Glen Gardner
Named in 8 PJM planning documents for 5 projects, from February 4, 2025 to October 6, 2026.
Also printed as: Glen Gardner substation
PJM interconnection queue
A PJM queue substation page has the same name: Glen Gardner (NJ) — 3 queue requests filed, 1 active.
Same name and state (weaker). Matched on name and state: the utility that presented this substation operates in one state, and every queue filing at a substation of the same name is in that state. No transmission owner is recorded on those filings, so this is a weaker match than one on owner. Not verified as the same facility.
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| Gilbert and Glen Gardner Substations JCPL-2023-047 · s3257.1 |
Not printed | $5.2M | 04/04/2025 | Not printed | 2026-09-08* SRRTEP Mid-Atlantic |
| Glen Gardner No. 1 230-34.5 kV Transformer JCPL-2024-022 · s3960.1 |
Not printed | $7.35 M | 11/17/2028 | Not printed | 2026-10-06 TEAC |
| Glen Gardner No. 8 230-34.5 kV Transformer JCPL-2024-031 · s3961.1 |
Not printed | $7.35 M | 06/07/2028 | Not printed | 2026-10-06 TEAC |
| Glen Gardner No. 2 230-34.5 kV Transformer JCPL-2024-043 · s3620.1 |
Not printed | $7.5 M | 05/01/2025 | Not printed | 2025-10-08 TEAC |
| East Flemington Substation, NJ JCPL-2026-005 |
Not printed | Not printed | Not printed | Not printed | 2026-02-12 SRRTEP Mid-Atlantic |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-10-06 | TEAC Informational Only - JCPL Local Plan Submission of Supplemental Projects for 2026 p. 18 |
Glen Gardner No. 1 230-34.5 kV Transformer | “Replace the Glen Gardner No. 1 230-34.5 kV Transformer” 230-34.5 kV |
| 2026-10-06 | TEAC Informational Only - JCPL Local Plan Submission of Supplemental Projects for 2026 p. 20 |
Glen Gardner No. 8 230-34.5 kV Transformer | “Replace the Glen Gardner No. 8 230-34.5 kV Transformer” 230-34.5 kV |
| 2026-10-01* | SRRTEP Mid-Atlantic JCPL local plan submission for 2026 RTEP p. 18 |
Glen Gardner No. 1 230-34.5 kV Transformer | “Replace the Glen Gardner No. 1 230-34.5 kV Transformer” 230-34.5 kV |
| 2026-10-01* | SRRTEP Mid-Atlantic JCPL local plan submission for 2026 RTEP p. 20 |
Glen Gardner No. 8 230-34.5 kV Transformer | “Replace the Glen Gardner No. 8 230-34.5 kV Transformer” 230-34.5 kV |
| 2026-09-08* | SRRTEP Mid-Atlantic JCPL local plan submission for 2025 RTEP p. 33 |
Glen Gardner No. 2 230-34.5 kV Transformer | “Replace the 230-34.5 kV No. 2 Transformer at Glen Gardner substation.” |
| 2026-09-08* | SRRTEP Mid-Atlantic JCPL local plan submission for 2024 RTEP p. 29 |
Gilbert and Glen Gardner Substations | “Replace limiting substation equipment at Gilbert and Glen Gardner substations” 230 kV |
| 2026-02-12 | SRRTEP Mid-Atlantic Item 02 - JCPL Supplemental Projects p. 5 |
East Flemington Substation, NJ | No role wording 34.5 kV |
| 2025-12-08 | TEAC Item 06 - JCPL Supplemental Projects p. 4 |
Glen Gardner No. 1 230-34.5 kV Transformer | “Replace the Glen Gardner No. 1 230-34.5 kV Transformer” 230-34.5 kV |
| 2025-12-08 | TEAC Item 06 - JCPL Supplemental Projects p. 6 |
Glen Gardner No. 8 230-34.5 kV Transformer | “Replace the Glen Gardner No. 1 230-34.5 kV Transformer” 230-34.5 kV |
| 2025-10-08 | TEAC Informational Only - JCPL Local Plan Submission of the Supplemental Projects for 2025 p. 33 |
Glen Gardner No. 2 230-34.5 kV Transformer | “Replace the 230-34.5 kV No. 2 Transformer at Glen Gardner substation.” 230-34.5 kV |
| 2025-02-04 | TEAC Item 06 - JCPL Supplemental Projects p. 4 |
Glen Gardner No. 2 230-34.5 kV Transformer | “Replace the 230-34.5 kV No. 2 Transformer at Glen Gardner substation” |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.