Mausdale

Named in 4 PJM planning documents for 1 project, from December 11, 2025 to October 6, 2026.

Newdescribed as
PPLzone
69-12kVkV as printed
4mentions

Described as new: “Install new Mausdale 69-12kV substation” — source, page 32

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Mausdale, PA
PPL-2025-0030
Engineering $3.6 M 03/30/2028 Not printed 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date 3/2028 → 03/30/2028 2025-12-11 2026-02-12
Substations named MAUSDALE → COLUMBIA; MAUSDALE; SUNBURY 2025-12-11 2026-02-12

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2026 p. 33
Mausdale, PA “Install new Mausdale 69-12kV substation”
69-12kV
2026-09-17* SRRTEP Mid-Atlantic
PPL local plan submission for 2026 RTEP p. 32
Mausdale, PA “Install new Mausdale 69-12kV substation”
69-12kV
2026-02-12 SRRTEP Mid-Atlantic
Item 05 - PPL Supplemental Projects p. 18
Mausdale, PA “Install new Mausdale 69-12kV substation”
69-12kV
2025-12-11 SRRTEP Mid-Atlantic
Item 11 - PPL Supplemental Projects p. 8
Mausdale, PA “new 69-12kV Substation (Mausdale)”
69-12kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.