Reeves Ave

Named in 3 PJM planning documents for 1 project, from November 4, 2025 to October 6, 2026.

Existingdescribed as
DOMzone
—kV as printed
3mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Dominion Transmission Zone: Supplemental Hibie St - New 230 kV Delivery - DEV
DOM-2025-0011 · s3834
Engineering $3.56M 12/31/2027 29.8 MW 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named HIBIE ST; REEVES AVE → HIBIE ST; REEVES AVE; THRASHER 2025-11-04 2025-12-08

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2026 p. 6
Dominion Transmission Zone: Supplemental Hibie St - New 230 kV Delivery - DEV “distribution circuits from Reeves Ave cross underneath the Elizabeth River”
2025-12-08 TEAC
Item 10 - DOM Supplemental Projects p. 5
Dominion Transmission Zone: Supplemental Hibie St - New 230 kV Delivery - DEV No role wording
2025-11-04 TEAC
Item 13 - DOM Supplemental Projects p. 6
Dominion Transmission Zone: Supplemental Hibie St - New 230 kV Delivery - DEV No role wording

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.