Kelayres

Named in 3 PJM planning documents for 3 projects, from November 4, 2025 to January 6, 2026.

Newdescribed as
PPLzone
500/230 kVkV as printed
3mentions

Described as new: “new Kelayres” — source, page 28

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
PPL Transmission Zone: Baseline MAAC PPL Cluster
b4029.1
Not printed $565.4M 6/1/2030 Not printed 2025-12-08
TEAC
PPL Cluster
B4029.18
Not printed $4.5 M 6/1/2030 Not printed 2026-01-06
TEAC
MAAC PPL Cluster
2025-W1-558
Not printed $565.4M 6/1/2030 Not printed 2025-11-04
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate $4.5 M → $7.39M 2026-01-06 2026-05-08
Cost estimate
prior value printed on the same page
$4.50M → $7.39M 2026-05-08 2026-05-08
Substations named KELAYRES; SUSQUEHANNA → SUSQUEHANNA 2026-01-06 2026-05-08

Every mention

DateDocumentProjectWhat the document says about it
2026-01-06 TEAC
Item 09 - Reliability Analysis Update p. 17
PPL Cluster No role wording
500/230 kV
2025-12-08 TEAC
Item 11 - Reliability Analysis Update p. 28
PPL Transmission Zone: Baseline MAAC PPL Cluster “new Kelayres”
500/230 kV
2025-11-04 TEAC
Item 14 - Reliability Analysis Update p. 54
MAAC PPL Cluster “loop into the new Kelayres”
500/230 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.