Thrasher

Named in 4 PJM planning documents for 3 projects, from December 3, 2024 to October 6, 2026.

Not stateddescribed as
DOMzone
230kVkV as printed
4mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
500kV Line #579 Rebuild (End of Life Criteria)
b3929.1
Not printed $216.78 M 6/1/2029 Not printed 2025-01-07
TEAC
Dominion Transmission Zone: Supplemental Hibie St - New 230 kV Delivery - DEV
DOM-2025-0011 · s3834
Engineering $3.56M 12/31/2027 29.8 MW 2026-10-06
TEAC
500kV Line #579 Rebuild (End of Life Criteria)
DOM-O1
Not printed $216.78 M 6/1/2029 Not printed 2024-12-03
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named HIBIE ST; REEVES AVE → HIBIE ST; REEVES AVE; THRASHER 2025-11-04 2025-12-08

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2026 p. 7
Dominion Transmission Zone: Supplemental Hibie St - New 230 kV Delivery - DEV No role wording
2025-12-08 TEAC
Item 10 - DOM Supplemental Projects p. 6
Dominion Transmission Zone: Supplemental Hibie St - New 230 kV Delivery - DEV No role wording
2025-01-07 TEAC
Item 12 - Reliability Analysis Update p. 54
500kV Line #579 Rebuild (End of Life Criteria) No role wording
230kV
2024-12-03 TEAC
Item 11 - Reliability Analysis Update p. 74
500kV Line #579 Rebuild (End of Life Criteria) No role wording
230kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.