (74) · January 2026 (69) · December 2025 (82) · November 2025 (156) · October 2025 (355) · September 2025 (219) · August 2025 (33) · July 2025 (40) · June 2025 (34) · May 2025 (41) · April 2025 (50) · March 2025 (56) · February 2025 (63) · January 2025 (42) · December 2024 (89) · November 2024 (138) · October 2024 (496)