Named in 3 PJM planning documents for 3 projects, from October 17, 2025 to May 15, 2026.

Existingdescribed as
AEPzone
69 kVkV as printed
3mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Falcon 69 kV Capacitor Bank Installation
b3951.1
Not printed $3.35 M 04/15/2030 Not printed 2025-11-14
SRRTEP Western
Falcon 69 kV Capacitor Bank Installation Not printed $3.35 M 04/15/2030 Not printed 2025-10-17
SRRTEP Western
Falcon, KY
AEP-2026-AP002
Not printed Not printed Not printed Not printed 2026-05-15
SRRTEP Western

Every mention

DateDocumentProjectWhat the document says about it
2026-05-15 SRRTEP Western
Item 01 - AEP Supplemental Projects p. 6
Falcon, KY “Falcon Station is in Salyersville, KY. Falcon station is constructed with deteriorated wood tie foundations”
2025-11-14 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 38
Falcon 69 kV Capacitor Bank Installation “Falcon station will need to be expanded to fit the capacitor bank. (b3951.1)”
69 kV
2025-10-17 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 33
Falcon 69 kV Capacitor Bank Installation “Falcon station will need to be expanded”
69 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.