Elmont
Named in 17 PJM planning documents for 14 projects, from October 8, 2024 to October 6, 2026.
PJM interconnection queue
A PJM queue substation page has the same name: Elmont (VA) — 3 queue requests filed, 0 active.
Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| Dominion Transmission Zone: Baseline Second Chickahominy 500/230kV Transformer b3213 |
Not printed | $34.03M | 6/1/2023 | Not printed | 2026-04-07 TEAC |
| Dominion Transmission Zone: Baseline
500kV Line #557 Elmont-Chickahominy b3692 |
Not printed | $185.16 M | 6/30/2028 | Not printed | 2025-05-06 TEAC |
| Dominion Transmission Zone: Baseline New 765/500/230kV Yeat Substation B4000.355 – B4000.359 |
Not printed | $1,109.89M | 6/1/2029 | Not printed | 2026-05-08 TEAC |
| Regional Solution: 2025-W1-275 Portfolio b4053.1 |
Not printed | $4832.45 | 6/1/2032 | Not printed | 2026-01-06 TEAC |
| Thornburg 500/230kV Substation (Bypass Elmont & Possum Point 500kV) b4053.34 |
Not printed | $1M | 6/1/2032 | Not printed | 2026-10-06 TEAC |
| Pearsons Switch Replacement DOM-2022-0060 · s3060 |
Not printed | $0.5 M | 10/31/2023 | Not printed | 2024-10-08 TEAC |
| Dominion Transmission Zone: Supplemental Do No Harm Analysis DOM-2023-0016 · s3731 |
Engineering | $27 M | 05/31/2025 | 248.0 MW | 2026-10-06 TEAC |
| Do No Harm Analysis DOM-2023-0023 - DNH · s3990.2 |
Conceptual | $17.5M | 12/31/2031 | Not printed | 2026-10-06 TEAC |
| Dominion Transmission Zone: Supplemental
Do No Harm Analysis DOM-2024-0018 · s3673 |
Engineering | $20M Substation, $5M Transmission Line | Q4 2027 | 255.0 MW | 2025-10-08 TEAC |
| Stockholm 230kV Delivery - DEV DOM-2024-0049 · s3995 |
Conceptual | $ 26M | Q4 2028 | 300 MW | 2026-10-06 TEAC |
| Dominion Transmission Zone: Supplemental
Operational Flexibility and Efficiency DOM-2024-0051 · s3999 |
Engineering | $185M | 12/31/2030 | Not printed | 2026-10-06 TEAC |
| Flamingo 230kV Delivery - DEV DOM-2024-0058 |
Cancelled | $10M | 12/31/2029 | 47.0 MW | 2026-09-08 TEAC |
| Install 230 kV Conductor on North Anna to Bristers Structures DOM-2026-0022 |
Engineering | $33.75 M | Q4 2030 | 3000 MW | 2026-06-02 TEAC |
| Dominion Transmission Zone: Baseline Regional Solution: 2025-W1-275 Portfolio 2025-W1-275 |
Not printed | Not printed | 6/1/2032 | Not printed | 2025-12-08 TEAC |
Changes between documents
Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.
| What changed | Printed values | Earlier | Later |
|---|---|---|---|
| Cost estimate prior value printed on the same page |
$31.05M → $34.03M | 2026-04-07 | 2026-04-07 |
| Cost estimate prior value printed on the same page |
$58.155 M → $185.16 M | 2025-05-06 | 2025-05-06 |
| Cost estimate prior value printed on the same page |
$1,055.3 M → $1,109.89M | 2025-01-07 | 2025-01-07 |
| Cost estimate prior value printed on the same page |
$1,109.89M → $978.76 M | 2026-08-04 | 2026-08-04 |
| Cost estimate | $1,109.89M → $978.76 M | 2026-05-08 | 2026-08-04 |
| Substations named | BRISTERS; ELK RUN; JOSHUA FALLS; MEADOWBROOK; VINT HILL; YEAT → BRISTERS; CULPEPER YEAT; CUNNINGHAM; ELK RUN; ELMONT; JOSHUA FALLS; KRAKEN; MEADOWBROOK; MIDLOTHIAN; MORRISVILLE; MOSBY; NOKESVILLE; NORTH ANNA; POSSUM PT; SPOTSYLVANIA; VINT HILL; VONTAY; WISHING STAR; YEAT | 2025-01-07 | 2026-04-07 |
| Substations named | BRISTERS; CULPEPER YEAT; CUNNINGHAM; ELK RUN; ELMONT; JOSHUA FALLS; KRAKEN; MEADOWBROOK; MIDLOTHIAN; MORRISVILLE; MOSBY; NOKESVILLE; NORTH ANNA; POSSUM PT; SPOTSYLVANIA; VINT HILL; VONTAY; WISHING STAR; YEAT → ANDERSON BRANCH; BRISTERS; CULPEPER YEAT; ELK RUN; ELMONT; JOSHUA FALLS; KRAKEN; MEADOWBROOK; MORRISVILLE; MOSBY; NOKESVILLE; POSSUM PT; SPOTSYLVANIA; VINT HILL; VONTAY; WISHING STAR; YEAT | 2026-04-07 | 2026-05-08 |
| Substations named | ANDERSON BRANCH; BRISTERS; CULPEPER YEAT; ELK RUN; ELMONT; JOSHUA FALLS; KRAKEN; MEADOWBROOK; MORRISVILLE; MOSBY; NOKESVILLE; POSSUM PT; SPOTSYLVANIA; VINT HILL; VONTAY; WISHING STAR; YEAT → BRISTERS; CLOVERDALE; ELK RUN; JOSHUA FALLS; MEADOWBROOK; VINT HILL; YEAT | 2026-05-08 | 2026-08-04 |
| Cost estimate | $27.0 M → $450.0M | 2025-04-01 | 2026-06-02 |
| Cost estimate | $450.0M → $27 M | 2026-06-02 | 2026-10-06 |
| In-service date | 05/31/2025 → 07/01/2029 | 2025-04-01 | 2026-06-02 |
| In-service date | 07/01/2029 → 05/31/2025 | 2026-06-02 | 2026-10-06 |
| Substations named | ALLMAN; ELMONT; FOUR RIVERS; FREDERICKSBURG; KRAKEN; LADYSMITH; LADYSMITH CT; LEES HILL; N DOSWELL; NEW POST; PINEWOOD; RUTHER GLEN; ST JOHNS → ALLMAN; CHANCELLOR; ELMONT; FOUR RIVERS; FREDERICKSBURG; KRAKEN; LADYSMITH; LADYSMITH CT; LEES HILL; N DOSWELL; NEW POST; PINEWOOD; POSSUM POINT; RUTHER GLEN; ST JOHNS; THORNBURG | 2025-04-01 | 2026-06-02 |
| Substations named | ALLMAN; CHANCELLOR; ELMONT; FOUR RIVERS; FREDERICKSBURG; KRAKEN; LADYSMITH; LADYSMITH CT; LEES HILL; N DOSWELL; NEW POST; PINEWOOD; POSSUM POINT; RUTHER GLEN; ST JOHNS; THORNBURG → ALLMAN; ELMONT; FOUR RIVERS; FREDERICKSBURG; KRAKEN; LADYSMITH; LADYSMITH CT; NEW POST; PINEWOOD; POSSUM POINT; RUTHER GLEN; ST JOHNS; THORNBURG | 2026-06-02 | 2026-10-06 |
| In-service date | Q4 2027 → 12/01/2030 | 2025-01-07 | 2025-05-06 |
| In-service date | 12/01/2030 → Q4 2027 | 2025-05-06 | 2025-10-08 |
| Status | engineering (Engineering) → conceptual (Conceptual) | 2025-01-07 | 2025-05-06 |
| Status | conceptual (Conceptual) → engineering (Engineering) | 2025-05-06 | 2025-10-08 |
| Substations named | CHICKAHOMINY; ELMONT; THICKET; WHITE OAK → BERMUDA HUNDRED; CHICKAHOMINY; DARBYTOWN; ELKO; ELMONT; TECHPARK PLACE; THICKET; WHITE OAK | 2025-01-07 | 2025-05-06 |
| Substations named | STOCKHOLM; THICKET → CHICKAHOMINY; ELMONT; STOCKHOLM; THICKET; WHITE OAK | 2026-05-08 | 2026-10-06 |
| Cost estimate prior value printed on the same page |
$108M → $165M | 2026-06-02 | 2026-06-02 |
| Cost estimate | Transmission: $108M; Substation: $15M → $165M | 2025-06-05 | 2026-06-02 |
| Cost estimate | $165M → $185M | 2026-06-02 | 2026-10-06 |
| Status | conceptual (Conceptual) → engineering (Engineering) | 2025-06-05 | 2026-06-02 |
| Cost estimate | $20.0M Substation, $10M Transmission Lines → $10M | 2025-10-08 | 2026-09-08 |
| Status | engineering (Engineering) → cancelled (Canceled) | 2025-10-08 | 2026-09-08 |
| Substations named | FLAMINGO → ELMONT; FLAMINGO; SHORT PUMP | 2025-10-08 | 2026-09-08 |
| Substations named | BRISTERS; ELMONT; FREDERICKSBURG; NORTH ANNA; THORNBURG → BRISTERS; NORTH ANNA; THORNBURG | 2026-06-02 | 2026-10-06 |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-10-06 | TEAC Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2026 p. 102 |
Do No Harm Analysis | “Replace Elmont 500/230 kV TX #2 with new 1440 MVA TX” 500/230 kV |
| 2026-10-06 | TEAC Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2026 p. 51 |
Dominion Transmission Zone: Supplemental Do No Harm Analysis | No role wording |
| 2026-10-06 | TEAC Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2026 p. 60 |
Stockholm 230kV Delivery - DEV | No role wording |
| 2026-10-06 | TEAC Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2026 p. 69 |
Dominion Transmission Zone: Supplemental Operational Flexibility and Efficiency | No role wording |
| 2026-10-06 | TEAC Item 16 - Reliability Analysis Update - Presentation p. 9 |
Thornburg 500/230kV Substation (Bypass Elmont & Possum Point 500kV) | No role wording |
| 2026-09-08 | TEAC Item 10 - DOM Supplemental Projects p. 12 |
Flamingo 230kV Delivery - DEV | No role wording 230kV |
| 2026-09-08* | SRRTEP Southern Dominion p. 104 |
Pearsons Switch Replacement | No role wording |
| 2026-07-07 | TEAC Item 14 - DOM Supplemental Projects p. 7 |
Do No Harm Analysis | “Replace Elmont 500/230 kV TX #2” 500/230 kV |
| 2026-06-02 | TEAC Item 11 - DOM Supplemental Projects p. 12 |
Dominion Transmission Zone: Supplemental Operational Flexibility and Efficiency | No role wording |
| 2026-06-02 | TEAC Item 11 - DOM Supplemental Projects p. 7 |
Install 230 kV Conductor on North Anna to Bristers Structures | No role wording |
| 2026-06-02 | TEAC Item 11 - DOM Supplemental Projects p. 9 |
Dominion Transmission Zone: Supplemental Do No Harm Analysis | No role wording 230 kV |
| 2026-05-08 | TEAC Item 10 - Reliability Analysis Update p. 18 |
Dominion Transmission Zone: Baseline New 765/500/230kV Yeat Substation | No role wording |
| 2026-04-07 | TEAC Item 11 - Reliability Analysis Update p. 14 |
Dominion Transmission Zone: Baseline New 765/500/230kV Yeat Substation | No role wording 500kV |
| 2026-04-07 | TEAC Item 11 - Reliability Analysis Update p. 18 |
Dominion Transmission Zone: Baseline Second Chickahominy 500/230kV Transformer | No role wording 500kV |
| 2026-01-06 | TEAC Item 09 - Reliability Analysis Update p. 36 |
Regional Solution: 2025-W1-275 Portfolio | “Construct one (1) new 500kV line terminal position at the existing Elmont substation.” 500kV |
| 2025-12-08 | TEAC Item 11 - Reliability Analysis Update p. 82 |
Dominion Transmission Zone: Baseline Regional Solution: 2025-W1-275 Portfolio | “Construct one (1) new 500kV line terminal position at the existing Elmont substation.” 500kV |
| 2025-10-08 | TEAC Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2025 p. 57 |
Dominion Transmission Zone: Supplemental Do No Harm Analysis | No role wording |
| 2025-06-05 | TEAC Item 08 - DOM Supplemental Projects p. 10 |
Dominion Transmission Zone: Supplemental Operational Flexibility and Efficiency | No role wording |
| 2025-05-06 | TEAC Item 09 - DOM Supplemental Projects p. 8 |
Dominion Transmission Zone: Supplemental Do No Harm Analysis | No role wording |
| 2025-05-06 | TEAC Item 10 - Reliability Analysis Update p. 8 |
Dominion Transmission Zone: Baseline 500kV Line #557 Elmont-Chickahominy | No role wording |
| 2025-04-01 | TEAC Item 11 - DOM Supplemental Projects p. 16 |
Dominion Transmission Zone: Supplemental Do No Harm Analysis | No role wording |
| 2025-01-07 | TEAC Item 10 - Dominion Supplemental Projects p. 4 |
Dominion Transmission Zone: Supplemental Do No Harm Analysis | No role wording |
| 2024-10-08 | TEAC Informational Only - DOM Local Plan submission of supplemental projects 2024 p. 104 |
Pearsons Switch Replacement | No role wording |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.