Substation Scout

Yadkin

Named in 5 PJM planning documents for 5 projects, from December 3, 2024 to October 6, 2026.

Existingdescribed as
DOMzone
500kVkV as printed
5mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Baseline 500kV Line #588 Rebuild (End of Life Criteria)
b3850.1 – b3850.3
Not printed $113.8M 12/31/2026 Not printed 2026-10-06
TEAC
500kV Line #579 Rebuild (End of Life Criteria)
b3929.1
Not printed $216.78 M 6/1/2029 Not printed 2025-01-07
TEAC
Dominion Transmission Zone: Baseline 500kV Line #565 Rebuild (End of Life Criteria)
b4030.6
Not printed $74.3 M 6/1/2030 Not printed 2025-12-08
TEAC
500kV Line #579 Rebuild (End of Life Criteria)
DOM-O1
Not printed $216.78 M 6/1/2029 Not printed 2024-12-03
TEAC
Hopewell – Chesterfield – Basin 230 kV
2025-W1-911
Not printed $113.55 M 6/1/2030 Not printed 2025-11-04
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate
prior value printed on the same page
$79.7 M → $113.8M 2026-10-06 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Item 16 - Reliability Analysis Update - Presentation p. 6
Baseline 500kV Line #588 Rebuild (End of Life Criteria) “structure 588/184 inside Yadkin substation”
2025-12-08 TEAC
Item 11 - Reliability Analysis Update p. 22
Dominion Transmission Zone: Baseline 500kV Line #565 Rebuild (End of Life Criteria) “Uprate Line 565 equipment at Yadkin substations to 5000A”
500kV
2025-11-04 TEAC
Item 14 - Reliability Analysis Update p. 31
Hopewell – Chesterfield – Basin 230 kV “Uprate Line 565 equipment at Suffolk & Yadkin substations to 5000A”
500kV
2025-01-07 TEAC
Item 12 - Reliability Analysis Update p. 54
500kV Line #579 Rebuild (End of Life Criteria) “At Yadkin substation, upgrade line leads to 5000A rating to support Line #579 rebuild”
500kV
2024-12-03 TEAC
Item 11 - Reliability Analysis Update p. 74
500kV Line #579 Rebuild (End of Life Criteria) “At Yadkin substation, upgrade line leads”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this