Blooming Grove
Named in 4 PJM planning documents for 1 project, from October 8, 2024 to October 8, 2025.
Existingdescribed as
PPLzone
230-69kV, 230/69kVkV as printed
4mentions
Also printed as: Blooming Grove substation
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| Blooming Groove, PA PPL-2024-0016 · s3553 |
Conceptual | $6.3 M | 12/31/2027 | Not printed | 2025-10-08 TEAC |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-09-08* | SRRTEP Mid-Atlantic PPL local plan submission for 2025 RTEP p. 15 |
Blooming Groove, PA | “replacement of the existing 230-69kV Blooming Grove Transformer 1” 230-69kV |
| 2025-10-08 | TEAC Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2025 p. 14 |
Blooming Groove, PA | “Install a new 170MVA, 230-69kV transformer as an inkind replacement of the existing 230-69kV Blooming Grove Transformer 1” 230/69kV |
| 2024-11-06 | TEAC Item 08 - PPL Supplemental Projects p. 18 |
Blooming Groove, PA | “in-kind replacement of the existing 230-69kV Blooming Grove Transformer 1” 230-69kV |
| 2024-10-08 | TEAC Item 07 - PPL Supplemental Projects p. 8 |
Blooming Groove, PA | No role wording 230/69kV |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.