Substation Scout

Mountaineer

Named in 2 PJM planning documents for 2 projects, from December 8, 2025 to January 6, 2026.

Existingdescribed as
PJM system-widezone
765 kV, 765kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
MAAC Regional Cluster: Baseline
b4036.1
Not printed $1789.39M 6/1/2032 Not printed 2026-01-06
TEAC
MAAC Regional Cluster: Baseline
2025-W1-237
Not printed $1738.6M 6/1/2031 Not printed 2025-12-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-01-06 TEAC
Item 09 - Reliability Analysis Update p. 22
MAAC Regional Cluster: Baseline “Upgrade the terminal equipment of Mountaineer 765kV”
765kV
2025-12-08 TEAC
Item 11 - Reliability Analysis Update p. 52
MAAC Regional Cluster: Baseline No role wording
765 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.