Substation Scout

Morocco

Named in 1 PJM planning document for 1 project, on December 8, 2025.

Not stateddescribed as
ATSIzone
345 kVkV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Lallendorf Substation Upgrades for MISO Tranche 2.1
ATSI-2025-005
Conceptual $7.21 M 6/1/2032 Not printed 2025-12-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate $5.9 M → $7.21 M 2025-03-04 2025-12-08
Cost estimate $7.21 M → $7.21 2025-12-08 2026-10-06
Substations named LALLENDORF; LAPLAISANCE CREEK; MONROE → LALLENDORF 2025-02-04 2025-03-04
Substations named LALLENDORF → ALLEN JUNCTION; LALLENDORF; MOROCCO 2025-03-04 2025-12-08
Substations named ALLEN JUNCTION; LALLENDORF; MOROCCO → ALLEN JUNCTION; LALLENDORF 2025-12-08 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2025-12-08 TEAC
Item 04 - ATSI Supplemental Projects p. 7
Lallendorf Substation Upgrades for MISO Tranche 2.1 No role wording
345 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.