Substation Scout

Black River

Named in 9 PJM planning documents for 4 projects, from October 8, 2024 to July 17, 2026.

Existingdescribed as
ATSIzone
138 kV, 69 kVkV as printed
9mentions

Also printed as: Black River Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
ATSI Transmission Zone M-3 Process Lorain, Ohio
ATSI-2024-029 · s3455.1
Not printed $0.40 M 6/2/2025 Not printed 2024-10-08
TEAC
Black River – Shinrock 69 kV Line
ATSI-2024-072
Conceptual $67.65M 12/31/2029 Not printed 2026-07-17
SRRTEP Western
Black River - Johnson West 69 kV Switches
ATSI-2025-011 · s3719.1
Not printed $1.66M 12/31/2026 Not printed 2025-10-08
TEAC
Black River - Willow Creek 69 kV
ATSI-2025-035
Conceptual $1.53M 12/31/2026 Not printed 2025-12-12
SRRTEP Western

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named AXTEL; BAUMHART; BLACK RIVER; SHINROCK; WASHINGTON → AXTEL; BAUMHART; BLACK RIVER; GREENFIELD; SHINROCK; WASHINGTON 2024-10-18 2026-07-17
Substations named AXTEL; BAUMHART; BLACK RIVER; GREENFIELD; SHINROCK; WASHINGTON → SHINROCK 2026-07-17 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
ATSI local plan submission of the supplemental projects for 2024 RTEP p. 87
ATSI Transmission Zone M-3 Process Lorain, Ohio “Adjust protection setting at Black River, Republic Arc, and Republic Vine substations.”
138 kV
2026-09-08* SRRTEP Western
ATSI local plan submission of the supplemental projects for 2025 RTEP p. 51
Black River - Johnson West 69 kV Switches No role wording
69 kV
2026-07-17 SRRTEP Western
Item 03 - ATSI Supplemental Projects p. 26
Black River – Shinrock 69 kV Line “The section from Str. 244=41 to Black River Substation will not be reconductored due to being reconductored recently.”
69 kV
2025-12-12 SRRTEP Western
Item 13 - ATSI Supplemental Projects p. 17
Black River - Willow Creek 69 kV No role wording
69 kV
2025-10-08 TEAC
Informational Only - ATSI Local Plan Submission of the Supplemental Projects for 2025 p. 51
Black River - Johnson West 69 kV Switches No role wording
69 kV
2025-06-13 SRRTEP Western
Item 05 - ATSI Supplemental Projects p. 5
Black River - Johnson West 69 kV Switches No role wording
69 kV
2025-03-14 SRRTEP Western
Item 05 - ATSI Supplemental Project p. 4
Black River - Johnson West 69 kV Switches No role wording
2024-10-18 SRRTEP Western
Item 04 - ATSI Supplemental Projects p. 3
Black River – Shinrock 69 kV Line No role wording
69 kV
2024-10-08 TEAC
Informational Only - ATSI Local Plan submission of supplemental project 2024 p. 88
ATSI Transmission Zone M-3 Process Lorain, Ohio “Adjust protection setting at Black River, Republic Arc, and Republic Vine substations.”
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this