Each row is one PJM document naming substations for one project, newest first. Showing the latest 200; earlier months are archived below. Atom feed

Latest · October 2026 (547) · September 2026 (830) · August 2026 (58) · July 2026 (80) · June 2026 (64) · May 2026 (90) · April 2026 (85) · March 2026 (71) · February 2026 (74) · January 2026 (69) · December 2025 (82) · November 2025 (156) · October 2025 (355) · September 2025 (219) · August 2025 (33) · July 2025 (40) · June 2025 (34) · May 2025 (41) · April 2025 (50) · March 2025 (56) · February 2025 (63) · January 2025 (42) · December 2024 (89) · November 2024 (138) · October 2024 (496)

DateDocumentProjectSubstations namedAs printed
2026-10-16 SRRTEP Mid-Atlantic
Item 01 - ACE Supplemental Projects Presentation p. 3
ACE-2026-004 England
Merion
No figures printed
2026-10-16 SRRTEP Mid-Atlantic
Item 02 - DPL Supplemental Projects Presentation p. 3
DPL-2026-004 Brandywine No figures printed
2026-10-16 SRRTEP Mid-Atlantic
Item 02 - DPL Supplemental Projects Presentation p. 5
DPL-2026-002 Carrcroft
Edgemoor
Silverside
Status Engineering
Cost $0.6 million
In service 3/15/2027
2026-10-16 SRRTEP Mid-Atlantic
Item 02 - DPL Supplemental Projects Presentation p. 7
DPL-2026-003 Oak Hall
Tasley
Status Engineering
Cost $300k
In service 10/30/2026
2026-10-16 SRRTEP Mid-Atlantic
Item 03 - PECO Supplemental Projects Presentation p. 3
PE-2026-016 Plymouth No figures printed
2026-10-16 SRRTEP Mid-Atlantic
Item 03 - PECO Supplemental Projects Presentation p. 4
PE-2026-017 Master No figures printed
2026-10-16 SRRTEP Mid-Atlantic
Item 03 - PECO Supplemental Projects Presentation p. 5
PE-2026-018 Burholme
Byberry
No figures printed
2026-10-16 SRRTEP Mid-Atlantic
Item 04 - BGE Supplemental Projects Presentation p. 3
Jennifer Rd to Cedar Park Wood Poles
BGE-2025-008
Bestgate
Cedar Park
Jennifer Rd
Status Engineering
Cost $8.1M
In service 12/31/2027
2026-10-16 SRRTEP Mid-Atlantic
Item 05 - DOM Supplemental Projects Presentation p. 4
Burlington Drive 115 kV DP – 3rd Feed - MEC
DOM-2026-0029
Burlington Drive DP Status Construction (Under construction)
Cost $0.010 M
In service 10/30/2026
Load approximately 30 MW
2026-10-16 SRRTEP Mid-Atlantic
Item 06 - JCPL Supplemental Projects Presentation p. 3
Taylor Lane Substation
JCPL-2026-048
Freneau
Keyport
Laurel Avenue
Red Bank
Roberts Road
Taylor Lane Substation
No figures printed
2026-10-16 SRRTEP Mid-Atlantic
Item 06 - JCPL Supplemental Projects Presentation p. 5
Wyckoff Street Substation
JCPL-2026-050
Englishtown
Windsor
Wyckoff Street
No figures printed
2026-10-16 SRRTEP Mid-Atlantic
Item 06 - JCPL Supplemental Projects Presentation p. 7
West Wharton Substation
JCPL-2026-053
West Wharton No figures printed
2026-10-16 SRRTEP Mid-Atlantic
Item 06 - JCPL Supplemental Projects Presentation p. 8
Melrose Substation
JCPL-2026-054
EH Werner
Melrose Substation
Raritan River Substation
No figures printed
2026-10-16 SRRTEP Mid-Atlantic
Item 06 - JCPL Supplemental Projects Presentation p. 9
Whitings Substation
JCPL-2026-055
Whitings No figures printed
2026-10-16 SRRTEP Mid-Atlantic
Item 06 - JCPL Supplemental Projects Presentation p. 11
New Providence Substation 34.5 kV Breaker Replacement
JCPL-2025-009
Air Reduction
Gillette
Murray Hill
New Providence
Status Conceptual
Cost $13.03 M
In service 05/31/2030
2026-10-16 SRRTEP Mid-Atlantic
Item 07 - MetEd Supplemental Projects Presentation p. 3
Cly - Smith Street 115 kV Line - Customer Connection
ME-2026-011
Cly
Smith Street
Status Conceptual
Cost $2.25 M
In service 06/01/2028
Load approximately 10 MW
2026-10-16 SRRTEP Mid-Atlantic
Item 08 - Penelec Supplemental Projects Presentation p. 3
Eagle Valley-Westfall 115 kV EVW Line Rebuild
PN-2019-036
Eagle Valley
Tyrone North Substation
Westfall
Status Conceptual
Cost $51.69 M
In service 06/14/2030
2026-10-16 SRRTEP Mid-Atlantic
Item 09 - PPL Supplemental Projects Presentation p. 3
POCO-JACK 69kV Improvements
PPL-2026-0047
None named In service 11/1/2029
2026-10-16 SRRTEP Mid-Atlantic
Item 09 - PPL Supplemental Projects Presentation p. 4
Penns Twin A Conversion
PPL-2026-0051
Penns In service 11/30/2030
2026-10-16 SRRTEP Mid-Atlantic
Item 09 - PPL Supplemental Projects Presentation p. 5
Twin Lakes Double Circuit
PPL-2026-0052
None named In service 5/30/2029
2026-10-16 SRRTEP Mid-Atlantic
Item 09 - PPL Supplemental Projects Presentation p. 6
McGovernville Twin A Conversion
PPL-2026-0053
McGovernville In service 11/30/2030
2026-10-16 SRRTEP Mid-Atlantic
Item 09 - PPL Supplemental Projects Presentation p. 7
Silver Spring Twin A Conversion
PPL-2026-0054
Sliver Spring In service 11/30/2029
2026-10-16 SRRTEP Mid-Atlantic
Item 09 - PPL Supplemental Projects Presentation p. 8
Roble Road MOS
PPL-2026-0055
None named In service 9/28/2029
Load 50MW
2026-10-16 SRRTEP Southern
Item 05 - DOM Supplemental Projects Presentation p. 4
Burlington Drive 115 kV DP – 3rd Feed - MEC
DOM-2026-0029
None named Status Construction (Under construction)
Cost $0.010 M
In service 10/30/2026
Load 30 MW
2026-10-16 SRRTEP Western
Item 01 - APS Supplemental Projects Presentation p. 3
Albright - Pruntytown 138 kV Line
APS-2026-014
Albright Substation
Kingwood
Pruntytown Substation
No figures printed
2026-10-16 SRRTEP Western
Item 01 - APS Supplemental Projects Presentation p. 5
Misoperation Relays
APS-2026-074
North Franklin
North Petersburg Substation
Seneca Caverns
No figures printed
2026-10-16 SRRTEP Western
Item 01 - APS Supplemental Projects Presentation p. 6
Misoperation Relays
APS-2026-073
Cecil
Crossgates
Peters
No figures printed
2026-10-16 SRRTEP Western
Item 01 - APS Supplemental Projects Presentation p. 7
Misoperation Relays
APS-2026-053
Edinburg
Strasburg
No figures printed
2026-10-16 SRRTEP Western
Item 01 - APS Supplemental Projects Presentation p. 8
Misoperation Relays
APS-2026-023
Black Oak
Cumberland
Short Gap
No figures printed
2026-10-16 SRRTEP Western
Item 01 - APS Supplemental Projects Presentation p. 9
Misoperation Relays
APS-2026-051
Bedington
Opequon
No figures printed
2026-10-16 SRRTEP Western
Item 01 - APS Supplemental Projects Presentation p. 10
New Customer Connection
APS-2026-078
Bedington
Reid
In service 1/1/2028
Load approximately 200 MW
2026-10-16 SRRTEP Western
Item 01 - APS Supplemental Projects Presentation p. 12
French Creek - Sutton 138 kV Line
APS-2026-012
French Creek
Sutton Substation
Status Conceptual
Cost $119.57 M
In service 05/06/2033
2026-10-16 SRRTEP Western
Item 01 - APS Supplemental Projects Presentation p. 15
Belmont – Long Reach 138 kV Line
APS-2024-093
Belmont
Long Reach
Status Conceptual
Cost $76.11 M
In service 11/27/2030
2026-10-16 SRRTEP Western
Item 01 - APS Supplemental Projects Presentation p. 18
Burma - Ridgway 138 kV Line
APS-2026-007
Burma
Clarion Substation
Ridgway
Status Conceptual
Cost $24.55 M
In service 06/22/2029
2026-10-16 SRRTEP Western
Item 02 - ATSI Supplemental Projects Presentation p. 3
Carlisle-Shinrock 138 kV Line
ATSI-2026-066
Carlisle
Concast Birmingham Tap
Shinrock
No figures printed
2026-10-16 SRRTEP Western
Item 02 - ATSI Supplemental Projects Presentation p. 4
Clark-Greene 138 kV Line
ATSI-2026-064
Clark
Green
Greene
No figures printed
2026-10-16 SRRTEP Western
Item 02 - ATSI Supplemental Projects Presentation p. 6
Old Plank 69 kV Ring Bus
ATSI-2019-070
Cascade
Cedar Street
Grant Street
New Wilmington
Old Plank
Shenango
Walmo
Status Conceptual
Cost $12.6 M
In service 12/29/2028
2026-10-16 SRRTEP Western
Item 02 - ATSI Supplemental Projects Presentation p. 9
Westgate Station 138 kV
ATSI-2024-009
Allen Junction Substation
Talmadge
Westgate Station
Status Conceptual
Cost $3.8 M
In service 05/26/2028
2026-10-16 SRRTEP Western
Item 02 - ATSI Supplemental Projects Presentation p. 11
New Customer Connection
ATSI-2026-059
Longview
Ontario
Status Conceptual
Cost $1.57 M
In service 06/26/2028
Load 10 MW
2026-10-16 SRRTEP Western
Item 02 - ATSI Supplemental Projects Presentation p. 13
New Customer Connection
ATSI-2026-061
Avon
Dawg Pound New
Eaton
Ford Brookpark Substation
Fowles
Fox
GM Cleveland (Parma)
Grovewood
Jim Brown New
Nasa
Pleasant Valley
Status Conceptual
Cost $13.78 M
In service 11/29/2029
Load 60 MW
2026-10-16 SRRTEP Western
Item 03 - AEP Supplemental Projects Presentation p. 3
Reno Switch - Mill Creek 138 kV Line
AEP-2026-OH040
Belmont
Duck Creek
Levee
Mill Creek
Reno SW
Reno Switch
No figures printed
2026-10-16 SRRTEP Western
Item 03 - AEP Supplemental Projects Presentation p. 4
Nickel Distribution Delivery
AEP-2026-OH036
Nickel New
Sterling
In service 12/2028
2026-10-16 SRRTEP Western
Item 03 - AEP Supplemental Projects Presentation p. 5
Pittsburgh Avenue Station
AEP-2026-OH038
Pittsburgh Avenue No figures printed
2026-10-16 SRRTEP Western
Item 03 - AEP Supplemental Projects Presentation p. 6
Bolton Station Distribution Delivery
AEP-2026-OH042
Bolton In service Q3 2027
2026-10-16 SRRTEP Western
Item 03 - AEP Supplemental Projects Presentation p. 7
Franklin Furnace Customer Delivery Point
AEP-2026-OH043
None named In service 3/31/2028
Load 20MW
2026-10-16 SRRTEP Western
Item 03 - AEP Supplemental Projects Presentation p. 8
Reedy Creek
AEP-2026-AP008
Lovedale
Orebank
Reedy Creek
Short Hills
Wellmont
No figures printed
2026-10-16 SRRTEP Western
Item 03 - AEP Supplemental Projects Presentation p. 11
Salamonie - Burr Oak 69 kV Line Solution
AEP-2019-IM031, AEP-2022-IM019
Bluff Point
Burr Oak
Jay
North Portland
Portland
Salamonie New
Status Scoping (Conceptual)
Cost $65.96 M
In service 12/14/2029
2026-10-16 SRRTEP Western
Item 04 - ComEd Supplemental Projects Presentation p. 3
138KV L10301 Circuit Switcher
ComEd-2026-014
Butterfield
Glen Ellyn Tap
Status Conceptual
Cost $183.2K
In service 12/31/2027
2026-10-16 SRRTEP Western
Item 04 - ComEd Supplemental Projects Presentation p. 5
138KV L14103 Transmission Switch
ComEd-2026-015
Algonquin Tap
North Huntley Tap
Status Conceptual
Cost $229.2K
In service 12/31/2028
2026-10-16 SRRTEP Western
Item 04 - ComEd Supplemental Projects Presentation p. 7
Mendota
ComEd-2026-016
Mendota Status Conceptual
Cost $4.85 M
In service 6/1/2030
2026-10-16 SRRTEP Western
Item 04 - ComEd Supplemental Projects Presentation p. 9
Burnham
ComEd-2026-017
Burnham Status Construction (Under construction)
Cost $1.4 M
In service 11/13/26
2026-10-16 SRRTEP Western
Item 05 - DEOK Supplemental Projects Presentation p. 3
Liberty 69 kV Ring Bus
DEOK-2026-005
Allen
Liberty
Shaker Run
No figures printed
2026-10-16 SRRTEP Western
Item 05 - DEOK Supplemental Projects Presentation p. 4
US_PO_SH 69 kV Substation Retirement
DEOK-2026-007
Allen
Kemper
US_PO_SH
Xtek
No figures printed
2026-10-16 SRRTEP Western
Item 05 - DEOK Supplemental Projects Presentation p. 5
Red Bank 138 kV Reliability Upgrade
DEOK-2026-008
Red Bank No figures printed
2026-10-16 SRRTEP Western
Item 05 - DEOK Supplemental Projects Presentation p. 6
US_PO_SH 69 kV Substation Retirement
DEOK-2026-010
US_PO_SH
Wyscarver
No figures printed
2026-10-16 SRRTEP Western
Item 06 - EKPC Supplemental Projects Presentation p. 3
Eli, KY
EKPC-2026-005
Salem No figures printed
2026-10-16 SRRTEP Western
Item 06 - EKPC Supplemental Projects Presentation p. 4
South Oak Hill
EKPC-2026-006
South Oakhill No figures printed
2026-10-16 SRRTEP Western
Item 07 - EKPC Supplemental Projects Presentation p. 3
Eli, KY
EKPC-2026-005
Salem No figures printed
2026-10-16 SRRTEP Western
Item 07 - EKPC Supplemental Projects Presentation p. 4
South Oak Hill
EKPC-2026-006
South Oakhill No figures printed
2026-10-07* SRRTEP Mid-Atlantic
Met-Ed local plan submission for 2026 RTEP p. 2
Round Top Substation
ME-2023-020 · s3733.1
Allen
Cly
Gardners
Round Top Substation
Roundtop Substation
Cost $22.1M
In service 6/2/2028
2026-10-07* SRRTEP Mid-Atlantic
Met-Ed local plan submission for 2026 RTEP p. 4
South Reading Substation
ME-2023-025 · s3742.1
South Reading Substation Cost $20.4M
In service 11/15/2027
2026-10-07* SRRTEP Mid-Atlantic
Met-Ed local plan submission for 2026 RTEP p. 6
Carlisle Pike – Gardners 115 kV 976 Line
ME-2024-008 · s3743.1
Gardners Cost $32.35M
In service 12/21/2029
2026-10-07* SRRTEP Mid-Atlantic
Met-Ed local plan submission for 2026 RTEP p. 8
Willis Road 115 kV Substation
ME-2023-002 · s3817.1
Smith Street
Willis Road New
Cost $25.00 M
In service 12/31/2027
2026-10-07* SRRTEP Mid-Atlantic
Met-Ed local plan submission for 2026 RTEP p. 10
Cleona – Campbelltown 69kV Line
ME-2023-009 · s3973.1
Campbelltown Substation Cost $32.33 M
In service 06/01/2028
2026-10-07* SRRTEP Mid-Atlantic
Met-Ed local plan submission for 2026 RTEP p. 12
Carpenter Technology Substation 69kV Circuit Breaker
ME-2024-021 · s3974.1
Carpenter Technology Substation Cost $1.01 M
In service 06/15/2027
2026-10-07* SRRTEP Mid-Atlantic
Met-Ed local plan submission for 2026 RTEP p. 14
South Reading - West Reading 69 kV Line
ME-2024-002 · s3975.1
South Reading Substation
West Reading
Cost $17.10M
In service 12/29/2028
2026-10-07* SRRTEP Mid-Atlantic
Met-Ed local plan submission for 2026 RTEP p. 16
Muhlenberg 69 kV Substation
ME-2024-005 · s3976.1
Carpenter Technology Substation
Lucent
Muhlenberg Substation
North Temple
Cost $29.29M
In service 10/22/2027
2026-10-07* SRRTEP Mid-Atlantic
Met-Ed local plan submission for 2026 RTEP p. 18
Frystown – South Lebanon 69 kV Line
ME-2024-022 · s3977.1
Frystown
South Lebanon
Cost $32.59M
In service 12/14/2029
2026-10-07* SRRTEP Mid-Atlantic
Met-Ed local plan submission for 2026 RTEP p. 20
Foxhill 230 kV Ring Bus
ME-2024-007 · s4015.1
Foxhill Substation
Monroe Substation
Shawnee Substation
Cost $11.80M
In service 12/21/2029
2026-10-07* SRRTEP Mid-Atlantic
Met-Ed local plan submission for 2026 RTEP p. 22
North Hanover 115 kV Breaker and a Half Substation
ME-2024-012 · s4016.1
Gitts Run
Hunterstown
Jackson
North Hanover
Cost $36.79M
In service 12/29/2028
2026-10-07* SRRTEP Mid-Atlantic
Met-Ed local plan submission for 2026 RTEP p. 24
Lincoln-Orrtanna 115 kV Customer Connection
ME-2025-001 · s4017.1
Lincoln Substation
Orrtanna Substation
Cost $3.06M
In service 04/08/2031
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 2
New Haven, Indiana
AEP-2023-IM026 · s3750.1-4
Allen
Zodiac New
Status Scoping (Conceptual)
Cost $169.1 M
In service 07/01/2029
Load 1200MW
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 5
MISO Tranche 2 Projects
AEP-2024-IM018 · s3608.1-7
Babcock
Batesville
Gwynneville New
Madison County New
Pike County New
Sorenson
Sullivan
Status Scoping (Conceptual)
Cost $0M
In service 2032-2034
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 8
New Carlisle, IN
AEP-2024-IM016 · s3763.1
Dumont
Navistar New
New Prairie
Status Scoping (Conceptual)
Cost $50.364 M
In service 03/15/2027
Load 437MW
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 10
New Carlisle Customer Needs
AEP-2023-IM020 · s3764.1-2
Creek Walker
Edison
Fillmore Road New
Olive
Status Scoping (Conceptual)
Cost $30.463 M
In service 05/09/2028
Load 90 MW
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 12
Dowagiac, MI
AEP-2024-IM011 · s3765.1
Hassle Switch New
Kenzie Creek
Valley
Status Engineering
Cost $3.719 M
In service 12/01/2025
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 14
Sand Branch, WV
AEP-2025-AP004 · s3825.1
Bradley
Kanawha
Pax Branch
Sand Branch New
Status Engineering
Cost 0
In service 11/14/2025
Load 7.5 MW
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 16
Pike County, KY
AEP-2023-AP006 · s3826.1-3
Johns Creek
Second Fork
Simers New
Status Engineering
Cost $3.99 M
In service 11/01/2025
Load 15 MW
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 18
Aloe Vera SW, WV
AEP-2025-AP003 · s3827.1
Aloe Vera SW New
Baileysville
Logan
Switchback
Trail Fork Stations
Status Engineering
Cost 0
In service 03/05/2026
Load 7MW
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 20
Elcona Tap, IN
AEP-2025-IM003 · s3828.1-4
Dunlap
East Elkhart
Elcona
Status Scoping (Conceptual)
Cost $18.128 M
In service 05/02/2029
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 22
Harrison, OH/Madison, OH
AEP-2025-OH001 · s3829.1-4
Erin Hills Switch New
Harrison
Madison
Status Engineering
Cost $11.015 M
In service 06/08/2029
Load 17.5 MW
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 24
Greif, OH/Huntley, OH/Busch, OH/Lazelle, OH
AEP-2025-OH003 · s3830.1
Busch
Greif
Huntley
Lazelle
Status Engineering
Cost $15.7 M
In service 03/03/2028
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 26
Windsor, OH
AEP-2025-OH004 · s3831.1-3
Carrollton
Krone Switch New
Sunnyside
Status Scoping (Conceptual)
Cost $2.455 M
In service 02/18/2027
Load 20 MW
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 28
Don Marquis, OH/Monza, OH/Customer, OH
AEP-2026-OH004 · s3864.1-6
Don Marquis
Monza New
Status Scoping (Conceptual)
Cost $156.6 M
In service 12/31/2027
Load 800 MW
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 30
East Leipsic, OH
AEP-2025-OH011 · s3837.1.
East Leipsic Status Engineering
Cost $10.624 M
In service 11/01/2027
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 32
Lockwood Rd., OH/Sowers, IN/South Hicksville, OH/Sowers, IN/Lockwood Rd., OH
AEP-2022-OH028 · s3836.1-3.
Lockwood Road
Sowers
Status Engineering
Cost $36.008 M
In service 04/26/2029
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 34
German, IN/Olive, IN/Notre Dame, IN
AEP-2025-IM002 · s3838.1-3.
German
Notre Dame
Olive
Status Scoping (Conceptual)
Cost $2.672 M
In service 09/29/2028
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 36
Helium Switch, OH/Forest3, OH/Upper Sandusky, OH
AEP-2025-OH009 · s3840.1-3.
Forest
Helium Switch New
Upper Sandusky
Status Engineering
Cost $4.901 M
In service 07/01/2026
Load 13.5MW
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 38
East Tiffin, OH/Mousey Switch, OH
AEP-2025-OH024 · s3842.1.
East Tiffin
Mousey Switch
West Rockaway
Status Engineering
Cost $19.174 M
In service 05/01/2027
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 40
Cleveland, IN/Capital Ave, IN/East Elkhart, IN
AEP-2025-IM006 · s3839.1-4.
Capital Avenue
Cleveland
East Elkhart
Status Scoping (Conceptual)
Cost $7.067 M
In service 12/31/2030
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 42
Abert, VA
AEP-2025-AP007 · s3841.1.
Abert Status Scoping (Conceptual)
Cost $3.4 M
In service 11/16/2029
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 44
Jennings Road Switch, OH/Sharp Road, OH/Commerce, OH
AEP-2024-OH028 · s3884.1-3.
Commerce
Jennings Road Switch
Sharp Road
Status Scoping (Conceptual)
Cost $2.575 M
In service 08/04/2027
Load 12.031 MW
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 46
S2888 Scope Change
AEP-2022-IM008 · S2888
Adams
Berne
Cost $19.45M
In service 2/13/2029
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 47
North Haverhill, OH
AEP-2022-OH002 · s3904.1.
North Haverhill Status Conceptual
Cost $12.985 M
In service 03/01/2027
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 49
Sancus Switch, OH
AEP-2025-OH002 · s3905.1.
Busch
Lazelle
Sancus Switch New
Status Engineering
Cost $4.44 M
In service 12/28/2027
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 51
s3440.3 Scope Change
AEP-2022-OH071 · s3440.1-.6
Beatty
Bixby
Cyprus
Marion station
Parsons
Saint Clair Avenue
Waverly
Status Scoping (Conceptual)
Cost $77.4M
In service 06/05/2027
Load 675 MW
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 53
Greenleaf, IN/Conant, IN/Elkhart Hydro, IN/Osolo, IN /Dunlap, IN/East Elkhart, IN/Wyland SS, IN /Middleton Run SS, IN/Middlebury, IN/Parkway, IN
AEP-2023-IM003, AEP-2023-IM005 · s3906.1-13
Conant
Dunlap
East Elkhart
Elkhart Hydro
Greenleaf
Middleton Run SS
Osolo
Wyland SS
Status Scoping (Conceptual)
Cost $20.647 M
In service 09/01/2028
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 57
Beatty, OH/Cyprus, OH
AEP-2026-OH001 · s3907.1-3
Beatty
Bixby
Cyprus
Status Engineering
Cost $5.218 M
In service 09/01/2026
Load 675 MW
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 59
West Moulton, OH/South Kossuth, OH
AEP-2022-OH022 · s3908.1
Kossuth
North Delphos
West Moulton
Status Engineering
Cost $23.396 M
In service 08/15/2029
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 61
Hannibal, OH
AEP-2024-OH039 · s3762.1
Hannibal
Kammer
North Sub Station
Status Scoping (Conceptual)
Cost $0.392 M
In service 07/17/2025
Load 200 MW
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 63
Wayne County, WV
AEP-2022-AP032 · s3952.1-3
East Lynn
Lavalette
Tri-State
Status Scoping (Conceptual)
Cost $98.8 M
In service 11/28/2029
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 65
Illinois Road, IN/Gateway, IN
AEP-2024-IM012 · s3953.1-2
Conrail SW New
Gateway
Illinois Road
Status Engineering
Cost $55.628 M
In service 08/15/2030
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 67
Thelma, KY/Big Sandy, KY/Busseyville, KY
AEP-2025-AP006 · s3954.1-4
Big Sandy
Busseyville
Thelma
Status Scoping (Conceptual)
Cost $169.555 M
In service 11/01/2030
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 69
Lancaster, OH
AEP-2024-OH031, AEP-2024-OH044 · s3955.1-6
Anchor Hocking
Memorial Drive
South Baltimore
West Lancaster
Status Engineering
Cost $33.852 M
In service 12/01/2028
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 72
Hanna, IN/Tanners Creek, IN
AEP-2025-IM010 · s3956.1
Batesville
Gwynneville
Hanna
Tanners Creek
Status Scoping (Conceptual)
Cost $520 M
In service 10/15/2031
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 75
Kenova, WV
AEP-2026-AP004 · s3957.1
Kenova Status In Service
Cost $0.6 M
In service 05/22/2026
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 77
Addison - Lick, Addison - Haners Upgrades
AEP-2022-OH067, AEP-2022-OH069 · s3958.1-8
Addison
Chickamauga New
Gavin
Haners
Lick
North Proctorville
Rio
Sporn
Status Scoping (Conceptual)
Cost $165.726 M
In service 10/08/2032
Load 20.6 MVA
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 86
Timken Mercy Rebuild
AEP-2023-OH009 · s3959.1-3
Eighth Street
Schroyer Avenue
Stadium Park
Timken Mercy
Status Engineering
Cost $7.195 M
In service 05/04/2028
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 90
Orrville, OH
AMPT-2023-004
Apple Ave
East Wooster
Mineral Springs New
Star-Cloverdale
Status Engineering
Cost $68.741M
In service 8/30/2030
Load 60 MW
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 93
Hannibal, WV
AEP-2025-OH012 · s4021.1-2
Hannibal Status Engineering
Cost $1.875 M
In service 10/26/2026
Load 570 MW
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 95
Canton Central, OH
AEP-2025-OH021 · s4022.1-5
Canton Central
Tidd
Triton New
Wagenhals
Status Engineering
Cost $21.961 M
In service 01/08/2028
Load 300MW
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 97
South Canton, OH/Torrey, OH
AEP-2025-OH007 · s4023.1-5
Petros New
South Canton
Timken Richville
Torrey
Status Engineering
Cost $49.124 M
In service 10/13/2027
Load 255 MW
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 99
Muskingum River, OH
AEP-2025-OH013 · s4024.1-2
Muskingum Status Conceptual
Cost $5.782 M
In service 12/06/2027
Load 200MW
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 101
Maliszewski Station Improvements
AEP-2026-OH008 · s4025.1-4
Hyatt
Maliszewski
Polaris
Status Scoping (Conceptual)
Cost $12.57 M
In service 09/15/2027
Load 25 MW
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 105
Ormet, OH
AEP-2024-OH040 · s4058.1-3
Hannibal
Kammer
Ormet
Stetson Run New
Status Scoping (Conceptual)
Cost $8.59 M
In service 06/01/2026
Load 266MW
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 107
New Albany, OH
AEP-2023-OH068 · s4060.1
Anguin
NBY-7 New
NBY6
Status Engineering
Cost $0.6 M
In service 8/1/2025
Load 720 MW
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 109
South East Canton, OH
AEP-2025-OH020 · s4061.1-4
South Canton
Southeast Canton
Sunnyside
Timken
Timken Richville
Torrey
Vettel New
Status Engineering
Cost $31.766 M
In service 01/07/2028
Load 312MW
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 111
Progress Park, VA
AEP-2026-AP001 · s4062.1-2
Progress Park Status Engineering
Cost $11.759 M
In service 02/08/2027
Load 240MW
2026-10-06 TEAC
Informational Only - ACE Local Plan Submission of Supplemental Projects for 2026 p. 2
ACE-2025-001 Beckett
Churchtown
Status Engineering
Cost $16M
In service Phase 1 – 4/28/2026, Phase 2 – 12/2029
Load 40 MW
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 2
New Haven, Indiana
AEP-2023-IM026 · s3750.1-4
Allen
Zodiac New
Status Scoping (Conceptual)
Cost $169.1 M
In service 07/01/2029
Load 1200MW
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 5
MISO Tranche 2 Projects
AEP-2024-IM018 · s3608.1-7
Babcock
Batesville
Gwynneville New
Madison County New
Pike County New
Sorenson
Sullivan
Status Scoping (Conceptual)
Cost $0M (PJM)
In service 2032-2034
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 8
New Carlisle, IN
AEP-2024-IM016 · s3763.1
Dumont
Navistar New
New Prairie
Status Scoping (Conceptual)
Cost $50.364 M
In service 03/15/2027
Load 437MW
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 10
New Carlisle Customer Needs
AEP-2023-IM020 · s3764.1-2
Creek Walker
Edison
Fillmore Road New
Olive
Status Scoping (Conceptual)
Cost $30.463 M
In service 05/09/2028
Load 90 MW
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 12
Dowagiac, MI
AEP-2024-IM011 · s3765.1
Hassle Switch New
Kenzie Creek
Valley
Status Engineering
Cost $3.719 M
In service 12/01/2025
Load 5.14 MVA
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 14
Pax Branch, WV
AEP-2025-AP004 · s3825.1
Bradley
Kanawha
Pax Branch
Sand Branch New
Status Engineering
Cost 0
In service 11/14/2025
Load 7.5 MW
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 16
Pike County, KY
AEP-2023-AP006 · s3826.1-3
Johns Creek
Second Fork
Simers New
Status Engineering
Cost $3.99 M
In service 11/01/2025
Load 15 MW
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 18
Trail Fork, WV
AEP-2025-AP003 · s3827.1
Aloe Vera SW New
Baileysville
Logan
Switchback
Trail Fork
Status Engineering
Cost 0
In service 03/05/2026
Load 7MW
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 20
Elcona Tap, IN
AEP-2025-IM003 · s3828.1-4
Dunlap
East Elkhart
Elcona
Elcona Tap
Status Scoping (Conceptual)
Cost $18.128 M
In service 05/02/2029
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 22
Harrison, OH/Madison, OH
AEP-2025-OH001 · s3829.1-4
Erin Hills Switch New
Harrison
Madison
Status Engineering
Cost $11.015 M
In service 06/08/2029
Load 17.5 MW
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 24
Greif, OH/Huntley, OH/Busch, OH/Lazelle, OH
AEP-2025-OH003 · s3830.1
Busch
Greif
Huntley
Lazelle
Status Engineering
Cost $15.7 M
In service 03/03/2028
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 26
Windsor, OH
AEP-2025-OH004 · s3831.1-3
Carrollton
Krone Switch New
Sunnyside
Status Scoping (Conceptual)
Cost $2.455 M
In service 02/18/2027
Load 20 MW
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 28
Don Marquis, OH
AEP-2026-OH004 · s3864.1-6
Don Marquis
Monza New
Status Scoping (Conceptual)
Cost $156.6 M
In service 12/31/2027
Load 800 MW
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 30
East Leipsic, OH
AEP-2025-OH011 · s3837.1
East Leipsic Status Engineering
Cost $10.624 M
In service 11/01/2027
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 32
Hicksville, OH
AEP-2022-OH028 · s3836.1-3
Lockwood Road
Sowers
Status Engineering
Cost $36.008 M
In service 04/26/2029
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 34
German, IN
AEP-2025-IM002 · s3838.1-3
German
Notre Dame
Olive
Status Scoping (Conceptual)
Cost $2.672 M
In service 09/29/2028
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 36
Forest3, OH/Upper Sandusky, OH
AEP-2025-OH009 · s3840.1-3
Forest
Helium Switch New
Upper Sandusky
Status Engineering
Cost $4.901 M
In service 07/01/2026
Load 13.5MW
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 38
East Tiffin, OH/Mousey Switch, OH
AEP-2025-OH024 · s3842.1
East Tiffin
Mousey Switch
Status Engineering
Cost $19.174 M
In service 05/01/2027
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 40
Cleveland, IN
AEP-2025-IM006 · s3839.1-4
Capital Avenue
Cleveland
East Elkhart
Status Scoping (Conceptual)
Cost $7.067 M
In service 12/31/2030
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 42
Abert, VA
AEP-2025-AP007 · s3841.1
Abert Status Scoping (Conceptual)
Cost $3.4 M
In service 11/16/2029
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 44
Mount Vernon, Ohio
AEP-2024-OH028 · s3884.1-3
Commerce
Jennings Road Switch
Sharp Road
Status Scoping (Conceptual)
Cost $2.575 M
In service 08/04/2027
Load 12.031 MW
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 46
S2888 Scope Change
AEP-2022-IM008 · S2888
Adams
Berne
Cost $19.45M
In service 2/13/2029
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 47
Haverhill, Ohio
AEP-2022-OH002 · s3904.1
North Haverhill Status Conceptual
Cost $12.985 M
In service 03/01/2027
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 49
Lazelle, OH/Bush, OH
AEP-2025-OH002 · s3905.1
Busch
Lazelle
Sancus Switch New
Status Engineering
Cost $4.44 M
In service 12/28/2027
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 51
s3440.3 Scope Change
AEP-2022-OH071 · s3440.3
Beatty
Bixby
Canal
Cyprus New
Marion station
Parsons
Waverly
Status Scoping (Conceptual)
Cost $77.4M
In service 06/05/2027
Load 675 MW
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 53
Elkhart, IN
AEP-2023-IM003, AEP-2023-IM005 · s3906.1-13
Conant
Dunlap
East Elkhart
Elkhart Hydro
Greenleaf
Middlebury Tap
Middleton Run SS
Osolo
Parkway Tap
Wyland SS
Status Scoping (Conceptual)
Cost $20.647 M
In service 09/01/2028
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 57
Bixby, OH/Beatty, OH
AEP-2026-OH001 · s3907.1-3
Cyprus Status Engineering
Cost $5.218 M
In service 09/01/2026
Load 675 MW
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 59
Auglaize County, OH
AEP-2022-OH022 · s3908.1
Kossuth
West Moulton
Status Engineering
Cost $23.396 M
In service 08/15/2029
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 61
Hannibal, OH
AEP-2024-OH039 · s3762.1
Hannibal
North Sub Station
Status Scoping (Conceptual)
Cost $0.392 M
In service 07/17/2025
Load 200 MW
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 63
Wayne County, WV
AEP-2022-AP032 · s3952.1-3
East Lynn
Lavalette
Tri-State
Status Scoping (Conceptual)
Cost $98.8 M
In service 11/28/2029
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 65
Illinois Road, IN/Gateway, IN
AEP-2024-IM012 · s3953.1-2
Conrail SW New
Gateway
Illinois Rd
Status Engineering
Cost $55.628 M
In service 08/15/2030
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 67
Thelma, KY/Big Sandy, KY/Busseyville, KY
AEP-2025-AP006 · s3954.1-4
Big Sandy
Busseyville
Thelma
Status Scoping (Conceptual)
Cost $169.555 M
In service 11/01/2030
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 69
Lancaster, OH
AEP-2024-OH031, AEP-2024-OH044 · s3955.1-6
Anchor Hocking
Memorial Drive
South Baltimore
West Lancaster
Status Engineering
Cost $33.852 M
In service 12/01/2028
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 72
Hanna, IN/Tanners Creek, IN
AEP-2025-IM010 · s3956.1
Batesville
Gwynneville
Hanna
Junction Tower
Tanners Creek
Status Scoping (Conceptual)
Cost $520 M
In service 10/15/2031
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 75
Kenova, WV
AEP-2026-AP004 · s3957.1
Kenova Status In Service
Cost $0.6 M
In service 05/22/2026
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 77
Addison - Lick, Addison - Haners Upgrades
AEP-2022-OH067, AEP-2022-OH069 · s3958.1-8
Addison
Chickamauga New
Gavin
Haners
Lick
Rio
Sporn
Status Scoping (Conceptual)
Cost $165.726 M
In service 10/08/2032
Load 20.6 MVA
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 86
Timken Mercy Rebuild
AEP-2023-OH009 · s3959.1-3
Schroyer Avenue
Stadium Park
Timken Mercy
Status Engineering
Cost $7.195 M
In service 05/04/2028
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 90
Orrville, OH
AMPT-2023-004
Apple Ave
East Wooster
Mineral Springs New
Status Engineering
Cost $68.741M
In service 8/30/2030
Load 60 MW
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 93
Hannibal, WV
AEP-2025-OH012 · s4021.1-2
Hannibal Status Engineering
Cost $1.875 M
In service 10/26/2026
Load 570 MW
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 95
Canton Central, OH
AEP-2025-OH021 · s4022.1-5
Canton Central
Triton New
Status Engineering
Cost $21.961 M
In service 01/08/2028
Load 300MW
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 97
South Canton, OH/Torrey, OH
AEP-2025-OH007 · s4023.1-5
Petros New
South Canton
Timken Richville
Torrey
Status Engineering
Cost $49.124 M
In service 10/13/2027
Load 255 MW
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 99
Muskingum River, OH
AEP-2025-OH013 · s4024.1-2
Muskingum River Status Conceptual
Cost $5.782 M
In service 12/06/2027
Load 200MW
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 101
Maliszewski Station Improvements
AEP-2026-OH008 · s4025.1-4
Hyatt
Maliszewski
Polaris
Status Scoping (Conceptual)
Cost $12.57 M
In service 09/15/2027
Load 25 MW
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 105
Ormet, OH
AEP-2024-OH040 · s4058.1-3
Hannibal
Kammer
Ormet
Status Scoping (Conceptual)
Cost $8.59 M
In service 06/01/2026
Load 266MW
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 107
New Albany, OH
AEP-2023-OH068 · s4060.1
Anguin
NBY-7 New
NBY6
Status Engineering
Cost $0.6 M
In service 8/1/2025
Load 720 MW
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 109
South East Canton, OH
AEP-2025-OH020 · s4061.1-4
South Canton
Southeast Canton
Sunnyside
Timken
Timken Richville
Torrey
Vettel New
Status Engineering
Cost $31.766 M
In service 01/07/2028
Load 312MW
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 111
Progress Park, VA
AEP-2026-AP001 · s4062.1-2
Progress Park Status Engineering
Cost $11.759 M
In service 02/08/2027
Load 240MW
2026-10-06 TEAC
Informational Only - AMPT Local Plan Submission of the Supplemental Projects for 2026 p. 2
AMPT Projects in DAY Transmission Zone M3 Process Versailles, OH
AMPT-2024-001 · s3734.1 (AMPT), s3734.2 (AMPT), s3734.3 (AMPT), s3734.4 (AMPT), s3734.5 (AMPT), s3734.6 (AMPT), s3734.7 (AES), s3734.8 (AES)
Baker Road New
Greenlawn
McGreevey Road Station New
Rossburg
Russia
Water Street
Water Street Tap
Status Engineering
Cost $66.6 M
In service 6/30/2028
Load 16 MW
2026-10-06 TEAC
Informational Only - AMPT Local Plan Submission of the Supplemental Projects for 2026 p. 5
AMPT Projects in ATSI Transmission Zone M3 Process Bowling Green, OH
AMPT-2025-003 · s3767.1 (AMPT)
Gypsy Lane Status Pre-Engineering (Engineering)
Cost $3.2M
In service 10/30/2027
2026-10-06 TEAC
Informational Only - AMPT Local Plan Submission of the Supplemental Projects for 2026 p. 7
AMPT Projects in AEP Transmission Zone M3 Process Orrville, OH
AMPT-2023-004 · s3832.1 (AMPT), s3832.2 (ATSI), s3832.3 (AMPT), s3832.4 (AMPT), s3832.5 (AMPT), s3832.6 (AEP)
Apple Ave
Cloverdale
East Wooster
Mineral Springs New
New FE switchyard New
Power Plant
Star
Status Engineering
Cost $68.741M
In service 8/30/2030
Load 60 MW
2026-10-06 TEAC
Informational Only - AMPT Local Plan Submission of the Supplemental Projects for 2026 p. 10
AMPT Transmission Zone M3 Process Niles Central 138 kV substation
AMPT-2025-005 · s3888.1 (AMPT) & s3888.2 (ATSI)
McDonald Steel
Niles
Niles Central
Status Pre-Engineering (Engineering)
Cost $14.1M
In service 08/01/2028
Load 63 MW
2026-10-06 TEAC
Informational Only - AMPT Local Plan Submission of the Supplemental Projects for 2026 p. 12
AMPT Transmission Zone M3 Process Poe Road - Tontogany 69 kV line
AMPT-2025-004 · s3889.1 (AMPT) & s3889.2 (ATSI)
Poe Road
Sand Ridge
Tontogany
Status Pre-Engineering (Engineering)
Cost $6.136 M
In service 11/30/2028
2026-10-06 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2026 p. 2
New Customer Connection
APS-2024-110 · s3755.1
Dutch Fork
Windsor
Status Conceptual
Cost $5.8 M
In service 08/14/2026
Load 20 MW
2026-10-06 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2026 p. 6
Leadsville – Loughs Lane 138 kV Misoperation Relays
APS-2024-112 · s3770.1
Leadsville Substation
Loughs Lane Substation
Cost $2.30M
In service 9/28/2029
2026-10-06 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2026 p. 9
Weirton - Wylie Ridge 138 kV Misoperation Relays
APS-2024-025 · s3771.1
Weirton Substation
Wylie Ridge Substation
Cost $4.50M
In service 07/20/2029
2026-10-06 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2026 p. 12
Rider – Weston 138 kV Line: Customer Connection
APS-2025-011 · s3772.1
Rider
Weston Substation
Cost $0.92 M
In service 4/29/2028
2026-10-06 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2026 p. 14
Gore - Hampshire 138 kV Line
APS-2024-029 · 3773.1
Gore Substation
Hampshire Substation
Cost $23.12M
In service 12/29/2028
2026-10-06 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2026 p. 16
Kammer Substation
APS-2025-020 · s3776.1
502 Junction Substation
Kammer Substation
Cost $9.25 M
In service 8/15/2030
2026-10-06 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2026 p. 18
Oak Mound Control Building and Breakers
APS-2024-095 · s3777.1
Glen Falls Substation
Oak Mound Substation
Quiet Dell Substation
Cost $13.35M
In service 6/16/2028
2026-10-06 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2026 p. 21
Misoperation Relays: Oak Mound - Quiet Dell 138 kV Line
APS-2024-089 · s3778.1
Oak Mound Substation
Quiet Dell Substation
Cost $2.63M
In service 6/16/2028
2026-10-06 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2026 p. 24
Misoperation Relays: Armstrong - Kittanning 138 kV Line
APS-2024-010 · s3865.1
Armstrong Substation
Kittanning Substation
Cost $3.44M
In service 09/10/2029
2026-10-06 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2026 p. 27
Misoperation Relays: Shepler Hill Junction (Charleroi - Mitchell - Yukon) 138 kV Line
APS-2024-102 · s3866.1
Belmon
Charleroi
Mitchell
Smithton Substation
Yukon
Cost $3.71M
In service 10/31/2028
2026-10-06 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2026 p. 31
Misoperation Relays: Cecil – Enlow 138 kV Line
APS-2024-105 · s3867.1
Cecil
Enlow
Cost $4.0M
In service 06/11/2029
2026-10-06 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2026 p. 34
Price Hill Substation
APS-2025-028 · s3868.1
Price Hill Substation Cost $0.10M
In service 04/03/2026
2026-10-06 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2026 p. 36
Eaglehead - Monocacy 230 kV Line
APS-2025-003 · s3869.1
Eaglehead Substation
Monocacy Substation
Cost $3.88M
In service 08/24/2029
2026-10-06 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2026 p. 38
Wylie Ridge No. 3 345/138 kV Transformer
APS-2024-079 · s3870.1
Wylie Ridge Substation Cost $13.45M
In service 12/13/2030
2026-10-06 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2026 p. 40
Carroll - Mount Airy 230 kV line
APS-2023-058 · s3871.1
Carroll
Mt. Airy
Cost $50M
In service 06/30/2029
2026-10-06 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2026 p. 42
Elko No. 1 230/138 kV Transformer
APS-2025-012 · s3874.1
Elko Substation Cost $6.69M
In service 06/01/2028
2026-10-06 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2026 p. 44
Grand Point – Roxbury 138 kV
APS-2024-028 · s3880.1
Grand Point
Greene Substation
Letterkenny Substation
Roxbury Substation
Cost $28.34M
In service 06/15/2029
2026-10-06 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2026 p. 47
Junction – Parr Run 138 kV
APS-2024-096 · s3875.1
None named Cost $35M
In service 06/16/2028
2026-10-06 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2026 p. 49
Page-Riverton 138 kV New Customer
APS-2023-014 · s3127.1
Catlett Mountain New Status Cancellation (Cancelled)
Cost $16M
In service 05/30/2025
2026-10-06 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2026 p. 51
Yukon No. 7 500/138 kV Transformer
APS-2025-030 · s3885.1
Yukon Cost $0.41M
In service 12/31/2026
2026-10-06 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2026 p. 53
Loughs Lane - Pickens 138 kV Line
APS-2025-016 · s3886.1
None named Cost $1.05M
In service 12/31/2026
2026-10-06 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2026 p. 55
Glenville - Weston 138 kV Line
APS-2024-074 · s3887.1
Glenville
Weston Substation
Cost $89.52M
In service 12/15/2030
2026-10-06 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2026 p. 58
Bethel Park, PA
APS-2025-026
Bethel Park Substation No figures printed
2026-10-06 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2026 p. 60
North Shenandoah – Page 138 kV Line
APS-2024-085 · s3937.1
North Shenandoah Substation
Page
Cost $4.06M
In service 06/01/2029
2026-10-06 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2026 p. 62
Loughs Lane – Pickens 138 kV Line
APS-2023-032 · s3938.1
Beverly Substation
Durbin Substation
Loughs Lane Substation
Pickens
Cost $182.84M
In service 11/04/2032
2026-10-06 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2026 p. 65
Gordon – Nyswaner 138kV Line
APS-2024-055 · s3939.1
Gordon
Nyswaner
Cost $30.12M
In service 12/29/2028
2026-10-06 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2026 p. 68
Dutch Fork – Enon 138 kV Line
APS-2023-033 · s3930.1
Dutch Fork
Enon Substation
Cost $41.70M
In service 12/08/2029
2026-10-06 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2026 p. 70
Misoperation Relay Projects
APS-2024-101
None named No figures printed
2026-10-06 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2026 p. 72
Rhodes Lane - Yukon 500 kV Line
APS-2025-029 · s3931.1
Rhodes Lane Substation
Yukon
Cost $5.45M
In service 05/12/2028

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Latest · October 2026 (547) · September 2026 (830) · August 2026 (58) · July 2026 (80) · June 2026 (64) · May 2026 (90) · April 2026 (85) · March 2026 (71) · February 2026 (74) · January 2026 (69) · December 2025 (82) · November 2025 (156) · October 2025 (355) · September 2025 (219) · August 2025 (33) · July 2025 (40) · June 2025 (34) · May 2025 (41) · April 2025 (50) · March 2025 (56) · February 2025 (63) · January 2025 (42) · December 2024 (89) · November 2024 (138) · October 2024 (496)