Substation Scout

Chickahominy

Named in 14 PJM planning documents for 11 projects, from December 3, 2024 to October 6, 2026.

Existingdescribed as
DOMzone
230kV, 500 kV, 500/230 kVkV as printed
19mentions

Also printed as: Chickahominy substation

PJM interconnection queue

A PJM queue substation page has the same name: Chickahominy (VA) — 11 queue requests filed, 1 active.

Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Dominion Transmission Zone: Baseline Second Chickahominy 500/230kV Transformer
b3213
Not printed $34.03M 6/1/2023 Not printed 2026-04-07
TEAC
Dominion Transmission Zone: Baseline 500kV Line #557 Elmont-Chickahominy
b3692
Not printed $185.16 M 6/30/2028 Not printed 2025-05-06
TEAC
Regional Solution: 2025-W1-275 Portfolio
b4053.1
Not printed $4832.45 6/1/2032 Not printed 2026-01-06
TEAC
Customer Load Request
DOM-2019-0021, DOM-2024-0022, DOM-2024-0023, DOM-2024-0024 - DNH
Conceptual 101.7M Q4 2030 Not printed 2026-07-07
TEAC
Dominion Transmission Zone: Supplemental Do No Harm Analysis
DOM-2024-0018 · s3673
Engineering $20M Substation, $5M Transmission Line Q4 2027 255.0 MW 2025-10-08
TEAC
Gray Bark 230kV Delivery - DEV
DOM-2024-0019 · s3676
Engineering $20M Substation, $20M Transmission Lines Q3 2027 300.0 MW 2025-10-08
TEAC
Stockholm 230kV Delivery - DEV
DOM-2024-0049 · s3995
Conceptual $ 26M Q4 2028 300 MW 2026-10-06
TEAC
Dominion Transmission Zone: Supplemental Operational Flexibility and Efficiency
DOM-2024-0051 · s3999
Engineering $185M 12/31/2030 Not printed 2026-10-06
TEAC
Dominion Transmission Zone: Supplemental Equipment Material Condition, Performance and Risk
DOM-2025-0026 · s3915
Engineering $160M 12/31/2028 Not printed 2026-10-06
TEAC
Equipment Material Condition, Performance and Risk
DOM-2025-0026 Update
Engineering $160M 12/31/2028 Not printed 2025-09-09
TEAC
Dominion Transmission Zone: Baseline Regional Solution: 2025-W1-275 Portfolio
2025-W1-275
Not printed Not printed 6/1/2032 Not printed 2025-12-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate
prior value printed on the same page
$31.05M → $34.03M 2026-04-07 2026-04-07
Cost estimate
prior value printed on the same page
$58.155 M → $185.16 M 2025-05-06 2025-05-06
Cost estimate $101.7M → $15.0 M 2026-10-06 Not reported
Cost estimate $15.0 M → $92.7M 2024-10-08 2024-12-03
Cost estimate
prior value printed on the same page
$92.7M → $95.1M 2026-01-06 2026-01-06
Cost estimate $92.7M → $95.1M 2025-10-08 2026-01-06
Cost estimate
prior value printed on the same page
$95.1M → 101.7M 2026-07-07 2026-07-07
Cost estimate $95.1M → 101.7M 2026-01-06 2026-07-07
Cost estimate
prior value printed on the same page
$92.7M → $101.7M 2026-10-06 2026-10-06
In-service date Q4 2030 → Q4 2026 2026-10-06 Not reported
In-service date Q4 2026 → Q4 2028 2024-10-08 2024-12-03
In-service date Q4 2028 → Q4 2030 2026-01-06 2026-07-07
Status conceptual (Conceptual) → engineering (Engineering) 2026-10-06 Not reported
Status engineering (Engineering) → conceptual (Conceptual) 2026-01-06 2026-07-07
Substations named ENON; HOPEWELL; MEADOWVILLE; SHAND CREEK; SYCAMORE SPRINGS → ALLIED; BERMUDA HUNDRED; ICI 2026-10-06 Not reported
Substations named ALLIED; BERMUDA HUNDRED; ICI → BERMUDA HUNDRED; CHICKAHOMINY; ENON; MEADOWVILLE; SYCAMORE SPRINGS 2024-10-08 2024-12-03
Substations named BERMUDA HUNDRED; CHICKAHOMINY; ENON; MEADOWVILLE; SYCAMORE SPRINGS → ENON; MEADOWVILLE; SYCAMORE SPRINGS 2024-12-03 2025-10-08
Substations named ENON; MEADOWVILLE; SYCAMORE SPRINGS → BERMUDA HUNDRED; CHICKAHOMINY; ENON; MEADOWVILLE; SHAND CREEK; SYCAMORE SPRINGS 2025-10-08 2026-01-06
Substations named BERMUDA HUNDRED; CHICKAHOMINY; ENON; MEADOWVILLE; SHAND CREEK; SYCAMORE SPRINGS → BERMUDA HUNDRED; CHICKAHOMINY; ENON; HOPEWELL; MEADOWVILLE; SHAND CREEK; SYCAMORE SPRINGS 2026-01-06 2026-07-07
Substations named BERMUDA HUNDRED; CHICKAHOMINY; ENON; HOPEWELL; MEADOWVILLE; SHAND CREEK; SYCAMORE SPRINGS → ENON; HOPEWELL; MEADOWVILLE; SHAND CREEK; SYCAMORE SPRINGS 2026-07-07 2026-10-06
In-service date Q4 2027 → 12/01/2030 2025-01-07 2025-05-06
In-service date 12/01/2030 → Q4 2027 2025-05-06 2025-10-08
Status engineering (Engineering) → conceptual (Conceptual) 2025-01-07 2025-05-06
Status conceptual (Conceptual) → engineering (Engineering) 2025-05-06 2025-10-08
Substations named CHICKAHOMINY; ELMONT; THICKET; WHITE OAK → BERMUDA HUNDRED; CHICKAHOMINY; DARBYTOWN; ELKO; ELMONT; TECHPARK PLACE; THICKET; WHITE OAK 2025-01-07 2025-05-06
Substations named STOCKHOLM; THICKET → CHICKAHOMINY; ELMONT; STOCKHOLM; THICKET; WHITE OAK 2026-05-08 2026-10-06
Cost estimate
prior value printed on the same page
$108M → $165M 2026-06-02 2026-06-02
Cost estimate Transmission: $108M; Substation: $15M → $165M 2025-06-05 2026-06-02
Cost estimate $165M → $185M 2026-06-02 2026-10-06
Status conceptual (Conceptual) → engineering (Engineering) 2025-06-05 2026-06-02
Cost estimate $54M → $160M 2025-07-08 2026-10-06
Substations named CHESTERFIELD; CHICKAHOMINY; LADYSMITH; LANEXA; POSSUM POINT; PROVIDENCE FORGE; TURNER → CHESTERFIELD; LANEXA; PROVIDENCE FORGE; TURNER 2025-06-05 2025-07-08
Substations named CHESTERFIELD; LANEXA; PROVIDENCE FORGE; TURNER → CHESTERFIELD; CHICKAHOMINY; LANEXA; PROVIDENCE FORGE; TURNER 2025-07-08 2026-10-06
Cost estimate
prior value printed on the same page
$54M → $160M 2025-09-09 2025-09-09

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2026 p. 60
Stockholm 230kV Delivery - DEV No role wording
2026-10-06 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2026 p. 69
Dominion Transmission Zone: Supplemental Operational Flexibility and Efficiency “Terminate one 230kV conductor rated at 1573 MVA at Thornburg and Chickahominy.”
2026-10-06 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2026 p. 94
Dominion Transmission Zone: Supplemental Equipment Material Condition, Performance and Risk No role wording
2026-07-07 TEAC
Item 14 - DOM Supplemental Projects p. 16
Customer Load Request “existing Chickahominy substation”
2026-06-02 TEAC
Item 11 - DOM Supplemental Projects p. 12
Dominion Transmission Zone: Supplemental Operational Flexibility and Efficiency No role wording
2026-04-07 TEAC
Item 11 - Reliability Analysis Update p. 18
Dominion Transmission Zone: Baseline Second Chickahominy 500/230kV Transformer “Reconfigure 500kV portion of substation into a ring bus”
500/230 kV
2026-01-06 TEAC
Item 07 - DOM Supplemental Projects p. 23
Customer Load Request “existing Chickahominy substation”
2026-01-06 TEAC
Item 09 - Reliability Analysis Update p. 31
Regional Solution: 2025-W1-275 Portfolio “Uprate Line 567 associated terminal equipment at Chickahominy to 5000A standards.”
500 kV
2025-12-08 TEAC
Item 11 - Reliability Analysis Update p. 77
Dominion Transmission Zone: Baseline Regional Solution: 2025-W1-275 Portfolio “Uprate Line 567 associated terminal equipment at Chickahominy to 5000A standards.”
2025-10-08 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2025 p. 25
Dominion Transmission Zone: Supplemental Do No Harm Analysis “back to Chickahominy substation”
2025-10-08 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2025 p. 31
Gray Bark 230kV Delivery - DEV No role wording
2025-09-09 TEAC
Item 14 - DOM Supplemental Projects p. 3
Equipment Material Condition, Performance and Risk No role wording
2025-06-05 TEAC
Item 08 - DOM Supplemental Projects p. 10
Dominion Transmission Zone: Supplemental Operational Flexibility and Efficiency No role wording
2025-06-05 TEAC
Item 08 - DOM Supplemental Projects p. 4
Dominion Transmission Zone: Supplemental Equipment Material Condition, Performance and Risk No role wording
2025-05-06 TEAC
Item 09 - DOM Supplemental Projects p. 8
Dominion Transmission Zone: Supplemental Do No Harm Analysis “back to Chickahominy substation”
2025-05-06 TEAC
Item 10 - Reliability Analysis Update p. 8
Dominion Transmission Zone: Baseline 500kV Line #557 Elmont-Chickahominy No role wording
2025-01-07 TEAC
Item 10 - Dominion Supplemental Projects p. 10
Gray Bark 230kV Delivery - DEV No role wording
230kV
2025-01-07 TEAC
Item 10 - Dominion Supplemental Projects p. 4
Dominion Transmission Zone: Supplemental Do No Harm Analysis No role wording
230kV
2024-12-03 TEAC
Item 10 - Dominion Supplemental Projects p. 19
Customer Load Request “existing Chickahominy substation”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this