Substation Scout

Newton Falls 138/69 kV Substation

Named in 2 PJM planning documents for 1 project, on December 12, 2025.

Existingdescribed as
ATSIzone
138/69 kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Newton Falls 138/69 kV Substation
ATSI-2022-031
Conceptual $51.52M 12/21/2028 Not printed 2025-12-12
SRRTEP Western

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named BRIDGE; EVERGREEN; FRANKLIN; IVANHOE; NEWTON FALLS; OHIO STAR FORGE; WHITMAN → BRIDGE; EVERGREEN; FRANKLIN; IVANHOE; NEWTON FALLS; NEWTON FALLS 138; OHIO STAR FORGE; WHITMAN 2026-10-06 Not reported
Substations named BRIDGE; EVERGREEN; FRANKLIN; GM LORDSTOWN; HANNA; IVANHOE; NEWTON FALLS; NEWTON FALLS 138; OHIO STAR FORGE; WHITMAN → BRIDGE; EVERGREEN; FRANKLIN; IVANHOE; NEWTON FALLS; OHIO STAR FORGE; WHITMAN 2025-12-12 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-09-23* SRRTEP Western
ATSI local plan submission of the supplemental projects for 2026 RTEP p. 28
Newton Falls 138/69 kV Substation No role wording
138/69 kV
2025-12-12 SRRTEP Western
Item 13 - ATSI Supplemental Projects p. 7
Newton Falls 138/69 kV Substation “Convert Newton Falls Substation 138 kV yard into a six-breaker ring bus”
138/69 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.