Cradock Substation

Named in 3 PJM planning documents for 1 project, from October 16, 2025 to October 6, 2026.

Existingdescribed as
DOMzone
115kVkV as printed
3mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Cradock 115kV Delivery – DEV
DOM-2025-0080 · s3998
Engineering $0.33M 04/30/2027 71.4 MW 2026-10-06
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2026 p. 65
Cradock 115kV Delivery – DEV “upgrade currently installed TX#2 (with 33.6 MVA rating) at Cradock Substation”
115kV
2026-05-14 SRRTEP Southern
Item 04 - DOM Supplemental Projects p. 5
Cradock 115kV Delivery – DEV “upgrade currently installed TX#2 (with 33.6 MVA rating) at Cradock Substation”
2025-10-16 SRRTEP Southern
Item 08 - DOM Supplemental Projects p. 5
Cradock 115kV Delivery – DEV “upgrade currently installed TX#2 (with 33.6 MVA rating) at Cradock Substation to 56 MVA”