Carpenter Technology Substation

Named in 7 PJM planning documents for 3 projects, from October 8, 2024 to October 6, 2026.

Existingdescribed as
METEDzone
69 kVkV as printed
9mentions

Also printed as: Carpenter Technology

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Carpenter Technology – South Reading 69 kV Line
ME-2019-043 · s3288.1
Not printed $15.2M 05/29/2026 Not printed 2024-10-08
TEAC
Muhlenberg 69 kV Substation
ME-2024-005 · s3976.1
Not printed $29.29M 10/22/2027 33 MW 2026-10-06
TEAC
Carpenter Technology Substation 69 kV Circuit Breaker
ME-2024-021 · s3974.1
Not printed $1.01 M 06/15/2027 Not printed 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named CARPENTER TECHNOLOGY; RIVERVIEW → CARPENTER TECHNOLOGY 2026-10-06 Not reported

Every mention

DateDocumentProjectWhat the document says about it
2026-10-07* SRRTEP Mid-Atlantic
Met-Ed local plan submission for 2026 RTEP p. 12
Carpenter Technology Substation 69 kV Circuit Breaker “The existing 69 kV breaker 83692 at Carpenter Technology Substation is over 50”
2026-10-07* SRRTEP Mid-Atlantic
Met-Ed local plan submission for 2026 RTEP p. 17
Muhlenberg 69 kV Substation “Revise relay settings at North Temple, Carpenter Technology, and Lucent substations.”
2026-10-06 TEAC
Informational Only - MetEd Local Plan Submission of Supplemental Projects for 2026 p. 12
Carpenter Technology Substation 69 kV Circuit Breaker “Replace Carpenter Technology 69 kV breaker 83692”
69 kV
2026-10-06 TEAC
Informational Only - MetEd Local Plan Submission of Supplemental Projects for 2026 p. 17
Muhlenberg 69 kV Substation “Revise relay settings at North Temple, Carpenter Technology, and Lucent substations”
2026-09-08* SRRTEP Mid-Atlantic
Met-Ed local plan submission for 2024 RTEP p. 13
Carpenter Technology – South Reading 69 kV Line “At Carpenter Technology Substation:  Replace 69 kV line-side disconnect and line relaying”
69 kV
2026-03-18 SRRTEP Mid-Atlantic
Item 07 - MetEd Supplemental Projects p. 8
Muhlenberg 69 kV Substation “Revise relay settings at North Temple, Carpenter Technology, and Lucent substations.”
69 kV
2025-12-11 SRRTEP Mid-Atlantic
Item 09 - MetEd Supplemental Projects p. 5
Carpenter Technology Substation 69 kV Circuit Breaker “The existing 69 kV breaker 83692 at Carpenter Technology Substation”
69 kV
2024-10-17 SRRTEP Mid-Atlantic
Item 05 - MetEd supplemental Projects p. 3
Carpenter Technology Substation 69 kV Circuit Breaker “The existing 69 kV breaker 83692 at Carpenter Technology Substation is over 50 years old”
69 kV
2024-10-08 TEAC
Informational Only - METED Local Plan submission of supplemental project 2024 p. 14
Carpenter Technology – South Reading 69 kV Line “At Carpenter Technology Substation: § Replace 69 kV line-side disconnect”
69 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this