Mentions: February 2026
Each row is one PJM document naming substations for one project, newest first. Atom feed
Latest · October 2026 (547) · September 2026 (830) · August 2026 (58) · July 2026 (80) · June 2026 (64) · May 2026 (90) · April 2026 (85) · March 2026 (71) · February 2026 (74) · January 2026 (69) · December 2025 (82) · November 2025 (156) · October 2025 (355) · September 2025 (219) · August 2025 (33) · July 2025 (40) · June 2025 (34) · May 2025 (41) · April 2025 (50) · March 2025 (56) · February 2025 (63) · January 2025 (42) · December 2024 (89) · November 2024 (138) · October 2024 (496)
| Date | Document | Project | Substations named | As printed |
|---|---|---|---|---|
| 2026-02-13 | SRRTEP Western Item 01 - SRRTEP West - Reliability Analysis Update p. 3 |
Avon 138 kV Breakers “4-B-107 and 4-B-84” Replacement b3985.1 |
Avon | Cost $1.92M |
| 2026-02-13 | SRRTEP Western Item 01 - SRRTEP West - Reliability Analysis Update p. 4 |
Johnson 69 kV Breaker “451-B-163” Replacement b3985.4 |
Johnson | Cost $0.957M |
| 2026-02-13 | SRRTEP Western Item 02 - AEP Supplemental Projects p. 3 |
AEP Transmission Zone: Supplemental s3440.3 Scope Change AEP-2022-OH071 · s3440.1-.6 |
Beatty Bixby Clinton Cyprus Marion station Mound Obetz Parsons Rozelle Saint Clair Avenue Waverly |
Status Scoping (Conceptual) Cost $77.4M In service 06/05/2027 Load 675 MW |
| 2026-02-13 | SRRTEP Western Item 02 - AEP Supplemental Projects p. 8 |
AEP Transmission Zone M-3 Process Greenleaf, IN/Conant, IN/Elkhart Hydro, IN/Osolo, IN /Dunlap, IN/East Elkhart, IN/Wyland SS, IN /Middleton Run SS, IN/Middlebury, IN/Parkway, IN AEP-2023-IM003, AEP-2023-IM005 |
Conant Dunlap East Elkhart Elkhart Hydro Greenleaf Middlebury Middleton Run SS Osolo Parkway Wyland SS |
Status Scoping (Conceptual) Cost $20.647 M In service 09/01/2028 |
| 2026-02-13 | SRRTEP Western Item 03 - AMPT Supplemental Projects p. 3 |
Poe Road - Tontogany 69 kV line AMPT-2025-004 |
Poe Road Sand Ridge Tontogany |
Status Pre-Engineering (Engineering) Cost $6.136 M In service 11/30/2028 |
| 2026-02-13 | SRRTEP Western Item 04 - ATSI Supplemental Projects p. 3 |
Avery - Carriage 69 kV Line ATSI-2026-015 |
Avery Carriage |
No figures printed |
| 2026-02-13 | SRRTEP Western Item 04 - ATSI Supplemental Projects p. 4 |
Chrysler – Dowling 138kV Line ATSI-2026-016 |
Chrysler Substation Dowling |
No figures printed |
| 2026-02-13 | SRRTEP Western Item 04 - ATSI Supplemental Projects p. 5 |
Cranberry - Pine No.1 138kV Line ATSI-2026-017 |
Cranberry Epworth Substation Pine |
Load 28 MW |
| 2026-02-13 | SRRTEP Western Item 04 - ATSI Supplemental Projects p. 6 |
Mantua – Garrettsville 69kV Line ATSI-2026-018 |
Garrettsville Mantua |
No figures printed |
| 2026-02-13 | SRRTEP Western Item 04 - ATSI Supplemental Projects p. 7 |
Frisco – Maple 69 kV Line ATSI-2026-019 |
Frisco Maple |
No figures printed |
| 2026-02-13 | SRRTEP Western Item 04 - ATSI Supplemental Projects p. 8 |
Peterburg Substation ATSI-2026-020 |
Boardman Columbiana Peterburg Substation Petersburg Substation |
Load 10 MW |
| 2026-02-13 | SRRTEP Western Item 04 - ATSI Supplemental Projects p. 9 |
Shawville and Mill Substations ATSI-2026-021 |
Abbe Johnson Mill Shawville |
Load 62 MW |
| 2026-02-13 | SRRTEP Western Item 05 - ComEd Supplemental Projects p. 2 |
Customer in Chicago ComEd-2025-021 |
None named | Status Withdraw Need (Cancelled) Load 300 MW |
| 2026-02-13 | SRRTEP Western Item 05 - ComEd Supplemental Projects p. 4 |
Belvidere Hardening ComEd-2026-002 |
Belvidere | No figures printed |
| 2026-02-13 | SRRTEP Western Item 05 - ComEd Supplemental Projects p. 6 |
Belvidere 138KV BT3-4 and L12205 Relays ComEd-2026-001 |
Belvidere Chrysler Marengo |
Status In Service Cost $200K In service 10/31/2025 |
| 2026-02-13 | SRRTEP Western Item 06 - Dayton Supplemental Projects p. 3 |
Dayton-2022-003 | Creekside New Eldean Millcreek |
Status Cancelled Cost $13.5M In service 06/1/2024 |
| 2026-02-13 | SRRTEP Western Item 06 - Dayton Supplemental Projects p. 5 |
Dayton-2026-002 | Huber Heights Phoneton |
No figures printed |
| 2026-02-13 | SRRTEP Western Item 06 - Dayton Supplemental Projects p. 6 |
Dayton-2026-003 | Marysville | No figures printed |
| 2026-02-13 | SRRTEP Western Item 06 - Dayton Supplemental Projects p. 8 |
Dayton-2021-003 | Camden Crystal Germantown Gratis Hutching Hutchings |
Status Conceptual Cost $6.2M In service 12/1/2028 Load 33MW |
| 2026-02-13 | SRRTEP Western Item 06 - Dayton Supplemental Projects p. 10 |
Dayton-2025-011 | East Casstown St. Paris |
Cost $8M In service 12/31/2027 |
| 2026-02-13 | SRRTEP Western Item 07 - DEOK Supplemental Projects p. 3 |
New Customer Load Request DEOK-2025-006 |
City of Hamilton Substation Fairfield Substation Port Union Seward Substation |
Status Scoping (Conceptual) Cost $65.0M In service 12/31/2029 Load 240 MW |
| 2026-02-12 | SRRTEP Mid-Atlantic Item 01 - SRRTEP Mid-Atlantic - Reliability Analysis Update p. 3 |
Warren 115kV Breaker “NO.1 XFMR” Replacement b3988.1 |
Warren | Status Cancellation (Cancelled) Cost $0.957M |
| 2026-02-12 | SRRTEP Mid-Atlantic Item 01 - SRRTEP Mid-Atlantic - Reliability Analysis Update p. 5 |
DPL Transmission Zone: b3749 b3749 |
New Church Piney Piney Grove |
Cost $77M In service 6/15/2027 |
| 2026-02-12 | SRRTEP Mid-Atlantic Item 01 - SRRTEP Mid-Atlantic - Reliability Analysis Update p. 6 |
ACE Transmission Zone: b3227 b3227 |
Corson Court England Middle |
Cost $20M In service 6/1/2026 |
| 2026-02-12 | SRRTEP Mid-Atlantic Item 02 - JCPL Supplemental Projects p. 3 |
Jerseyville Substation, NJ JCPL-2026-003 |
Bradevelt Jerseyville Smithburg |
No figures printed |
| 2026-02-12 | SRRTEP Mid-Atlantic Item 02 - JCPL Supplemental Projects p. 4 |
East Flemington Substation, NJ JCPL-2026-005 |
East Flemington Flemington Glen Gardner Neshanic Rocktown Road West Flemington |
No figures printed |
| 2026-02-12 | SRRTEP Mid-Atlantic Item 03 - MetEd Supplemental Projects p. 3 |
Lincoln-Orrtanna 115 kV Customer Connection, PA ME-2025-001 |
Lincoln Substation Orrtanna Substation West Gettysburg |
Status Conceptual Cost $3.06M In service 04/08/2031 |
| 2026-02-12 | SRRTEP Mid-Atlantic Item 04 - Penelec Supplemental Projects p. 3 |
Bethlehem Mine 33 - Nanty Glo 46 kV SGR Line, PA PN-2026-001 |
Bethlehem Mine 33 Cambria County Prison Ebensburg Nanty Glo REA Energy Reese Reese REA Tap Revloc |
No figures printed |
| 2026-02-12 | SRRTEP Mid-Atlantic Item 04 - Penelec Supplemental Projects p. 6 |
Bethlehem Mine 33 - Nanty Glo 46 kV SGR Line, PA PN-2025-009 |
Bethlehem Ebensburg Nanty Glo Reese Rea Revloc |
Status Conceptual Cost $1.67M In service 05/21/2027 |
| 2026-02-12 | SRRTEP Mid-Atlantic Item 05 - PPL Supplemental Projects p. 3 |
Cumberland, PA PPL-2026-0009 |
Cumberland West Shore |
In service 6/30/2029 |
| 2026-02-12 | SRRTEP Mid-Atlantic Item 05 - PPL Supplemental Projects p. 4 |
Berks, PA PPL-2026-0010 |
Berks South Akron |
In service 12/31/2028 |
| 2026-02-12 | SRRTEP Mid-Atlantic Item 05 - PPL Supplemental Projects p. 5 |
Lock Haven, PA PPL-2026-0011 |
Flemington Lock Haven Renovo |
In service 6/30/2030 |
| 2026-02-12 | SRRTEP Mid-Atlantic Item 05 - PPL Supplemental Projects p. 6 |
Hughestown, PA PPL-2026-0012 |
None named | In service 2/28/2029 Load 150MW |
| 2026-02-12 | SRRTEP Mid-Atlantic Item 05 - PPL Supplemental Projects p. 7 |
Lake Naomi, PA PPL-2026-0013 |
None named | In service 12/30/2028 Load 290MW |
| 2026-02-12 | SRRTEP Mid-Atlantic Item 05 - PPL Supplemental Projects p. 9 |
White Haven, PA PPL-2025-0026 |
Harwood White Haven |
Status Engineering Cost $0.3 M In service 12/01/2026 |
| 2026-02-12 | SRRTEP Mid-Atlantic Item 05 - PPL Supplemental Projects p. 11 |
Bear Creek, PA PPL-2025-0027 |
Bear Creek Jenkins Palooka |
Status Conceptual Cost $8 M In service 11/30/2028 |
| 2026-02-12 | SRRTEP Mid-Atlantic Item 05 - PPL Supplemental Projects p. 13 |
Fountain Springs, PA PPL-2025-0028 |
Fountain Springs Fountain springs Creek Frackville |
Status Conceptual Cost $1.6 M In service 11/30/2028 |
| 2026-02-12 | SRRTEP Mid-Atlantic Item 05 - PPL Supplemental Projects p. 15 |
Parrish, PA PPL-2025-0029 |
Hanover Harwood Palooka Parrish |
Status Conceptual Cost $0.3 M In service 11/30/2028 |
| 2026-02-12 | SRRTEP Mid-Atlantic Item 05 - PPL Supplemental Projects p. 17 |
Mausdale, PA PPL-2025-0030 |
Columbia Mausdale New Sunbury |
Status Engineering Cost $3.6 M In service 03/30/2028 |
| 2026-02-12 | SRRTEP Mid-Atlantic Item 05 - PPL Supplemental Projects p. 19 |
Watson, PA PPL-2026-0005 |
Clinton Milton Watson |
Status Conceptual Cost $0.5 M In service 04/01/2027 |
| 2026-02-12 | SRRTEP Mid-Atlantic Item 05 - PPL Supplemental Projects p. 21 |
West Berwick, PA PPL-2026-0007 |
Columbia Glen Brook West Berwick |
Status Conceptual Cost $0.1 M In service 11/30/2028 |
| 2026-02-12 | SRRTEP Mid-Atlantic Item 05 - PPL Supplemental Projects p. 23 |
Fairfield, PA PPL-2026-0008 |
Clinton Fairfield Lycoming |
Status Conceptual Cost $0.2 M In service 10/08/2028 |
| 2026-02-12 | SRRTEP Mid-Atlantic Item 06 - PSEG Supplemental Projects p. 3 |
PSE&G Southern Territory PSEG-2025-0010 |
Lawnside Nicholson |
Status Conceptual Cost $42.5 M In service 12/31/2030 |
| 2026-02-12 | SRRTEP Mid-Atlantic Item 08 - DPL Supplemental Projects p. 3 |
DPL-2025-003 | Carrcroft Edgemoor Silverside |
Status Engineering Cost $1.93M In service 4/2/2027 |
| 2026-02-12 | SRRTEP Mid-Atlantic Item 09 - PECO Supplemental Projects p. 3 |
PE-2026-003 | Master | No figures printed |
| 2026-02-12 | SRRTEP Mid-Atlantic Item 10 - BGE Supplemental Projects p. 3 |
Port Covington 115/13 kV Update BE-2019-0001 · s2025 |
Greene St Port Covington New Westport |
Status Design & Engineering Cost $407.25M In service 12/01/2026 Load 392MW |
| 2026-02-12 | SRRTEP Southern Item 07 - DOM Supplemental Projects p. 3 |
Supplemental Customer Load Request DOM-2026-0007 |
Boykins Substation | In service 12/31/2027 Load 8.9MW |
| 2026-02-12 | SRRTEP Southern Item 07 - DOM Supplemental Projects p. 4 |
Supplemental Equipment Material Condition, Performance and Risk DOM-2026-0006 |
Plywood Sedge hill |
No figures printed |
| 2026-02-12 | SRRTEP Southern Item 07 - DOM Supplemental Projects p. 6 |
Trego 115 kV Delivery – Install 2nd TX and Upgrade TX#1 - DEV DOM-2025-0036 |
Trego Substation | Status Construction (Under construction) Cost $0.7M In service 11/16/2026 |
| 2026-02-03 | TEAC Item 04 - APS Supplemental Projects p. 3 |
Doubs - Lime Kiln 230 kV Line APS-2025-021 |
Doubs Lime Kiln Manor Woods Quantum 300 Substation New Sage |
Status Conceptual Cost $63.16 M In service 09/23/2032 |
| 2026-02-03 | TEAC Item 05 - AEP Supplemental Projects p. 3 |
Don Marquis, OH AEP-2026-OH004 |
None named | In service 12/2027 Load 800 MW |
| 2026-02-03 | TEAC Item 06 - Dayton Supplemental Projects p. 3 |
Dayton-2025-007 | Eldean | Load 1400 MW |
| 2026-02-03 | TEAC Item 06 - Dayton Supplemental Projects p. 4 |
Dayton-2026-001 | Stuart | Load 1300 MW |
| 2026-02-03 | TEAC Item 06 - Dayton Supplemental Projects p. 6 |
Dayton-2025-008 | Darby Substation Flatlick (AEP) Substation Marysville (AEP) Patina New Peoria Weaver New |
Status Conceptual Cost $246M In service 05/01/2031 Load 800 MW |
| 2026-02-03 | TEAC Item 06 - Dayton Supplemental Projects p. 8 |
Dayton-2025-009 | Airport Substation Union New West Milton |
Status Conceptual Cost $25.8M In service 12/31/2029 Load 300 MW |
| 2026-02-03 | TEAC Item 07 - PPL Supplemental Projects p. 3 |
Martins Creek, PA S0866 |
Fox Hill Martins Creek Monroe Shawnee Substations |
Status Engineering Cost $66.9M In service 5/30/2028 |
| 2026-02-03 | TEAC Item 07 - PPL Supplemental Projects p. 6 |
Archbald Mountain, PA PPL-2025-0014 |
Archbald Mountain New Callender Gap Hopatcong Lackawanna Paupack Sturges Sturgis |
Status Project Development (Conceptual) Cost $220 M In service 05/30/2028 Load 1,000 MW |
| 2026-02-03 | TEAC Item 08 - PECO Supplemental Projects p. 3 |
Lock Substation New 230 kV Breaker PE-2025-006 |
Lock | Status Engineering Cost $2.4 million In service 12/31/2026 |
| 2026-02-03 | TEAC Item 09 - BGE Supplemental Projects p. 3 |
Customer in Calvert County BGE-2025-011 |
Calvert Cliffs Camp Canoy New Chalk Point Waugh Chapel |
Status Engineering Cost $263.5M In service 3/1/2028 Load 880 MW |
| 2026-02-03 | TEAC Item 10 - ComEd Supplemental Projects p. 2 |
Customer in Braidwood ComEd-2025-012 |
None named | Load 750 MW |
| 2026-02-03 | TEAC Item 10 - ComEd Supplemental Projects p. 2 |
Customer in Aurora ComEd-2025-017 |
None named | Load 450 MW |
| 2026-02-03 | TEAC Item 10 - ComEd Supplemental Projects p. 4 |
Customer in DeKalb ComEd-2025-009 |
Charter Grove New Gurler New Keslinger |
Status Conceptual Cost $245M In service 12/4/2029 Load 504 MW |
| 2026-02-03 | TEAC Item 10 - ComEd Supplemental Projects p. 6 |
Customer in DeKalb ComEd-2025-010 |
Keslinger | Status Conceptual Cost $30M In service 10/31/2028 Load 860 MW |
| 2026-02-03 | TEAC Item 10 - ComEd Supplemental Projects p. 8 |
Customer in Morris ComEd-2025-011 |
Collins Hiawatha New Kendall County E. C. |
Status Conceptual Cost $99M In service 6/1/2028 Load 1,000 MW |
| 2026-02-03 | TEAC Item 10 - ComEd Supplemental Projects p. 10 |
Customer in Coal City ComEd-2025-013 |
Braidwood Coal City New Dresden LaSalle Pontiac Midpoint |
Status Conceptual Cost $145M In service 7/1/2028 Load 1,296 MW |
| 2026-02-03 | TEAC Item 10 - ComEd Supplemental Projects p. 12 |
Customer in Rockford ComEd-2025-014 |
Byron Cherry Valley Edson Road New |
Status Conceptual Cost $92M In service 1/1/2028 Load 600 MW |
| 2026-02-03 | TEAC Item 10 - ComEd Supplemental Projects p. 14 |
Customer in Joliet ComEd-2025-016 |
Elwood Goodings Grove Rowell New |
Status Conceptual Cost $269M In service 7/1/2028 Load 1,800 MW |
| 2026-02-03 | TEAC Item 11 - PSEG Supplemental Projects p. 3 |
PSE&G Transmission Zone M-3 Process
Mount Laurel Area PSEG-2026-0001 |
None named | Load 300 MW |
| 2026-02-03 | TEAC Item 11 - PSEG Supplemental Projects p. 4 |
PSE&G Transmission Zone M-3 Process
Hamilton Area PSEG-2026-0002 |
None named | Load 120MW |
| 2026-02-03 | TEAC Item 12 - DOM Supplemental Projects p. 4 |
Mudd Tavern 230kV Delivery - REC DOM-2025-0032 |
Mudd Tavern New Orrock(Matta) |
Status Conceptual Cost $ 26M In service 03/01/2029 Load 300 MW |
| 2026-02-03 | TEAC Item 12 - DOM Supplemental Projects p. 6 |
James Hill 230kV Delivery - DEV DOM-2024-0036 |
Chesterfield James Hill New Poe |
Status Conceptual Cost $26M In service 12/30/2031 Load in excess of 100 MW |
| 2026-02-03 | TEAC Item 12 - DOM Supplemental Projects p. 8 |
Emy 230kV Delivery - REC DOM-2025-0051 |
Emy New Kraken New Post Tributary |
Status Conceptual Cost $26M In service 05/01/2030 Load 212 MW |
| 2026-02-03 | TEAC Item 12 - DOM Supplemental Projects p. 10 |
Cosner 230kV Delivery - REC DOM-2025-0083 |
Cosner New Lee’s Hill New Post |
Status Conceptual Cost $28M In service 09/30/2030 Load 300 MW |
| 2026-02-03 | TEAC Item 13 - Reliability Analysis Update p. 7 |
Yeat Substation Relocation Update b4000.357 |
Bristers Elk Run Meadowbrook Vint Hill Yeat New |
No figures printed |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Latest · October 2026 (547) · September 2026 (830) · August 2026 (58) · July 2026 (80) · June 2026 (64) · May 2026 (90) · April 2026 (85) · March 2026 (71) · February 2026 (74) · January 2026 (69) · December 2025 (82) · November 2025 (156) · October 2025 (355) · September 2025 (219) · August 2025 (33) · July 2025 (40) · June 2025 (34) · May 2025 (41) · April 2025 (50) · March 2025 (56) · February 2025 (63) · January 2025 (42) · December 2024 (89) · November 2024 (138) · October 2024 (496)
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.