Mt. Pony Sub

Named in 3 PJM planning documents for 1 project, from November 6, 2024 to October 8, 2025.

Newdescribed as
DOMzone
230 kV, 230kVkV as printed
3mentions

Described as new: “Connect the new substation” — source, page 18

Also printed as: Mt Pony

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Dominion Transmission Zone: Supplemental Customer Load Request
DOM-2024-0084 · s3684
Conceptual $39.8M Q2 2028 160 MW 2025-10-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date 01/01/2027 → Q2 2028 2024-11-06 2025-02-04
Substations named MT PONY → MCDEVITT; MT PONY 2024-11-06 2025-02-04

Every mention

DateDocumentProjectWhat the document says about it
2025-10-08 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2025 p. 46
Dominion Transmission Zone: Supplemental Customer Load Request “new 230 kV delivery point (Mt. Pony Sub)”
230 kV
2025-02-04 TEAC
Item 11 - Dominion Supplemental Projects p. 18
Dominion Transmission Zone: Supplemental Customer Load Request “Connect the new substation”
230kV
2024-11-06 TEAC
Item 12 - Dominion Supplemental Projects p. 12
Dominion Transmission Zone: Supplemental Customer Load Request “new 230 kV delivery point (Mt. Pony Sub)”
230 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.