Substation Scout

Hopewell

Named in 6 PJM planning documents for 4 projects, from May 6, 2025 to October 6, 2026.

Existingdescribed as
DOMzone
230kVkV as printed
6mentions

Also printed as: Hopewell substation · Hopewell Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Dominion Transmission Zone: Baseline Hopewell – Chesterfield – Basin 230 kV
b4030.1
Not printed $113.55 M 6/1/2030 Not printed 2025-12-08
TEAC
Do No Harm Analysis
DOM-2019-0021, DOM-2024-0022, DOM-2024-0023, DOM-2024-0024 – DNH · s3672
Conceptual $101.7M Q4 2030 Not printed 2026-10-06
TEAC
Do No Harm Analysis
DOM-2024-0023 - DNH · s3671
Conceptual Lines 211 and 228: $33M Line 238: $112M Q4 2030 300MW 2025-10-08
TEAC
Hopewell – Chesterfield – Basin 230 kV
2025-W1-911
Not printed $113.55 M 6/1/2030 Not printed 2025-11-04
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate $101.7M → $15.0 M 2026-10-06 Not reported
Cost estimate $15.0 M → $92.7M 2024-10-08 2024-12-03
Cost estimate
prior value printed on the same page
$92.7M → $95.1M 2026-01-06 2026-01-06
Cost estimate $92.7M → $95.1M 2025-10-08 2026-01-06
Cost estimate
prior value printed on the same page
$95.1M → 101.7M 2026-07-07 2026-07-07
Cost estimate $95.1M → 101.7M 2026-01-06 2026-07-07
Cost estimate
prior value printed on the same page
$92.7M → $101.7M 2026-10-06 2026-10-06
In-service date Q4 2030 → Q4 2026 2026-10-06 Not reported
In-service date Q4 2026 → Q4 2028 2024-10-08 2024-12-03
In-service date Q4 2028 → Q4 2030 2026-01-06 2026-07-07
Status conceptual (Conceptual) → engineering (Engineering) 2026-10-06 Not reported
Status engineering (Engineering) → conceptual (Conceptual) 2026-01-06 2026-07-07
Substations named ENON; HOPEWELL; MEADOWVILLE; SHAND CREEK; SYCAMORE SPRINGS → ALLIED; BERMUDA HUNDRED; ICI 2026-10-06 Not reported
Substations named ALLIED; BERMUDA HUNDRED; ICI → BERMUDA HUNDRED; CHICKAHOMINY; ENON; MEADOWVILLE; SYCAMORE SPRINGS 2024-10-08 2024-12-03
Substations named BERMUDA HUNDRED; CHICKAHOMINY; ENON; MEADOWVILLE; SYCAMORE SPRINGS → ENON; MEADOWVILLE; SYCAMORE SPRINGS 2024-12-03 2025-10-08
Substations named ENON; MEADOWVILLE; SYCAMORE SPRINGS → BERMUDA HUNDRED; CHICKAHOMINY; ENON; MEADOWVILLE; SHAND CREEK; SYCAMORE SPRINGS 2025-10-08 2026-01-06
Substations named BERMUDA HUNDRED; CHICKAHOMINY; ENON; MEADOWVILLE; SHAND CREEK; SYCAMORE SPRINGS → BERMUDA HUNDRED; CHICKAHOMINY; ENON; HOPEWELL; MEADOWVILLE; SHAND CREEK; SYCAMORE SPRINGS 2026-01-06 2026-07-07
Substations named BERMUDA HUNDRED; CHICKAHOMINY; ENON; HOPEWELL; MEADOWVILLE; SHAND CREEK; SYCAMORE SPRINGS → ENON; HOPEWELL; MEADOWVILLE; SHAND CREEK; SYCAMORE SPRINGS 2026-07-07 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2026 p. 48
Do No Harm Analysis “over duty breakers at existing Hopewell Substation”
2026-07-07 TEAC
Item 14 - DOM Supplemental Projects p. 15
Do No Harm Analysis “existing Hopewell Substation”
230kV
2025-12-08 TEAC
Item 11 - Reliability Analysis Update p. 20
Dominion Transmission Zone: Baseline Hopewell – Chesterfield – Basin 230 kV No role wording
230kV
2025-11-04 TEAC
Item 14 - Reliability Analysis Update p. 29
Hopewell – Chesterfield – Basin 230 kV No role wording
230kV
2025-10-08 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2025 p. 58
Do No Harm Analysis “existing Hopewell substation”
2025-05-06 TEAC
Item 09 - DOM Supplemental Projects p. 10
Do No Harm Analysis “existing Hopewell substation”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this