Named in 1 PJM planning document for 1 project, on December 11, 2025.

Not stateddescribed as
DOMzone
—kV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Equipment Material Condition, Performance and Risk
DOM-2025-0085
Not printed Not printed 12/31/2029 Not printed 2025-12-11
SRRTEP Southern

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named CENTRAL → CENTRAL SUBSTATION TAP 2025-12-11 2026-03-18

Every mention

DateDocumentProjectWhat the document says about it
2025-12-11 SRRTEP Southern
Item 02 - DOM Supplemental Projects p. 3
Equipment Material Condition, Performance and Risk No role wording