Substation Scout

Montour

Named in 4 PJM planning documents for 4 projects, from November 4, 2025 to September 8, 2026.

Existingdescribed as
PPLzone
230 kV, 230kVkV as printed
4mentions

PJM interconnection queue

A PJM queue substation page has the same name: Montour (PA) — 14 queue requests filed, 2 active.

Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
PPL Transmission Zone: Baseline MAAC PPL Cluster
b4029.1
Not printed $565.4M 6/1/2030 Not printed 2025-12-08
TEAC
Jerseytown, PA
PPL-2026-0001
Conceptual $109.2 M 05/30/2028 1,500 MW 2026-05-08
TEAC
Natalie 500-230kV Substation
PPL-2026-0029
Conceptual $408 M 12/30/2029 2,000 MW 2026-09-08
TEAC
MAAC PPL Cluster
2025-W1-558
Not printed $565.4M 6/1/2030 Not printed 2025-11-04
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date 5/2028 → 05/30/2028 2026-03-10 2026-05-08
In-service date 06/2028 → 12/30/2029 2026-04-07 2026-09-08

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08 TEAC
Item 07 - PPL Supplemental Projects p. 4
Natalie 500-230kV Substation “Install a 230kV line terminal”
230kV
2026-05-08 TEAC
Item 06 - PPL Supplemental Projects p. 8
Jerseytown, PA “Expanding the existing Montour 230kV switchyard was infeasible”
230kV
2025-12-08 TEAC
Item 11 - Reliability Analysis Update p. 28
PPL Transmission Zone: Baseline MAAC PPL Cluster No role wording
230 kV
2025-11-04 TEAC
Item 14 - Reliability Analysis Update p. 54
MAAC PPL Cluster No role wording
230 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this