Jarratt Substation

Named in 3 PJM planning documents for 1 project, from November 13, 2025 to October 6, 2026.

Existingdescribed as
DOMzone
115 kVkV as printed
3mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Jarratt 115kV Delivery – Upgrade TX#4 and Retire TX#3 - DEV
DOM-2025-0076 · s3833
Engineering $0.4M 6/30/2028 33 MW 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date 12/31/2026 → 6/30/2028 2025-11-13 2025-12-11

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2026 p. 12
Jarratt 115kV Delivery – Upgrade TX#4 and Retire TX#3 - DEV “upgrade TX #4 and retire TX #3 at Jarratt Substation”
115 kV
2025-12-11 SRRTEP Southern
Item 02 - DOM Supplemental Projects p. 8
Jarratt 115kV Delivery – Upgrade TX#4 and Retire TX#3 - DEV “upgrade TX #4 and retire TX #3 at Jarratt Substation”
2025-11-13 SRRTEP Southern
Item 07 - DOM Supplemental Projects p. 3
Jarratt 115kV Delivery – Upgrade TX#4 and Retire TX#3 - DEV “upgrade TX #4 and retire TX #3 at Jarratt Substation”
115 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.