Named in 1 PJM planning document for 1 project, on December 12, 2025.

Not stateddescribed as
ATSIzone
69 kVkV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Black River - Willow Creek 69 kV
ATSI-2025-035
Conceptual $1.53M 12/31/2026 Not printed 2025-12-12
SRRTEP Western

Every mention

DateDocumentProjectWhat the document says about it
2025-12-12 SRRTEP Western
Item 13 - ATSI Supplemental Projects p. 17
Black River - Willow Creek 69 kV No role wording