Frackville

Named in 10 PJM planning documents for 9 projects, from April 1, 2025 to October 6, 2026.

Existingdescribed as
PPLzone
230kV, 69kVkV as printed
18mentions

PJM interconnection queue

A PJM queue substation page has the same name: Frackville (PA) — 3 queue requests filed, 0 active.

Same name and state (weaker). Matched on name and state: the utility that presented this substation operates in one state, and every queue filing at a substation of the same name is in that state. No transmission owner is recorded on those filings, so this is a weaker match than one on owner. Not verified as the same facility.

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Frackville, PA
PPL-2019-0004
Conceptual $45 M 06/30/2028 Not printed 2026-10-06
TEAC
Hauto, PA
PPL-2025-0002
Conceptual $101 M 05/30/2028 350 MW 2025-04-01
TEAC
Gordon, PA
PPL-2025-0008
Conceptual $231.65 M 05/30/2028 600MW 2026-10-06
TEAC
Girardville, PA
PPL-2025-0016
Conceptual $0.7 M 02/28/2027 Not printed 2026-10-06
TEAC
Fountain Springs, PA
PPL-2025-0028
Conceptual $1.6 M 11/30/2028 Not printed 2026-10-06
TEAC
PPL Transmission Zone: Supplemental Port Carbon, PA
PPL-2026-0026
Conceptual $7.2 M 11/30/2028 Not printed 2026-10-06
TEAC
Natalie 500-230kV Substation
PPL-2026-0029
Conceptual $408 M 12/30/2029 2,000 MW 2026-09-08
TEAC
Frackville 230kV yard
PPL-2026-0040
Conceptual $36.3 M 05/30/2029 750 MW 2026-10-06
TEAC
Lansford Tap
PPL-2026-0042
Conceptual $1.9 M 12/01/2029 Not printed 2026-09-17
SRRTEP Mid-Atlantic

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date 05/2027 → 05/30/2028 2025-03-04 2025-04-01
In-service date 05/2027 → 5/30/2027 2025-05-06 2025-10-08
In-service date 5/30/2027 → 05/30/2028 2025-10-08 2026-10-06
In-service date 11/2028 → 11/30/2028 2025-12-11 2026-02-12
Substations named FOUNTAIN SPRINGS → FOUNTAIN SPRINGS; FOUNTAIN SPRINGS CREEK; FRACKVILLE 2025-12-11 2026-02-12
Substations named FOUNTAIN SPRINGS; FOUNTAIN SPRINGS CREEK; FRACKVILLE → FOUNTAIN SPRINGS; FOUNTAIN SPRINGS CREEK; FRACKVILLE; MOWRY 2026-02-12 2026-10-06
Substations named PORT CARBON → FRACKVILLE; ORWIGSBURG; PORT CARBON 2026-03-18 2026-05-14
In-service date 06/2028 → 12/30/2029 2026-04-07 2026-09-08
In-service date 05/2029 → 05/30/2029 2026-08-04 2026-10-06
Substations named LANSFORD → FRACKVILLE; LANSFORD; SIEGFRIED 2026-08-13 2026-09-17

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Item 12 - PPL Supplemental Projects - Presentation p. 9
Frackville 230kV yard “Frackville 230kV Yard • Install three BAAH 230kV bays with an 80MVAR Capacitor bank.”
230kV
2026-10-06 TEAC
Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2026 p. 25
Gordon, PA “Install one new 230kV breaker, 230kV dead-end, and ancillary equipment in bay #3 at Frackville 230kV Yard”
230kV
2026-10-06 TEAC
Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2026 p. 39
Fountain Springs, PA No role wording
2026-10-06 TEAC
Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2026 p. 4
Frackville, PA No role wording
2026-10-06 TEAC
Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2026 p. 73
PPL Transmission Zone: Supplemental Port Carbon, PA No role wording
2026-10-06 TEAC
Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2026 p. 9
Girardville, PA No role wording
2026-09-17 SRRTEP Mid-Atlantic
Item 04 - PPL Supplemental Projects p. 13
Lansford Tap No role wording
69kV
2026-09-17* SRRTEP Mid-Atlantic
PPL local plan submission for 2026 RTEP p. 25
Gordon, PA “Install one new 230kV breaker, 230kV dead-end, and ancillary equipment in bay #3 at Frackville 230kV Yard”
230kV
2026-09-17* SRRTEP Mid-Atlantic
PPL local plan submission for 2026 RTEP p. 39
Fountain Springs, PA No role wording
69kV
2026-09-17* SRRTEP Mid-Atlantic
PPL local plan submission for 2026 RTEP p. 4
Frackville, PA No role wording
69kV
2026-09-17* SRRTEP Mid-Atlantic
PPL local plan submission for 2026 RTEP p. 73
PPL Transmission Zone: Supplemental Port Carbon, PA No role wording
69kV
2026-09-17* SRRTEP Mid-Atlantic
PPL local plan submission for 2026 RTEP p. 9
Girardville, PA “existing Frackville-Siegfried 2 69kV line”
69kV
2026-09-08 TEAC
Item 07 - PPL Supplemental Projects p. 4
Natalie 500-230kV Substation “Install a 230kV line terminal and one 230kV breaker”
230kV
2026-05-14 SRRTEP Mid-Atlantic
Item 08 - PPL Supplemental Projects p. 16
PPL Transmission Zone: Supplemental Port Carbon, PA No role wording
69kV
2026-02-12 SRRTEP Mid-Atlantic
Item 05 - PPL Supplemental Projects p. 14
Fountain Springs, PA “Frackville 69kV Substation”
69kV
2025-10-08 TEAC
Item 09 - PPL Supplemental Projects p. 6
Gordon, PA “Install one new 230kV breaker, 230kV dead-end, and ancillary equipment in bay #3 at Frackville 230kV Yard”
230kV
2025-06-12 SRRTEP Mid-Atlantic
Item 04 - PPL Supplemental Projects p. 4
Frackville, PA No role wording
69kV
2025-04-01 TEAC
Item 07 - PPL Supplemental Projects p. 6
Hauto, PA “Install additional 69kV terminals at Frackville 69kV yard”
69kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.