Substation Scout

Montville

Named in 14 PJM planning documents for 12 projects, from October 8, 2024 to October 6, 2026.

Existingdescribed as
JCPLzone
230 kV, 230-34.5 kV, 34.5 kV, 500 kV, 500/230 kVkV as printed
17mentions

Also printed as: Montville Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
b2003 Cancellation: Whippany – Montville 230kV
b2003
Cancelled $37.5 M Not printed Not printed 2025-02-04
TEAC
Montville 500/230 kV Substation
b4032.1
Not printed $98.10 M 11/1/2029 Not printed 2026-01-06
TEAC
JCPL Transmission Zone M-3 Process Whippany, NJ/Montville, NJ/Greystone, NJ
JCPL-2019-024 · s3609.1
Not printed $20.1 M 06/11/2027 Not printed 2025-10-08
TEAC
Montville Substation
JCPL-2023-050 · s3258.1
Not printed $8.55M 04/01/2026 Not printed 2024-10-08
TEAC
Customer Connection
JCPL-2024-016 · s3336.1
Not printed $1.45M 06/30/2024 Not printed 2026-09-08*
SRRTEP Mid-Atlantic
Automatic Restoration Projects
JCPL-2024-050 and 052
Not printed Not printed Not printed Not printed 2024-12-12
SRRTEP Mid-Atlantic
Automatic Restoration Projects
JCPL-2024-052 · s3637.1
Not printed $0.15 M 07/05/2026 Not printed 2025-10-08
TEAC
Montville, NJ/Riverdale Substation, NJ
JCPL-2025-007
Not printed Not printed Not printed Not printed 2025-12-11
SRRTEP Mid-Atlantic
Montville - Whippany 34.5 kV D4 Line
JCPL-2026-014
Not printed Not printed Not printed Not printed 2026-04-14
SRRTEP Mid-Atlantic
Greystone Substation Breaker Replacements
JCPL-2026-045
Conceptual $9.71 M 12/15/2029 Not printed 2026-10-06
TEAC
Riverdale Substation, NJ
JCPL-2026-046
Not printed Not printed Not printed Not printed 2026-08-13
SRRTEP Mid-Atlantic
Montville Substation
2025-W1-140
Not printed $66.83 M 11/1/2029 Not printed 2025-11-04
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate $40.2 M → $20.1 M 2025-03-13 2025-10-08
Substations named HALSEY → HALSEY; MONTVILLE; WHIPPANY 2024-10-08 Not reported
Substations named FERNDALE; GILBERT; JACKSONVILLE TAP; MONTVILLE → GILBERT 2024-12-12 2026-08-13
Substations named CHILCOTT; DENVILLE; FOLL HILL; GREYSTONE; WEST DENVILLE → CHILCOTT; DENVILLE; FOLL HILL; GREYSTONE; MONTVILLE; MORRISTOWN; ROCKAWAY; WEST DENVILLE 2026-08-04 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Item 08 - JCPL Supplemental Projects - Presentation p. 5
Greystone Substation Breaker Replacements No role wording
34.5 kV
2026-09-08* SRRTEP Mid-Atlantic
JCPL local plan submission for 2025 RTEP p. 3
JCPL Transmission Zone M-3 Process Whippany, NJ/Montville, NJ/Greystone, NJ No role wording
2026-09-08* SRRTEP Mid-Atlantic
JCPL local plan submission for 2025 RTEP p. 35
Automatic Restoration Projects “Upgrade line protection at Montville Substation”
2026-09-08* SRRTEP Mid-Atlantic
JCPL local plan submission for 2024 RTEP p. 31
Montville Substation “Replace the 230-34.5 kV No. 3A and 3B transformers at Montville Substation”
230-34.5 kV
2026-09-08* SRRTEP Mid-Atlantic
JCPL local plan submission for 2024 RTEP p. 75
Customer Connection No role wording
34.5 kV
2026-08-13 SRRTEP Mid-Atlantic
Item 02 - JCPL Supplemental Projects p. 11
Riverdale Substation, NJ No role wording
34.5 kV
2026-04-14 SRRTEP Mid-Atlantic
Item 02 - JCPL Supplemental Projects p. 4
Montville - Whippany 34.5 kV D4 Line No role wording
34.5 kV
2026-01-06 TEAC
Item 09 - Reliability Analysis Update p. 16
Montville 500/230 kV Substation “At Montville Substation, install a 500 kV double-bus”
500/230 kV
2025-12-11 SRRTEP Mid-Atlantic
Item 08 - JCPL Supplemental Projects p. 3
Montville, NJ/Riverdale Substation, NJ No role wording
2025-11-04 TEAC
Item 14 - Reliability Analysis Update p. 27
Montville Substation “At Montville Substation, install a 500 kV three breaker ring bus”
500 kV
2025-10-08 TEAC
Informational Only - JCPL Local Plan Submission of the Supplemental Projects for 2025 p. 3
JCPL Transmission Zone M-3 Process Whippany, NJ/Montville, NJ/Greystone, NJ No role wording
34.5 kV
2025-10-08 TEAC
Informational Only - JCPL Local Plan Submission of the Supplemental Projects for 2025 p. 35
Automatic Restoration Projects “Upgrade line protection at Montville Substation”
34.5 kV
2025-04-10 SRRTEP Mid-Atlantic
Item 02 - JCPL Supplemental Projects p. 12
Automatic Restoration Projects “Upgrade line protection at Montville Substation”
2025-03-13 SRRTEP Mid-Atlantic
Item 05 - JCPL Supplemental Projects p. 9
JCPL Transmission Zone M-3 Process Whippany, NJ/Montville, NJ/Greystone, NJ No role wording
34.5 kV
2025-02-04 TEAC
Item 12 - Reliability Analysis Update p. 11
b2003 Cancellation: Whippany – Montville 230kV No role wording
230 kV
2024-12-12 SRRTEP Mid-Atlantic
Item 08 - JCPL Supplemental Projects p. 4
Automatic Restoration Projects No role wording
2024-10-08 TEAC
Informational Only - JCPL Local Plan submission of supplemental project 2024 p. 31
Montville Substation “Replace the 230-34.5 kV No. 3A and 3B transformers at Montville Substation with a single 168 MVA unit.”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this