West Milton

Named in 3 PJM planning documents for 2 projects, from February 3, 2026 to May 8, 2026.

Existingdescribed as
DAYTONzone
138 kVkV as printed
3mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Dayton-2025-007 Conceptual $591.5M June 30th, 2032 1400 MW 2026-05-08
TEAC
Dayton Transmission Zone M-3 Process
Dayton-2025-009
Conceptual $25.8M 12/31/2029 300 MW 2026-03-19
SRRTEP Western

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date 03/2030 → 12/31/2029 2025-10-08 2026-02-03
Substations named AIRPORT → AIRPORT; UNION; WEST MILTON 2025-10-08 2026-02-03

Every mention

DateDocumentProjectWhat the document says about it
2026-05-08 TEAC
item 05 - Dayton Supplemental Projects p. 4
Dayton-2025-007 “Cutin the existing 138 kV transmission line from West Milton”
138 kV
2026-03-19 SRRTEP Western
Item 06 - Dayton Supplemental Projects p. 4
Dayton Transmission Zone M-3 Process “Remote end work at West Milton and Airport 138 kV substations”
138 kV
2026-02-03 TEAC
Item 06 - Dayton Supplemental Projects p. 9
Dayton Transmission Zone M-3 Process “Remote end work at West Milton and Airport 138 kV substations.”
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.