Beech Branch

Named in 2 PJM planning documents for 1 project, from May 14, 2026 to October 6, 2026.

Not stateddescribed as
DOMzone
115kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
115 kV Mayo Dunbar DP Modification – EMC-EMC
DOM-2025-0022 · s3913
Under construction $1.9M 5/31/2026 9.2 MW 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named MAYO DUNBAR DP → BEECH BRANCH; COOL SPRINGS; MAYO DUNBAR DP 2025-09-18 2026-05-14
Substations named BEECH BRANCH; COOL SPRINGS; MAYO DUNBAR DP → BEECH BRANCH; COOL SPRINGS 2026-05-14 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2026 p. 97
115 kV Mayo Dunbar DP Modification – EMC-EMC No role wording
2026-05-14 SRRTEP Southern
Item 04 - DOM Supplemental Projects p. 4
115 kV Mayo Dunbar DP Modification – EMC-EMC No role wording
115kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.