Named in 2 PJM planning documents for 2 projects, from November 14, 2025 to December 12, 2025.

Not stateddescribed as
COMEDzone
138 kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Mendota-Sandwich 138 kV
b4025.1
Not printed $171.88 M 4/15/2030 Not printed 2025-12-12
SRRTEP Western
Mendota-Sandwich 138 kV Not printed $171.88 M 4/15/2030 Not printed 2025-11-14
SRRTEP Western

Every mention

DateDocumentProjectWhat the document says about it
2025-12-12 SRRTEP Western
Item 16 - SRRTEP West - Reliability Analysis Update p. 3
Mendota-Sandwich 138 kV No role wording
138 kV
2025-11-14 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 3
Mendota-Sandwich 138 kV No role wording
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.