Mentions: June 2026
Each row is one PJM document naming substations for one project, newest first. Atom feed
Latest · October 2026 (547) · September 2026 (830) · August 2026 (58) · July 2026 (80) · June 2026 (64) · May 2026 (90) · April 2026 (85) · March 2026 (71) · February 2026 (74) · January 2026 (69) · December 2025 (82) · November 2025 (156) · October 2025 (355) · September 2025 (219) · August 2025 (33) · July 2025 (40) · June 2025 (34) · May 2025 (41) · April 2025 (50) · March 2025 (56) · February 2025 (63) · January 2025 (42) · December 2024 (89) · November 2024 (138) · October 2024 (496)
| Date | Document | Project | Substations named | As printed |
|---|---|---|---|---|
| 2026-06-17 | SRRTEP Western Item 01 - AMPT Supplemental Projects p. 3 |
Moore Street substation AMPT 2026-006 |
Moore St Moore Street |
Load 14 MW |
| 2026-06-17 | SRRTEP Western Item 01 - AMPT Supplemental Projects p. 4 |
Riverside-Bridge St-Brantly 69 kV line AMPT 2026-008 |
None named | No figures printed |
| 2026-06-17 | SRRTEP Western Item 01 - AMPT Supplemental Projects p. 5 |
New Customer Service AMPT 2026-010 |
Rock Springs | Load 150 MW |
| 2026-06-17 | SRRTEP Western Item 01 - AMPT Supplemental Projects p. 6 |
New Customer Service AMPT 2026-011 |
Rock Springs | Load 170 MW |
| 2026-06-17 | SRRTEP Western Item 01 - AMPT Supplemental Projects p. 7 |
Niles Central substation AMPT 2026-005 |
Niles Central | Load 60 MW |
| 2026-06-17 | SRRTEP Western Item 01 - AMPT Supplemental Projects p. 8 |
Newton Falls 69 kV AMPT 2026-007 |
Newton Falls | Load 10 MW |
| 2026-06-17 | SRRTEP Western Item 02 - ATSI Supplemental Projects p. 3 |
Lockwood Road - Richland 138 kV ATSI-2026-041 |
Lockwood Road Richland |
In service 01/01/2030 Load 120 MVA |
| 2026-06-17 | SRRTEP Western Item 02 - ATSI Supplemental Projects p. 4 |
Cloverdale - Torrey 138 kV Line & Canton Central - Cloverdale 138 kV Line ATSI-2026-044 |
Canton Central Cloverdale Torrey |
In service 06/22/2028 Load 90 MVA |
| 2026-06-17 | SRRTEP Western Item 02 - ATSI Supplemental Projects p. 5 |
The Ingomar (Pine) 69 kV Rebuild ATSI-2026-045 |
Brandt Tap-Allegheny Brandt Tap-Brandt Ingomar Ingomar-Brandt Tap Manor Road Tap-Manor Road Manor Road Tap-McKnight Tap McKnight Tap-Ingomar Pine Pine-Wexford Tap Richard Tap-Brandt Tap Wexford Tap-Manor Road Tap |
No figures printed |
| 2026-06-17 | SRRTEP Western Item 03 - APS Supplemental Projects p. 3 |
Burma - Ridgway 138 kV Line APS-2026-007 |
Burma Clarion Substation Ridgway |
No figures printed |
| 2026-06-17 | SRRTEP Western Item 03 - APS Supplemental Projects p. 5 |
New Customer Request APS-2026-016 |
Glenville Sand Fork Substation Weston Substation |
In service 04/06/2027 Load 2 MW |
| 2026-06-17 | SRRTEP Western Item 03 - APS Supplemental Projects p. 6 |
New Customer Request APS-2026-021 |
Taneytown No. 1 Substation | In service 12/30/2028 Load 25 MW |
| 2026-06-17 | SRRTEP Western Item 03 - APS Supplemental Projects p. 7 |
Misoperation Relay Projects APS-2026-022 |
Ringgold West Waynesboro |
No figures printed |
| 2026-06-17 | SRRTEP Western Item 03 - APS Supplemental Projects p. 8 |
Misoperation Relay Projects APS-2026-024 |
Inwood Stonewall |
No figures printed |
| 2026-06-17 | SRRTEP Western Item 03 - APS Supplemental Projects p. 9 |
Misoperation Relay Projects APS-2026-027 |
Cumberland Ridgeley |
No figures printed |
| 2026-06-17 | SRRTEP Western Item 03 - APS Supplemental Projects p. 10 |
Misoperation Relay Projects APS-2026-029 |
Stephenson Stonewall |
No figures printed |
| 2026-06-17 | SRRTEP Western Item 03 - APS Supplemental Projects p. 11 |
Misoperation Relay Projects APS-2026-031 |
Double Toll Gate Meadow Brook |
No figures printed |
| 2026-06-17 | SRRTEP Western Item 03 - APS Supplemental Projects p. 12 |
Misoperation Relay Projects APS-2026-032 |
Gordonsville Pratts |
No figures printed |
| 2026-06-17 | SRRTEP Western Item 03 - APS Supplemental Projects p. 13 |
Misoperation Relay Projects APS-2026-033 |
Bethel Riverton Viscose |
No figures printed |
| 2026-06-17 | SRRTEP Western Item 03 - APS Supplemental Projects p. 15 |
New Customer Request APS-2026-006 |
Cecil Weirton Substation Windsor |
Status Conceptual Cost $1.40 M In service 07/17/2028 Load 29 MW |
| 2026-06-17 | SRRTEP Western Item 03 - APS Supplemental Projects p. 17 |
Dutch Fork – Enon 138 kV Line APS-2023-033 |
Dutch Fork Enon Substation |
Status Conceptual Cost $41.70M In service 12/08/2029 |
| 2026-06-17 | SRRTEP Western Item 03 - APS Supplemental Projects p. 20 |
Misoperation Relay Projects APS-2024-101 |
None named | Status Cancelled |
| 2026-06-17 | SRRTEP Western Item 04 - AEP Supplemental Projects p. 3 |
Hillsboro, OH/Wildcat, OH AEP-2026-OH021 |
Hillsboro Kenton Maysville Sardinia Wildcat |
No figures printed |
| 2026-06-17 | SRRTEP Western Item 04 - AEP Supplemental Projects p. 4 |
Wagenhals, OH AEP-2026-OH024 |
Wagenhals | Load 324 MW |
| 2026-06-17 | SRRTEP Western Item 04 - AEP Supplemental Projects p. 5 |
Torrey, OH AEP-2026-OH025 |
Torrey | No figures printed |
| 2026-06-17 | SRRTEP Western Item 04 - AEP Supplemental Projects p. 7 |
Mound, OH/Marion, OH AEP-2026-OH026 |
Mound Street | No figures printed |
| 2026-06-17 | SRRTEP Western Item 04 - AEP Supplemental Projects p. 11 |
West Lancaster, OH/South Baltimore, OH AEP-2024-OH031, AEP-2024-OH044 |
Anchor Hocking Memorial Drive South Baltimore West Lancaster |
Status Engineering Cost $33.852 M In service 12/01/2028 |
| 2026-06-17 | SRRTEP Western Item 04 - AEP Supplemental Projects p. 13 |
Kenova, WV AEP-2026-AP004 |
Kenova | Status In Service Cost $0.6 M In service 05/22/2026 |
| 2026-06-17 | SRRTEP Western Item 05 - ComEd Supplemental Projects p. 3 |
Des Plaines 345KV/138KV TR 34KV Tertiary Caps ComEd-2026-010 |
Des Plaines | No figures printed |
| 2026-06-17 | SRRTEP Western Item 05 - ComEd Supplemental Projects p. 5 |
138 kV L1210 Circuit Switcher ComEd-2026-008 |
None named | Status Engineering Cost $545K In service 9/31/2026 |
| 2026-06-16 | SRRTEP Mid-Atlantic Item 01 - DOM Supplemental Projects p. 3 |
Equipment Material Condition, Performance and Risk DOM-2025-0074 |
Moon Corner Northern Neck Rappahannock |
Status Cancelled |
| 2026-06-16 | SRRTEP Mid-Atlantic Item 02 - JCPL Supplemental Projects p. 3 |
Flanders - Pohatcong Mountain 34.5 kV R772 Line, NJ JCPL-2026-020 |
Allamuchy Bud Lake SW PT Flanders Hackettstown Hackettstown Hosp Hackettstown Hosp TP Hackettstown Tap M&M- MARS Netcong Panther Valley Pohatcong Mountain Saxton Falls |
No figures printed |
| 2026-06-16 | SRRTEP Mid-Atlantic Item 02 - JCPL Supplemental Projects p. 6 |
Cookstown- Windsor 34.5 kV H60 Line, NJ JCPL-2026-021 |
Cookstown Great Adventure Great Adventure Swpt Hornerstown New Canton Tap Plumstead Battery Tap Upper Free Solar Tap Windsor |
No figures printed |
| 2026-06-16 | SRRTEP Mid-Atlantic Item 02 - JCPL Supplemental Projects p. 8 |
Customer Connection - Larrabee-Point Pleasant No. 2 34.5 kV R44 Line, NJ JCPL-2026-023 |
Larrabee Ocean Medical Point Pleasant |
In service 12/31/2027 |
| 2026-06-16 | SRRTEP Mid-Atlantic Item 02 - JCPL Supplemental Projects p. 10 |
Highlands-Long Branch 34.5 kV K89 Line Rebuild, NJ JCPL-2019-025 |
Highlands Substation Long Branch Substation Monmouth Beach Sandy Hook Sandy Hook SW Sea Bright Sea Bright SW |
Status Conceptual Cost $28.27M In service 03/11/2030 |
| 2026-06-16 | SRRTEP Mid-Atlantic Item 02 - JCPL Supplemental Projects p. 14 |
Allenhurst 34.5 kV Substation Breaker Replacements, NJ JCPL-2025-008 |
Allenhurst Substation Oceanview |
Status Conceptual Cost $3.31M In service 12/31/2028 |
| 2026-06-16 | SRRTEP Mid-Atlantic Item 03 - MetEd Supplemental Projects p. 3 |
North Lebanon 69 kV Substation, PA ME-2026-003 |
Cleona Fredericksburg Tap North Lebanon Stouchsburg |
Load 16 MW |
| 2026-06-16 | SRRTEP Mid-Atlantic Item 03 - MetEd Supplemental Projects p. 5 |
New Customer Connection – Taneytown No.1 Substation, MD ME-2026-007 |
Taneytown No.1 Substation | In service 12/30/2028 Load 25 MW |
| 2026-06-16 | SRRTEP Mid-Atlantic Item 03 - MetEd Supplemental Projects p. 7 |
North Hanover 115 kV Breaker and a Half Substation, PA ME-2024-012 |
Gitts Run Hunterstown Jackson North Hanover |
Status Conceptual Cost $36.79M In service 12/29/2028 Load 59 MW |
| 2026-06-16 | SRRTEP Mid-Atlantic Item 04 - Penelec Supplemental Projects p. 3 |
Erie South - French Road No. 2 115 kV Line, PA PN-2026-006 |
Erie South French Road |
No figures printed |
| 2026-06-16 | SRRTEP Mid-Atlantic Item 04 - Penelec Supplemental Projects p. 5 |
Glory - Nanty Glo - Spangler 46 kV N Line Switches, PA PN-2026-007 |
Glory Moss Creek Nanty Glo Nicktown Spangler Teakettle |
No figures printed |
| 2026-06-16 | SRRTEP Mid-Atlantic Item 04 - Penelec Supplemental Projects p. 7 |
Garman Substation 115 kV Breaker B3, PA PN-2026-008 |
Garman | No figures printed |
| 2026-06-16 | SRRTEP Mid-Atlantic Item 04 - Penelec Supplemental Projects p. 8 |
Valley REC Miller - Warrior Ridge 46 kV Line, PA PN-2026-010 |
Miller REC Valley REC Miller Warrior Ridge |
No figures printed |
| 2026-06-16 | SRRTEP Mid-Atlantic Item 04 - Penelec Supplemental Projects p. 10 |
East Pike - Glory 115 kV Line Rebuild, PA PN-2024-027 |
East Pike Glory |
Status Conceptual Cost $47.73M In service 12/19/2029 |
| 2026-06-16 | SRRTEP Mid-Atlantic Item 05 - PPL Supplemental Projects p. 3 |
PPL Transmission Zone: Supplemental Lock Haven, PA PPL-2026-0011 |
Flemington Flemington Tap Lock Haven Renovo |
Status Conceptual Cost $59.9 M In service 11/30/2030 |
| 2026-06-16 | SRRTEP Mid-Atlantic Item 05 - PPL Supplemental Projects p. 5 |
PPL Transmission Zone: Supplemental Lake Naomi, PA PPL-2026-0013 |
Acahela Jackson |
Cost $28.8 M In service 12/30/2028 Load 290MW |
| 2026-06-16 | SRRTEP Mid-Atlantic Item 06 - PSEG Supplemental Projects p. 3 |
PSE&G Southern Territory PSEG-2025-0009 |
Lawrence | Status Conceptual Cost $48.4 M In service 12/31/2029 |
| 2026-06-16 | SRRTEP Southern Item 01 - DOM Supplemental Projects p. 3 |
Equipment Material Condition, Performance and Risk DOM-2025-0074 |
Moon Corner Northern Neck Rappahannock |
Status Cancelled |
| 2026-06-02 | TEAC Informational Only - 5034 500 kV Line Cut-in Immediate Need Assessment - Need Statement p. 1 |
Cut-in the ‘5034’ 500 kV line into Bramah 500 kV Substation | Bramah Conastone Delta York Peach Bottom |
Cost $12 million In service October 14, 2027 |
| 2026-06-02 | TEAC Item 04 - UGI Supplemental Projects p. 3 |
UGI-2026-0003 | None named | In service Q3 of 2029 and an additional 250MW in Q1 of 2030 Load 500MW |
| 2026-06-02 | TEAC Item 05 - JCPL Supplemental Projects p. 3 |
JCPL Transmission Zone M-3 Process
34.5 kV System JCPL-2026-026 |
None named | No figures printed |
| 2026-06-02 | TEAC Item 06 - AEP Supplemental Projects p. 3 |
Flatlick, OH AEP-2026-OH022 |
Flatlick | No figures printed |
| 2026-06-02 | TEAC Item 06 - AEP Supplemental Projects p. 5 |
Hanna, IN/Tanners Creek, IN AEP-2025-IM010 |
Batesville Gwynneville Hanna Junction Tower Sunnyside Tanners Creek |
Status Scoping (Conceptual) Cost $520 M In service 10/15/2031 |
| 2026-06-02 | TEAC Item 07 - PPL Supplemental Projects p. 3 |
Bressler, PA PPL-2026-0037 |
None named | In service 03/2029 Load 900 MW |
| 2026-06-02 | TEAC Item 08 - PECO Supplemental Projects p. 3 |
PECO Transmission Zone PE-2026-007 |
Whitpain | Status Engineering Cost $3.3 million In service 6/1/2030 |
| 2026-06-02 | TEAC Item 08 - PECO Supplemental Projects p. 5 |
PECO Transmission Zone PE-2026-008 |
Whitpain | Status Engineering Cost $55.7 million In service 6/1/2030 |
| 2026-06-02 | TEAC Item 08 - PECO Supplemental Projects p. 7 |
PECO Transmission Zone PE-2026-012 |
Buckingham Warrington |
Status Engineering Cost $582k In service 10/10/2026 |
| 2026-06-02 | TEAC Item 09 - 5034 500 kV Line Cut-in Immediate Need Assessment - First Read p. 6 |
PECO Transmission Zone: Cut-in the ‘5034’ 500 kV line in and out of the Bramah (North Delta) 500 kV Substation | Bramah Delta York Peach Bottom |
Cost $12M In service 10/14/2027 |
| 2026-06-02 | TEAC Item 10 - ComEd Supplemental Projects p. 3 |
Burnham 345KV/138KV TR ComEd-2026-009 |
Burnham | No figures printed |
| 2026-06-02 | TEAC Item 11 - DOM Supplemental Projects p. 3 |
Dominion Transmission Zone: Supplemental Customer Load Request DOM-2026-0025 |
Mudel New | In service 12/30/2029 Load 300 MW |
| 2026-06-02 | TEAC Item 11 - DOM Supplemental Projects p. 5 |
Dominion Transmission Zone: Supplemental Do No Harm Analysis DOM-2025-0070-DNH |
McDevitt Remington Remmington Shaw |
Status Planning (Conceptual) Cost $4M In service 5/1/2028 |
| 2026-06-02 | TEAC Item 11 - DOM Supplemental Projects p. 7 |
Install 230 kV Conductor on North Anna to Bristers Structures DOM-2026-0022 |
Bristers Elmont Fredericksburg North Anna Thornburg |
Status Engineering Cost $33.75 M In service Q4 2030 Load 3000 MW |
| 2026-06-02 | TEAC Item 11 - DOM Supplemental Projects p. 9 |
Dominion Transmission Zone: Supplemental Do No Harm Analysis DOM-2023-0016, 0053, 0055, 2024-0012 - DNH |
Allman Chancellor Elmont Four Rivers Fredericksburg Kraken Ladysmith Ladysmith CT Lee’s Hill N. Doswell New Post Pinewood Possum Point Ruther Glen St. Johns Thornburg |
Status Engineering Cost $450.0M In service 07/01/2029 |
| 2026-06-02 | TEAC Item 11 - DOM Supplemental Projects p. 12 |
Dominion Transmission Zone: Supplemental Operational Flexibility and Efficiency DOM-2024-0051 |
Chickahominy Elmont Four Rivers Fredericksburg Ladysmith CT Lee’s Hill New Post Ruther Glen Thornburg |
Status Engineering Cost $165M In service 12/31/2030 |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Latest · October 2026 (547) · September 2026 (830) · August 2026 (58) · July 2026 (80) · June 2026 (64) · May 2026 (90) · April 2026 (85) · March 2026 (71) · February 2026 (74) · January 2026 (69) · December 2025 (82) · November 2025 (156) · October 2025 (355) · September 2025 (219) · August 2025 (33) · July 2025 (40) · June 2025 (34) · May 2025 (41) · April 2025 (50) · March 2025 (56) · February 2025 (63) · January 2025 (42) · December 2024 (89) · November 2024 (138) · October 2024 (496)
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.