Substation Scout

Nicktown

Named in 3 PJM planning documents for 2 projects, from December 11, 2025 to September 17, 2026.

Existingdescribed as
PENELECzone
46 kVkV as printed
3mentions

Also printed as: Nicktown Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Glory – Nanty Glo – Spangler 46 kV Line
PN-2024-022
Conceptual $13.81M 06/30/2028 11 MW 2025-12-11
SRRTEP Mid-Atlantic
Glory - Nanty Glo - Spangler 46 kV Line - Replace Line Switches
PN-2026-007
Conceptual $760,000 10/05/2027 Not printed 2026-09-17
SRRTEP Mid-Atlantic

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named BOBIK LANE; GLORY; MOSS CREEK; NANTY GLO; NICKTOWN; SPANGLER; STRONGSTOWN; TEAKETTLE → BOBIK LANE; GLORY; NANTY GLO; SPANGLER; STRONGSTOWN 2025-12-11 2026-10-06
Substations named GLORY; MOSS CREEK; NANTY GLO; NICKTOWN; SPANGLER; TEAKETTLE → NICKTOWN 2026-06-16 2026-09-17

Every mention

DateDocumentProjectWhat the document says about it
2026-09-17 SRRTEP Mid-Atlantic
Item 03 - Penelec Supplemental Projects p. 7
Glory - Nanty Glo - Spangler 46 kV Line - Replace Line Switches “Replace the obsolete 46 kV switches A-111, A-112 & A-113 at Nicktown Substation”
46 kV
2026-06-16 SRRTEP Mid-Atlantic
Item 04 - Penelec Supplemental Projects p. 6
Glory - Nanty Glo - Spangler 46 kV Line - Replace Line Switches No role wording
46 kV
2025-12-11 SRRTEP Mid-Atlantic
Item 10 - PENELEC Supplemental Projects p. 8
Glory – Nanty Glo – Spangler 46 kV Line No role wording
46 kV