Substation Scout

Pitney

Named in 3 PJM planning documents for 1 project, from November 6, 2024 to October 8, 2025.

Newdescribed as
PPLzone
138kVkV as printed
3mentions

Described as new: “Construct a new five bay BAAH 138kV switchyard” — source, page 27

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Donnelley Gravure, PA
PPL-2024-0010 · s3547
Conceptual $117.8 M 06/01/2028 350 MW 2025-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Mid-Atlantic
PPL local plan submission for 2025 RTEP p. 27
Donnelley Gravure, PA “Construct a new five bay BAAH 138kV switchyard”
138kV
2025-10-08 TEAC
Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2025 p. 27
Donnelley Gravure, PA “Construct a new five bay BAAH 138kV switchyard”
138kV
2024-11-06 TEAC
Item 08 - PPL Supplemental Projects p. 6
Donnelley Gravure, PA “Construct a new five bay BAAH 138kV switchyard near the customer's facility”
138kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.