Elko Substation
Named in 5 PJM planning documents for 2 projects, from April 1, 2025 to October 6, 2026.
Existingdescribed as
APSzone
230 kV and 138 kV, 230/138 kVkV as printed
5mentions
Also printed as: Elko
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| Elko Substation APS-2024-037, PN-2024-015 |
Conceptual | $44.66 M | 12/13/2030 | Not printed | 2026-10-06 TEAC |
| Elko 230/138 kV Transformer APS-2025-012 · s3874.1 |
Not printed | $6.69M | 06/01/2028 | Not printed | 2026-10-06 TEAC |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-10-06 | TEAC Informational Only - APS Local Plan Submission of the Supplemental Projects for 2026 p. 43 |
Elko 230/138 kV Transformer | “At Elko Substation:
Replace No. 1 230/138 kV transformer” 230/138 kV |
| 2026-10-06 | TEAC Item 07 - APS Supplemental Projects - Presentation p. 7 |
Elko Substation | “At Elko Substation: Rebuild the 230 kV and 138 kV yards” 230 kV and 138 kV |
| 2026-09-28* | SRRTEP Western APS local plan submission of the supplemental projects for 2026 RTEP p. 43 |
Elko 230/138 kV Transformer | “At Elko Substation:
▪ Replace No. 1 230/138 kV transformer” 230/138 kV |
| 2025-12-08 | TEAC Item 05 - APS Supplemental Projects p. 6 |
Elko 230/138 kV Transformer | “At Elko Substation:
§ Replace No. 1 230/138 kV transformer” 230/138 kV |
| 2025-04-01 | TEAC Item 04 - APS Supplemental Projects p. 3 |
Elko 230/138 kV Transformer | No role wording 230/138 kV |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.