Substation Scout

Glen Gardner

Named in 8 PJM planning documents for 5 projects, from February 4, 2025 to October 6, 2026.

Existingdescribed as
JCPLzone
230 kV, 230-34.5 kV, 34.5 kVkV as printed
11mentions

Also printed as: Glen Gardner substation

PJM interconnection queue

A PJM queue substation page has the same name: Glen Gardner (NJ) — 3 queue requests filed, 1 active.

Same name and state (weaker). Matched on name and state: the utility that presented this substation operates in one state, and every queue filing at a substation of the same name is in that state. No transmission owner is recorded on those filings, so this is a weaker match than one on owner. Not verified as the same facility.

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Gilbert and Glen Gardner Substations
JCPL-2023-047 · s3257.1
Not printed $5.2M 04/04/2025 Not printed 2026-09-08*
SRRTEP Mid-Atlantic
Glen Gardner No. 1 230-34.5 kV Transformer
JCPL-2024-022 · s3960.1
Not printed $7.35 M 11/17/2028 Not printed 2026-10-06
TEAC
Glen Gardner No. 8 230-34.5 kV Transformer
JCPL-2024-031 · s3961.1
Not printed $7.35 M 06/07/2028 Not printed 2026-10-06
TEAC
Glen Gardner No. 2 230-34.5 kV Transformer
JCPL-2024-043 · s3620.1
Not printed $7.5 M 05/01/2025 Not printed 2025-10-08
TEAC
East Flemington Substation, NJ
JCPL-2026-005
Not printed Not printed Not printed Not printed 2026-02-12
SRRTEP Mid-Atlantic

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - JCPL Local Plan Submission of Supplemental Projects for 2026 p. 18
Glen Gardner No. 1 230-34.5 kV Transformer “Replace the Glen Gardner No. 1 230-34.5 kV Transformer”
230-34.5 kV
2026-10-06 TEAC
Informational Only - JCPL Local Plan Submission of Supplemental Projects for 2026 p. 20
Glen Gardner No. 8 230-34.5 kV Transformer “Replace the Glen Gardner No. 8 230-34.5 kV Transformer”
230-34.5 kV
2026-10-01* SRRTEP Mid-Atlantic
JCPL local plan submission for 2026 RTEP p. 18
Glen Gardner No. 1 230-34.5 kV Transformer “Replace the Glen Gardner No. 1 230-34.5 kV Transformer”
230-34.5 kV
2026-10-01* SRRTEP Mid-Atlantic
JCPL local plan submission for 2026 RTEP p. 20
Glen Gardner No. 8 230-34.5 kV Transformer “Replace the Glen Gardner No. 8 230-34.5 kV Transformer”
230-34.5 kV
2026-09-08* SRRTEP Mid-Atlantic
JCPL local plan submission for 2025 RTEP p. 33
Glen Gardner No. 2 230-34.5 kV Transformer “Replace the 230-34.5 kV No. 2 Transformer at Glen Gardner substation.”
2026-09-08* SRRTEP Mid-Atlantic
JCPL local plan submission for 2024 RTEP p. 29
Gilbert and Glen Gardner Substations “Replace limiting substation equipment at Gilbert and Glen Gardner substations”
230 kV
2026-02-12 SRRTEP Mid-Atlantic
Item 02 - JCPL Supplemental Projects p. 5
East Flemington Substation, NJ No role wording
34.5 kV
2025-12-08 TEAC
Item 06 - JCPL Supplemental Projects p. 4
Glen Gardner No. 1 230-34.5 kV Transformer “Replace the Glen Gardner No. 1 230-34.5 kV Transformer”
230-34.5 kV
2025-12-08 TEAC
Item 06 - JCPL Supplemental Projects p. 6
Glen Gardner No. 8 230-34.5 kV Transformer “Replace the Glen Gardner No. 1 230-34.5 kV Transformer”
230-34.5 kV
2025-10-08 TEAC
Informational Only - JCPL Local Plan Submission of the Supplemental Projects for 2025 p. 33
Glen Gardner No. 2 230-34.5 kV Transformer “Replace the 230-34.5 kV No. 2 Transformer at Glen Gardner substation.”
230-34.5 kV
2025-02-04 TEAC
Item 06 - JCPL Supplemental Projects p. 4
Glen Gardner No. 2 230-34.5 kV Transformer “Replace the 230-34.5 kV No. 2 Transformer at Glen Gardner substation”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this